Before the works
An overflow that spills while its own treatment works stays shut is not being overwhelmed by rain — the problem is upstream of the works, and local.
If the sewer network were genuinely overwhelmed by rainfall, the treatment works' own storm overflow would be discharging too.
When an upstream overflow spills on a day its works did not, the works still had capacity — so the discharge points to a blockage, a failed pump, or infiltration on that branch, not to a works too small for its catchment. That changes who pays and how fast: a branch fault is maintenance, chargeable now, not a capital scheme waiting for the next five-year price review.
| Overflow | Events | Its works | On record |
|---|---|---|---|
| Myddfai Storm Overflow | 3 | Myddfai | Measure linked |
| Alltwallis Overflow | 2 | Alltwallis | Measure linked |
| Old Station Road Storm Overflow | 2 | Carmarthen STW | Measure linked |
| Carmarthen Sticle Footpath Storm Overflow | 2 | Carmarthen STW | Measure linked |
| Tanerdy Storm Overflow | 2 | Carmarthen STW | Measure linked |
| Old Llansteffan Road Carmarthen Storm Overflow | 2 | Carmarthen STW | Measure linked |
| Manordeilo Overflow | 1 | Llangadog | No measure |
| Llangain Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Pothouse Wharf Storm Overflow | 1 | Carmarthen STW | Measure linked |
| South of Roundabout A40 A485 Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Croes Y Ceiliog Overflow | 1 | Carmarthen STW | Measure linked |
| Llandeilo of Station Road Storm Overflow | 1 | Ffairfach Wwtw Ffairfach Carms STW | Measure linked |
| Llandeilo Yscubor Abad North Storm Overflow | 1 | Ffairfach Wwtw Ffairfach Carms STW | No measure |
| Job's Well Road Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Ferryside Storm Overflow | 1 | Ferryside | No measure |
| Pontargothi Overflow | 1 | Nantgaredig | Measure linked |
| Llangain Pwntan Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Pont Cynwyl Storm Overflow | 1 | Conwyl Elfed | Measure linked |
| Abergorlech Storm Overflow | 1 | Abergorlech | Measure linked |
| Morfa Lane Carmarthen Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Old Priory Road Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Peniel Overflow | 1 | Carmarthen STW | Measure linked |
| Llansadwrn Storm Overflow | 1 | Llangadog | Measure linked |
| Russell Terrace Storm Overflow | 1 | Carmarthen STW | Measure linked |
| Ashfield Llangadog Storm Overflow | 1 | Llangadog | Measure linked |
| Cynghordy Storm Overflow | 1 | Cynghordy | No measure |
What this needs to be reliable
The comparison needs both monitors working. Where a works' own overflow monitor was offline we record no result rather than a pre-works spill, so this is a floor. A treatment works itself is excluded — it is the end of the line and cannot spill before the works. Two works in the catchment have no monitored overflow at all, so their upstream overflows are listed as not assessed, not as clean.