What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100107a · 09d48433 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ABERBAIDEN STW BEHIND HOP YARD FARM | Complete 2025-26 | Aberbaiden WwTW Inlet Storm Overflow |
| DCWW100137a · c739038e | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BRECON | Complete 2025-26 | Brecon WwTW Storm Overflow |
| DCWW100142a · da1e8470 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BRYNMAWR BLACKROCK | Complete 2025-26 | Brynmawr Blackrock WwTW Storm Overflow |
| DCWW100072a · 9296c11f | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BWLCH SOUTH | Complete 2025-26 | Bwlch WwTW Storm Overflow |
| DCWW100178a · 8359809a | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CRICKHOWELL | Complete 2025-26 | Crickhowell WwTW Storm Overflow |
| DCWW100220a · 87a74341 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ GOYTRE WWTW (NR PONTYPOOL) | Complete 2025-26 | Goytre WwTW Storm Overflow |
| DCWW100241a · 86e9b9fd | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LITTLE MILL STW MONKSWOOD USK | Complete 2025-26 | Little Mill WwTW Overflow |
| DCWW100266a · f9665742 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANFOIST WWTW | Complete 2025-26 | Llanfoist WwTW Storm Overflow |
| DCWW100278a · cbb5b50e | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANGYBI (S OF USK) | Complete 2025-26 | Llangybi WwTW Storm Overflow |
| DCWW100316a · 3787ba9f | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ NASH STW WEST NASH ROAD NEWPORT | Complete 2025-26 | Nash WwTW Storm Overflow |
| DCWW100355a · 4784c425 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ RAGLAN STW CHEPSTOW ROAD RAGLAN | Complete 2025-26 | Raglan WwTW Storm Overflow |
| DCWW100095a · 1a75cd6e | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ SENNYBRIDGE ARMY CAMP | Complete 2025-26 | Sennybridge WwTW Storm Overflow |
| DCWW100379a · dd5b497e | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ TALYBONT SEWAGE TREATMENT WORKS TAL | Complete 2025-26 | Talybont WwTW Storm Overflow |
| DCWW100404a · 7a0fc960 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ USK STW GRAIG OLWAY FARM LLANGVIEW | Complete 2025-26 | Usk WwTW Storm Overflow |
| DCWW102850a · 145105c6 | W_WFD_WRHMWB_INV1 | Investigation | Investigation and appraisal of options to determine the impact of abstraction on achievement of good ecological potential (GEP) in an Artificial or Heavily Modified Water Body (for water resources uses). WR Crai | Due 2026-27 | Water body only |
| DCWW102119a · 31b1f5bb | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CRICKHOWELL GARN 1 SPS EOF | Due 2026-27 | Crickhowell Garn 1 Storm Overflow |
| DCWW101531a · c309f802 | W_FISH_IMP1 | Improvement | Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage. Fish Fish Barrier Mitigation at asset 41097297 | Due 2026-27 | Water body only |
| DCWW101666a · 32151d8b | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. WQ GREAT OAK | Due 2026-27 | Water body only |
| DCWW102621a · 6dbc71f9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LIMESTONE ROAD | Due 2026-27 | Limestone Road Storm Overflow |
| DCWW102117a · ad3fd679 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANFRYNACH STW | Due 2026-27 | Llanfrynach WwTW Storm Overflow |
| DCWW102639a · c443fe2f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ MAGOR PS CSO | Due 2026-27 | Magor Storm Overflow |
| DCWW102187a · 6e5fcb55 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ SHAFTESBURY PARK NEWPORT | Due 2026-27 | Shaftesbury Park Storm Overflow |
| DCWW102891a · 5aeb823f | W_WFD_PG_IMP1 | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PG_IMP and associated PR19 driver paper WQ CAERWENT (7CDC1092) | Due 2027-28 | Water body only |
| DCWW100641a · abf8f117 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ TALYBONT-ON-USK | Due 2027-28 | Talybont WwTW Storm Overflow |
| DCWW101582a · 06a9a749 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ 11 Robertson Way CSO, Newport | Due 2029-30 | Horrocks Close Woodlands Storm Overflow |
| DCWW101582a · 5fabdd7d | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ 27 Wavell Drive CSO | Due 2029-30 | Horrocks Close Woodlands Storm Overflow |
| DCWW100833a · d728430d | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ A SPS, CAERLEON TOWN SEWAGE PUMPING STATION, CASTLE MEWS, CAERLEON, NEWPORT, NP18 1BY | Due 2029-30 | Caerleon Storm Overflow |
| DCWW100820a · 53d8b18e | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ A SPS, RESIDENTIAL DEVELOPMENT OFF NEWGATE STREET, LLANFAES, BRECON, LD3 8DF | Due 2029-30 | Water body only |
| DCWW100819a · a6af4924 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ A SPS, RESIDENTIAL DEVELOPMENT OFF PRINCE CHARLES ROAD, RAGLAN, NP 15 2FB | Due 2029-30 | Water body only |
| DCWW101769b · 0f67843d | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ ABER STW | Due 2029-30 | Water body only |
| DCWW101769a · ef137b07 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ ABER VILLAGE | Due 2029-30 | Water body only |
| DCWW101760a · 9abeeb6f | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ ABERBAIDEN STW | Due 2029-30 | Water body only |
| DCWW102229a · 751ebdcb | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ABERBAIDEN STW STORM AT INLET | Due 2029-30 | Aberbaiden WwTW Inlet Storm Overflow |
| DCWW100789a · df4cdfd9 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Bettws Lane SPS, Bettws, Newport NP20 7AZ | Due 2029-30 | Bettws Lane Storm Overflow |
| DCWW100658a · 69d54a34 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ BRECON | Due 2029-30 | Brecon WwTW Storm Overflow |
| DCWW101917a · cd3e1904 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Brecon - East STW Dorlangoch | Due 2029-30 | East of Brecon WwTW Storm Overflow |
| DCWW101920a · 7e65450f | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Brecon Main Pumping Station SPS | Due 2029-30 | Canal Road Brecon Storm Overflow |
| DCWW101582a · 7f5c7cf6 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Brecon Supermarket CSO | Due 2029-30 | Canal Road Brecon Storm Overflow |
| DCWW101582a · 48af137c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Bridge St CSO | Due 2029-30 | Bridge Street Crickhowell Storm Overflow |
| DCWW101582a · 24289573 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Brodawel - Sennybridge | Due 2029-30 | Brodawel Storm Storm Overflow |
| DCWW101761a · 05cf01ea | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ BRYN SEWAGE TREATMENT WORKS BRYN MONM | Due 2029-30 | Water body only |
| DCWW101582a · b1124733 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Brynawel Estate, Trecastle CSO | Due 2029-30 | Brynawelon Storm Overflow |
| DCWW102339a · aa64fead | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BRYNMAWR OPPOSITE BRIDGE END INN | Due 2029-30 | King Street Brynmawr Storm Overflow |
| DCWW101461a · 20f1cebe | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Brynmawr SPS Emergency Overflow, Brynmawr, Ebbw Vale, Blaenau Gwent, NP23 4SH | Due 2029-30 | King Street Brynmawr Storm Overflow |
| DCWW101704b · de0d4412 | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ BWLCH (S) STW | Due 2029-30 | Water body only |
| DCWW101704a · 43ac725c | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ BWLCH S STW | Due 2029-30 | Water body only |
| DCWW101453a · 1e1f1fb2 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Caerleon (Usk Road) PS | Due 2029-30 | Usk road Caerleon Storm Overflow |
| DCWW100703a · 00305aa8 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Caerleon (Usk Road) PS | Due 2029-30 | Caerleon Storm Overflow |
| DCWW101582a · 64cb7701 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Caerleon Town Sewage Pumping Station | Due 2029-30 | Caerleon Storm Overflow |
| DCWW101582a · 27e8265a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CAERLEON WWTW (STW) CSO CAERLEON | Due 2029-30 | Cold Bath Lane Storm Overflow |
| DCWW100739a · 61a02975 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CAPEL-ED FIELS RESIDENTIAL DEVELOPMENT PUMPING STATION, PENPERLLENI, PONTYPOOL | Due 2029-30 | Water body only |
| DCWW101582a · 12bd785f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Chepstsow Road CSO | Due 2029-30 | Chepstow Road 2 Storm Overflow |
| DCWW102555a · 3dc637c5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Christchurch STW Overflow SO | Due 2029-30 | Christchurch WwTW Storm Overflow |
| DCWW100733a · 11262e6d | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CHURCH FARM RESIDENTIAL DEVMT PS | Due 2029-30 | Water body only |
| DCWW102678a · 906d079a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CHURCH STREET NEWPORT | Due 2029-30 | Church Street Roundabout Storm Overflow |
| DCWW101873a · cdb6713f | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ COEDWAUNGAER | Due 2029-30 | Water body only |
| DCWW100817a · 378f3f77 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CORPORATION ROAD, LISWERRY, NEWPORT | Due 2029-30 | Liswerry Storm Overflow |
| DCWW100816a · ff5dee10 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CORPORATION ROAD, LISWERRY, NEWPORT | Due 2029-30 | Junction of Chepstow Road & Somerton Road Storm Overflow |
| DCWW101871a · e0bb1546 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ CRADOC | Due 2029-30 | Water body only |
| DCWW100779a · 6cdb98e0 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CRADOC PUMPING STATION | Due 2029-30 | Water body only |
| DCWW100471a · 3220cd3e | W_WFD_WRHMWB_IMP1 | Improvement | Implementation of actions to mitigate impacts of abstraction and achieve Good ecological potential GEP in Artificial or Heavily Modified Water Bodies. This usually follows investigation in the previous AMP but not necessarily. WR Crai | Due 2029-30 | Water body only |
| DCWW101582a · e8d5e48e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Cray Sewage Treatment Works | Due 2029-30 | Crai WwTW Storm Overflow |
| DCWW101582a · 34918e1b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CRICKHOWELL - BRIDGE END CAR P | Due 2029-30 | Crickhowell Garn 2 Storm Overflow |
| DCWW100747a · bec4ff26 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CRICKHOWELL - BRIDGE END CAR PARK PS | Due 2029-30 | Crickhowell Garn 2 Storm Overflow |
| DCWW101582a · dbe07b5d | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Crickhowell - Bullpit Meadow S CSO | Due 2029-30 | Bullpit Meadow Storm Overflow |
| DCWW101582a · 92f4470a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CRICKHOWELL CSO | Due 2029-30 | Crickhowell Garn 1 Storm Overflow |
| DCWW101715b · 5a05faa2 | W_HR_AMM_T_IMP1 | Improvement | Operational costs relating to Ammonia permit condition
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ Crickhowell STW | Due 2029-30 | Water body only |
| DCWW101715a · 344dfec0 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ CRICKHOWELL STW | Due 2029-30 | Water body only |
| DCWW100760a · 66d2c18d | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Croesllanfro PS Rogerstone (adj to 13 Bala Lane, Uplands) | Due 2029-30 | Water body only |
| DCWW101874a · e6c0e957 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ CROSS OAK (NR TALYBONTONUSK) | Due 2029-30 | Water body only |
| DCWW101463a · 7352e285 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CSO & EO AT SENNYBRIDGE VILLAGE SPS | Due 2029-30 | Sennybridge Storm Overflow |
| DCWW101582a · 24a9d542 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO and EO at Sennybridge Village SPS | Due 2029-30 | Sennybridge Storm Overflow |
| DCWW101582a · 4baee170 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Newport Chepstow Road Near No589 | Due 2029-30 | Chepstow Road 1 Storm Overflow |
| DCWW101582a · 4192d6e9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Howe Circle | Due 2029-30 | Howe Circle Storm Overflow |
| DCWW101582a · 8ba1a765 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO AT NEWPORT PILLMAWR RD RELIEF SEW | Due 2029-30 | Pillmawr Road Storm Overflow |
| DCWW101868a · 24354fc5 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ CWMDU | Due 2029-30 | Water body only |
| DCWW100837a · 33f347af | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Dan y Gollen SPS, Crickhowell, Powys | Due 2029-30 | Dan-y-Gollen Overflow |
| DCWW101751a · a259c2c0 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ DEVAUDEN STW | Due 2029-30 | Water body only |
| DCWW101530a · ea138ad4 | W_FISH_IMP1 | Improvement | Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage. Fish Fish Barrier Mitigation at asset 40280307 | Due 2029-30 | Water body only |
| DCWW100815a · c3d5488c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ GARN PUMPING STATION, CRICKHOWELL, POWYS | Due 2029-30 | Crickhowell Garn 1 Storm Overflow |
| DCWW101753a · b0ab365e | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ GREAT OAK | Due 2029-30 | Water body only |
| DCWW102238a · 944172a3 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Great oak STW Overflow SO | Due 2029-30 | Great Oak WwTW Storm Overflow |
| DCWW101762a · 35a7074d | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ GROESFFORDD STW | Due 2029-30 | Water body only |
| DCWW100758a · 232eacdd | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ HAND FARM MEADOWS PUMPING STATION, NEW INN, PONTYPOOL | Due 2029-30 | Water body only |
| DCWW101582a · 454fa733 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Hartridge Farm SPS | Due 2029-30 | Hartridge Newport Storm Overflow |
| DCWW100811a · c98d0215 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ HARTRIDGE FARM SPS, LANE ON R/BOUT NR HARTRIDGE FARM, NEWPORT,NP18 | Due 2029-30 | Hartridge Newport Storm Overflow |
| DCWW100732a · 1de7b557 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ HEOL FELIN/RUTH ROAD PUMPING STATION | Due 2029-30 | Water body only |
| DCWW101943a · d3317aa8 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ HUXLEY GREEN CSO, Newport | Due 2029-30 | South Of Huxley Green Rear Storm Overflow |
| DCWW100734a · be95616b | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LADYHILL PUMPING STATION, USK | Due 2029-30 | Cwrt Bryn Derwen Storm Overflow |
| DCWW101465a · a4edf8e3 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Land off Tredillon Road, Abergavenny | Due 2029-30 | Water body only |
| DCWW101582a · 94504e41 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Legar CSO | Due 2029-30 | Legar Storm Overflow |
| DCWW101932a · 2dea25a3 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Legar CSO, Crickhowell | Due 2029-30 | Legar Storm Overflow |
| DCWW101582a · 9982baa5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Liswerry Rd/Aberthaw Rd Newport , | Due 2029-30 | Liswerry Road Storm Overflow |
| DCWW100671a · f2f30a1b | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LITTLE MILL | Due 2029-30 | Water body only |
| DCWW101757b · c2979b36 | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ LITTLE MILL STW | Due 2029-30 | Water body only |
| DCWW101757a · 1ee01f58 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LITTLE MILL STW MONKSWOOD USK | Due 2029-30 | Water body only |
| DCWW101754a · 085af167 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANARTH STW LLANARTH MONMOUTHSHIRE | Due 2029-30 | Water body only |
| DCWW100537a · b64c784b | W_BW_IMP3 | Improvement | Schemes to implement W_BW_INV4 (non-designated waters) BW Llandegfedd | Due 2029-30 | Water body only |
| DCWW101763a · c38e97c9 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANELLEN STW | Due 2029-30 | Water body only |
| DCWW101763b · 306c8f4e | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ LLANELLEN STW | Due 2029-30 | Water body only |
| DCWW101764a · 967a1771 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANFAIR SEWAGE TREATMENT WORKS | Due 2029-30 | Water body only |
| DCWW101872a · 95e841ff | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANFIHANGEL NANT BRAN (N OF SENNYBRI | Due 2029-30 | Water body only |
| DCWW102858b · 0ca85bd3 | W_HR_AMM_T_IMP1 | Improvement | Operational costs relating to Ammonia permit condition
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ LLANFOIST WASTEWATER TREATMENT WORKS | Due 2029-30 | Water body only |
| DCWW100673a · d6362a57 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANFOIST WWTW | Due 2029-30 | Llanfoist WwTW Storm Overflow |
| DCWW101765a · 240d5e58 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANGIBBY STW | Due 2029-30 | Water body only |
| DCWW101765b · ada4206e | W_HR_AMM_T_IMP1 | Improvement | Operational costs relating to Ammonia permit condition
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ LLANGYBI SEWAGE TREATMENT WORKS | Due 2029-30 | Water body only |
| DCWW101582a · 5bc76594 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llangybi STW Llangybi Usk Settled Storm | Due 2029-30 | Llangybi WwTW Storm Overflow |
| DCWW101582a · a93bfef9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llangynidr (Coed-yr-Ynys) SPS | Due 2029-30 | Llangynidr Coed-Yr-Ynys Storm Overflow |
| DCWW100746a · 2ccbd8d9 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANGYNIDR P.S. - OVERFLOW | Due 2029-30 | Llangynidr Coed-Yr-Ynys Storm Overflow |
| DCWW101766b · 4a16699c | W_HR_AMM_T_IMP1 | Improvement | Operational costs relating to Ammonia permit condition
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ LLANOVER STW | Due 2029-30 | Water body only |
| DCWW101766a · 28ed59fc | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANOVER STW | Due 2029-30 | Water body only |
| DCWW101767a · a25ddacc | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANSPYDDID STW | Due 2029-30 | Water body only |
| DCWW102692a · 5edb85af | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Lodge Road CSO Caerleon | Due 2029-30 | Lodge Road Storm Overflow |
| DCWW101582a · 1b780acb | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Maesygwartha SPS and CSO | Due 2029-30 | Water body only |
| DCWW100702a · 4598b267 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Maesygwartha SPS and CSO, Gilwern, Monmouthshire NP7 0HA | Due 2029-30 | Forge Hammer Storm Overflow |
| DCWW100825a · 3bf063bd | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MAGOR SEWAGE PUMPING STATION, MAGOR STW SITE, MAGOR, NEWPORT | Due 2029-30 | Magor Storm Overflow |
| DCWW101468a · 6b6200b2 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MALPAS PARK/ROWAN WAY PS, MALPAS, NEWPORT | Due 2029-30 | Pilton Vale Storm Overflow |
| DCWW101582a · 6354e08c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Maple Close CSO, Underwood | Due 2029-30 | Maple Close Storm Overflow |
| DCWW101916a · 09ccf2c9 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ MILL STREET CASTLE MEADOWS | Due 2029-30 | Mill Street Castle Meadows Storm Overflow |
| DCWW102342a · fa20ecc7 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT BARRACK HILL LOWER END | Due 2029-30 | Barrack Hill Road Storm Overflow |
| DCWW102317a · 85f9ac74 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT BETTWS LANE PS | Due 2029-30 | Bettws Lane Storm Overflow |
| DCWW102309a · 72515ecd | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT BRYNGLAS ROAD NO 33 | Due 2029-30 | Brynglas Road Storm Overflow |
| DCWW102560a · 6db07685 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT LISWERRY PILL PS | Due 2029-30 | Liswerry Storm Overflow |
| DCWW102566a · 977f906b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT MALPAS PARK PS (ROWAN WAY PS) | Due 2029-30 | Rowan Way Storm Overflow |
| DCWW102233a · 97c90524 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT NASH STW STORM | Due 2029-30 | Nash WwTW Storm Overflow |
| DCWW102567a · 1b612dc1 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEWPORT ST JULIANS ROAD OPPOSITE NO 1 | Due 2029-30 | St. Julians Avenue Newport Storm Overflow |
| DCWW101875a · 0779624c | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ PENCELLI (SE OF BRECON) | Due 2029-30 | Water body only |
| DCWW101876a · 5341d246 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ PENNORTH & SCETHROG | Due 2029-30 | Water body only |
| DCWW101582a · 76f14254 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Pill North PS North Octopus Rdbt | Due 2029-30 | Pill North Storm Overflow |
| DCWW101582a · d21fa54b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Pill South B Pumping Station | Due 2029-30 | Pill South Storm Overflow |
| DCWW100762a · f58744b4 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PRIORY DRIVE SPS, PRIORY DRIVE, LANGSTONE, NEWPORT | Due 2029-30 | Water body only |
| DCWW101582a · 8995a72b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ R/O 228 Pilton Vale CSO, Newport | Due 2029-30 | Pilton Vale Storm Overflow |
| DCWW102230a · 47070c06 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RAGLAN STW STORM | Due 2029-30 | Raglan WwTW Storm Overflow |
| DCWW100701a · b54b1b97 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ROBERTSON WAY/WOODLAND PS, MALPAS, NEWPORT | Due 2029-30 | Horrocks Close Woodlands Storm Overflow |
| DCWW101938a · fd54f1bd | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Sennybridge Army Camp CSO, Sennybridge | Due 2029-30 | Sennybridge WwTW Storm Overflow |
| DCWW101582a · aa3d33bc | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ SOMERTON ROAD BALMORAL ROAD CSO NEW | Due 2029-30 | Somerton Road Storm Overflow |
| DCWW102661a · f2749688 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ST CADOCS CHURCH CSO, RAGLAN | Due 2029-30 | West of Barton Bridge Storm Overflow |
| DCWW101582a · 493942e2 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ St Cadocs Hospital CSO | Due 2029-30 | St. Cadoc's Hospital Storm Overflow |
| DCWW101582a · c858ef59 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Talybont Across from Cattle Market CSO | Due 2029-30 | Talybont Cattle Market Storm Overflow |
| DCWW102252a · 0a614c67 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ TALYBONT STW STORM | Due 2029-30 | Talybont WwTW Storm Overflow |
| DCWW101761b · fee9bd02 | W_HR_AMM_T_IMP1 | Improvement | Operational costs relating to Ammonia permit condition
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ The Bryn | Due 2029-30 | Water body only |
| DCWW100836a · 974eac4f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ The Manor SPS, Newport Road, Llantarnam, Cwmbran, NP44 3AQ | Due 2029-30 | Water body only |
| DCWW100853a · 053be5b2 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ THE SHIP INN PUB CAR PARK OUTFALL, LULWORTH RD, CAERLEON | Due 2029-30 | Caerleon Storm Overflow |
| DCWW101582a · 476fe0b5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Treberth Estate CSO | Due 2029-30 | Treberth Crescent Storm Overflow |
| DCWW101922a · b4c24b19 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Trecastle SWK | Due 2029-30 | Trecastle WwTW Storm Overflow |
| DCWW101869a · bdca8f5a | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ TRELLEC SEWAGE TREATMENT WORKS | Due 2029-30 | Water body only |
| DCWW101870a · 543ab5fb | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ TRETOWER | Due 2029-30 | Water body only |
| DCWW101918a · 0b6eb785 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Underwood SPS | Due 2029-30 | Underwood Storm Overflow |
| DCWW100704a · 1236ab16 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Underwood SPS, Underwood, Newport | Due 2029-30 | Underwood Storm Overflow |
| DCWW100782a · 66d015f8 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ UNDY PUMPING STATION, NEAR CHURCH ROAD, UNDY, GWENT | Due 2029-30 | Water body only |
| DCWW102534a · e37f2d2c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ USK PS | Due 2029-30 | Mill Lane Usk Overflow |
| DCWW102689a · b26f38e9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ USK RAILWAY COTTAGE | Due 2029-30 | Cwrt Bryn Derwen Storm Overflow |
| DCWW101582a · b5c591b0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Usk Road PS Usk Road Caerleon | Due 2029-30 | Usk road Caerleon Storm Overflow |
| DCWW101750b · 88ad9db6 | W_HR_AMM_T_IMP1 | Improvement | Operational costs relating to Ammonia permit condition
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ USK STW | Due 2029-30 | Water body only |
| DCWW101750a · a2931fb0 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ USK STW GRAIG OLWAY | Due 2029-30 | Water body only |
| DCWW102231a · f800a244 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ USK STW STORM | Due 2029-30 | Water body only |
| DCWW100808a · 6ec443fd | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ USK VIEW PUMPING STATION, MERTHYR ROAD, LLANFOIST | Due 2029-30 | Water body only |
| DCWW101582a · d02aab28 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Woodlands (Horrocks Close) SPS | Due 2029-30 | Horrocks Close Woodlands Storm Overflow |
| DCWW100606a · 7b79a241 | W_U_IMP7(a-e) | Improvement | Upgrade septic tank primary treated effluent to secondary treated effluent capable of delivering 40/60 BOD/SS Biological Oxygen Demand: Suspended Soilids WQ WOODSIDE No 2, Usk Septic Tank | Due 2029-30 | Water body only |
| DCWW100607a · cdcc9076 | W_U_IMP7(a-e) | Improvement | Upgrade septic tank primary treated effluent to secondary treated effluent capable of delivering 40/60 BOD/SS Biological Oxygen Demand: Suspended Soilids WQ WOODSIDE, Usk Septic Tank | Due 2029-30 | Water body only |
160 of 160 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.