Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.

The Storm Overflows Discharge Reduction Plan covers England only. The River Usk is in Wales, which sets its own storm overflow targets. The figures below still show how often each overflow spills against its own baseline and against 10 spills a year, but that cap is England’s. Welsh annual returns start in 2022, so the baseline here is each overflow’s 2022 figure, not 2020.

What the plan is, and what it leaves out

The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:

  • By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
  • By 2045 — the remaining high-priority overflows.
  • By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.

The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the EDM record: each overflow's counted spills per year — the standard 12/24-hour block figure, the same basis the cap is written in — against its 2022 baseline (the first Welsh annual return) and the 2050 cap of ~10, with the deadline its location implies.

34
Above the 2050 cap
of 52 tracked
21
Rising since baseline
trend is the wrong way
0
On a 2035 deadline
near a bathing water
18
Within the cap
≤10 spills in 2025

Every overflow against its cap

Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.

OverflowDeadlineBaselineLatestSince baselinevs capTrajectoryVerdict
Castell Coch Overflow
DCWW1021
205086 ·22
152
0 events
+77%15.2×Rising
Trecastle Wwtw Storm Overflow
DCWW663
205041 ·22
149
0 events
+263%14.9×Rising
Malpas Road Storm Overflow
DCWW1883
2050123 ·22
136
0 events
+11%13.6×Rising
Sennybridge Wwtw Storm Overflow
DCWW771
2050107 ·22
117
0 events
+9%11.7×Rising
Forge Hammer Storm Overflow
DCWW1291
205036 ·22
92
0 events
+156%9.2×Rising
Christchurch Wwtw Storm Overflow
DCWW1761
2050168 ·22
75
0 events
-55%7.5×Falling — behind
Underwood Storm Overflow
DCWW1516
205094 ·22
72
0 events
-23%7.2×Falling — behind
Pill North Storm Overflow
DCWW808
205072 ·22
69
0 events
-4%6.9×Falling — behind
Pill South Storm Overflow
DCWW510
205072 ·22
66
0 events
-8%6.6×Falling — behind
Canal Road Brecon Storm Overflow
DCWW98
205045 ·22
66
0 events
+47%6.6×Rising
Caravan Park Clydach Storm Overflow
DCWW668
205068 ·22
61
0 events
-10%6.1×Falling — behind
Sennybridge Storm Overflow
DCWW1734
20505 ·22
53
0 events
+960%5.3×Rising
Mill Lane Usk Overflow
DCWW335
205040 ·22
48
0 events
+20%4.8×Rising
King Street Brynmawr Storm Overflow
DCWW921
205041 ·22
44
0 events
+7%4.4×Rising
Great Oak Wwtw Storm Overflow
DCWW1533
205061 ·22
44
0 events
-28%4.4×Falling — behind
Llangynidr Coed-yr-ynys Storm Overflow
DCWW258
205043 ·22
43
0 events
0%4.3×Falling — behind
Llanover Close Newport Overflow
DCWW1497
205038 ·22
39
0 events
+3%3.9×Rising
Rowan Way Storm Overflow
DCWW1103
205029 ·22
37
0 events
+28%3.7×Rising
Legar Storm Overflow
DCWW1233
205085 ·22
32
0 events
-62%3.2×Falling — behind
Little Mill Storm Overflow
DCWW911
205026 ·22
32
0 events
+23%3.2×Rising
St. Julians Avenue Newport Storm Overflow
DCWW755
205031 ·22
31
0 events
0%3.1×Falling — behind
East of Brecon Wwtw Storm Overflow
DCWW404
20500 ·22
25
0 events
—2.5×Rising
Pilton Vale Storm Overflow
DCWW509
205029 ·22
24
0 events
-17%2.4×Falling — behind
Field West of Brecon Wwtw Storm Overflow
DCWW2040
205047 ·22
23
0 events
-51%2.3×Falling — behind
Horrocks Close Woodlands Storm Overflow
DCWW575
205025 ·22
19
0 events
-24%1.9×Falling — behind
Brynglas Road Storm Overflow
DCWW2173
205016 ·22
19
0 events
+19%1.9×Rising
Barrack Hill Road Storm Overflow
DCWW707
205010 ·22
19
0 events
+90%1.9×Rising
Brodawel Storm Storm Overflow
DCWW2377
20500 ·22
16
0 events
—1.6×Rising
Wavell Drive Storm Overflow
DCWW2045
205014 ·22
16
0 events
+14%1.6×Rising
Talybont Cattle Market Storm Overflow
DCWW465
20504 ·22
15
1 events
+275%1.5×Rising
Chepstow Road 1 Storm Overflow
DCWW430
20502 ·22
14
0 events
+600%1.4×Rising
Bettws Lane Storm Overflow
DCWW1578
20507 ·22
13
0 events
+86%1.3×Rising
Crickhowell Wwtw Storm Overflow
DCWW631
2050149 ·22
13
0 events
-91%1.3×Nearly there
Maple Close Storm Overflow
DCWW551
20508 ·22
11
0 events
+38%1.1×Rising
Crickhowell Garn 1 Storm Overflow
DCWW415
205012 ·22
10
0 events
-17%1×Within the cap
Robertson Way Storm Overflow
DCWW1414
205042 ·22
10
0 events
-76%1×Within the cap
Hartridge Newport Storm Overflow
DCWW1647
20505 ·22
9
0 events
+80%0.9×Within the cap
Shaftesbury Park Storm Overflow
DCWW481
205013 ·22
8
0 events
-38%0.8×Within the cap
Allt-yr-yn Avenue Newport Overflow
DCWW1656
20505 ·22
8
0 events
+60%0.8×Within the cap
West of Barton Bridge Storm Overflow
DCWW826
20500 ·22
7
0 events
—0.7×Within the cap
Limestone Road Storm Overflow
DCWW914
20500 ·22
5
1 events
—0.5×Within the cap
Bridge Street Crickhowell Storm Overflow
DCWW2048
20501 ·22
3
0 events
+200%0.3×Within the cap
Heol Gouesnou Storm Overflow
DCWW2231
20504 ·22
2
0 events
-50%0.2×Within the cap
Brynawelon Storm Overflow
DCWW439
20506 ·22
2
1 events
-67%0.2×Within the cap
Church Street Roundabout Storm Overflow
DCWW1939
20500 ·22
2
0 events
—0.2×Within the cap
Howe Circle Storm Overflow
DCWW927
20502 ·22
2
0 events
0%0.2×Within the cap
Cwrt Bryn Derwen Storm Overflow
DCWW75
20500 ·22
1
0 events
—0.1×Within the cap
Crai Wwtw Storm Overflow
DCWW634
20506 ·22
1
0 events
-83%0.1×Within the cap
Crickhowell Garn 2 Storm Overflow
DCWW997
20501 ·25
1
1 events
0%0.1×—Within the cap
Cold Bath Lane Storm Overflow
DCWW2039
205058 ·24
0
0 events
-100%0×—Within the cap
Treberth Crescent Storm Overflow
DCWW433
20501 ·22
0
0 events
-100%0×Within the cap
Caerleon Storm Overflow
DCWW672
205067 ·22
0
0 events
-100%0×Within the cap

What this is — and what it is not

This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2022 baseline and the 10/year cap. Counted spills use the standard 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →