Why it keeps happening

Why it keeps happening

Three things we can measure in the data. None of them proves a cause on its own, but each points at a different kind of infrastructure problem.

Indicator 1
0Dry
overflows spilling with no rain to excuse it

A discharge in dry weather is not an exceptional circumstance, so it is not permitted on any reading of regulation 4.

See the 0 →
Indicator 2
0Overloaded
works whose estimated load sits above their permitted flow

A strong signal, not a finding. We cannot see whether flow is transferred to another works for treatment, and the permitted figure is not always published.

See the 0 →
Indicator 3
24Early
overflows that spilled while their works stayed shut

Rainfall across the catchment does not explain a discharge that an overflow's own treatment works did not share.

See the 24 →

Where the indicators concentrate

OverflowHoursDryWhat it points toVerdict
Thrale Road113Spills before its worksNo action
Streatham & Balham Storm Relief920Spills before its worksNo action
Dorking Road (tadworth) pumping station520Spills before its worksNo action
Streatham Storm Relief E380Spills before its worksNo action
Streatham Storm Relief A290Spills before its worksNo action
Streatham Storm Relief B260Spills before its worksNo action
Streatham & Balham Storm Relief210Spills before its worksNo action
Frogmore Storm130Spills before its worksNo action
Streatham Vale Storm Relief70Spills before its worksNo action
Bell Lane Creek20Spills before its worksNo action

Hours are the last full year; dry spills are since 2020. Verdict is whether a measure is linked to the overflow — see the gaps.

What this analysis cannot see

These indicators are measured from spill timing and rainfall alone. They cannot see misconnections, the quality of effluent from a works that is running normally, flow transferred between works for treatment, a company's maintenance history, or the periods when a monitor was offline. Because a quiet monitor records nothing, every count here is a floor, not a total.