Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

30
Measures in this catchment
WINEP, current record
30
Still active
not yet past their date
0
Assumed complete
completion date has passed
7
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08TW100034 · aWFD_INV_WRFlowInvestigation
Further phase of investigation
Waddon and Brantwood Road Sources investigation
Due 2026-27Wandle (Croydon to Wandsworth) and the Graveney
08TW100107 · aWFD_NDLS_Chem2No deterioration
Beddington STW, Nonylphenol, 0.69 ug
Reduce Nonylphenol loading
Due 2026-27Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · twEnvAct_INV4Investigation
Storm Overflows investigation
Bell Lane Creek- Storm Overflows investigation
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · tuEnvAct_INV4Investigation
Storm Overflows investigation
Frogmore Storm- Storm Overflows investigation
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · edEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at BEDDINGTON STW
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · fjEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at CANTERBURY ROAD, THORNTON HEATH CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · jmEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at CHURCH ROAD UNPERMITTED CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · dzEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at DUNTSHILL ROAD CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · duEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at GAP ROAD (CEMETERY) CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · ktEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at HOME PARK ROAD UNPERMITTED CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · lbEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at LEVERSON STREET UNPERMITTED CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · dtEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at LONGLEY ROAD (1), TOOTING HIGH STREET CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · dsEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at MAPLETON ROAD CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · dvEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at PENWITH ROAD CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · efEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at ROAD A217, BURGH HEATH CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · mfEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at SOMERSET ROAD, WIMBLEDON UNPERMITTED CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · ifEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at STREATHAM STORM RELIEF CSO A
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · dyEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at STREATHAM STORM RELIEF CSO B
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · igEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at STREATHAM STORM RELIEF CSO E
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · eaEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at STREATHAM VALE STORM RELIEF CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · mlEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at THRALE ROAD UNPERMITTED CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · jlEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at TREE TOPS, NORBURY UNPERMITTED CSO
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
08TW101108 · vbEnvAct_INV4Investigation
Storm Overflows investigation
Streatham & Balham Storm Relief B- Storm Overflows investigation
Due 2027-28Wandle (Croydon to Wandsworth) and the Graveney
09TW100007 · aWFD_IMP_WRHMWBImprovement
Implement a solution to make the impeding structure passable/easable to fish
Beddington Park Weir 1 Fish Pass
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney
09TW100008 · aWFD_IMP_WRHMWBImprovement
Implement a solution to make the impeding structure passable/easable to fish
Beddington Park Weir 2 Fish Pass
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney
08TW101096 · aENVAct_IMP2Improvement
Investigation and Solution in AMP 8: UPM - Improved by Streatham Storm Relief CSO B
Storm Overflows action at STREATHAM STORM RELIEF CSO A
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney
08TW101064 · aENVAct_IMP2Improvement
Investigation and Solution in AMP 8: UPM - This option is an interception of spill from CSO A and diverting partial flow to a new 1700m3 storage. The storage will support the betterment of CSO A as well as CSO B.
Storm Overflows action at STREATHAM STORM RELIEF CSO B
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney
08TW101097 · aENVAct_IMP2Improvement
Investigation and Solution in AMP 8: UPM - New 100m3 storage immediately after CSO weir and the flow to discharged back to the system with 25l/s pump at DWF using a real time control (RTC)
Storm Overflows action at STREATHAM STORM RELIEF CSO E
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney
08TW101065 · aENVAct_IMP2Improvement
Investigation and Solution in AMP 8: UPM - Diversion of a short section of pipeline and CSO refurbishment
Storm Overflows action at STREATHAM VALE STORM RELIEF CSO
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney
09TW100014 · aWFD_IMP_WRHMWBImprovement
Implement a river restorations schmeme to promote natural morphological processes
Wandle (Beddington Park) River Restoration Scheme
Due 2029-30Wandle (Croydon to Wandsworth) and the Graveney

30 of 30 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.