Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

107
Measures in this catchment
NEP, current record
93
Still active
not yet past their date
14
Assumed complete
completion date has passed
28
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100138a · 1eca6af3W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BRICKYARD LANE
Complete 2025-26Brickyard Lane Storm Overflow
DCWW100186a · 8a6a03daW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CWM IFOR STW MANORDEI
Complete 2025-26Cwm Ifor WwTW Storm Overflow
DCWW100191a · 21e935c5W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CYNWYL ELFED
Complete 2025-26Cynwyl Elfed WwTW Storm Overflow
DCWW100206a · 83b6c15aW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
FERRYSIDE STW FERRYSIDE CARMS
Complete 2025-26Ferryside Near Railway Track WwTW Storm Overflow
DCWW100207a · 1719230aW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
FFAIRFACH STW
Complete 2025-26Ffairfach WwTW Storm Overflow
DCWW100250a · c175ab3bW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANDOVERY WASTEWATER TREATMENT
Complete 2025-26Llandovery WwTW Storm Overflow
DCWW100086a · a2ac6aa7W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANFYNYDD STW
Complete 2025-26Llanfynydd WwTW Storm Overflow
DCWW100267a · 9ebfcb7aW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANFYRNACH WWTW LLANFYRNACH PEMBS
Complete 2025-26Llangadog WwTW Storm Overflow
DCWW100268a · 19308174W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANGADOG STW
Complete 2025-26Llangadog WwTW Storm Overflow
DCWW100284a · aad8d930W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANPUMSAINT
Complete 2025-26Llanpumpsaint WwTW Storm Overflow
DCWW100289a · eb195964W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANSAINT WWTW LLANSAINT FERRYSIDE
Complete 2025-26Llansaint WwTW Storm Overflow
DCWW100291a · cd5449fcW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANSTEPHAN STW
Complete 2025-26Llansteffan WwTW Overflow
DCWW100341a · d6c29e81W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PONT-AR-GOTHI & NANTGAREDIG WWTW
Complete 2025-26Pont-ar-gothi & Nantgaredig WwTW Storm Overflow
DCWW100353a · 6c91ff1aW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PWNTAN LLANGAIN SPS
Complete 2025-26Llangain Pwntan Storm Overflow
DCWW100140a · e2141f8fW_U_MON4Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows
WQ
BRONWYDD (NR CARMARTHEN) STW
Due 2026-27Bronwydd WwTW Storm Overflow
DCWW100139a · b949e524W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BRONWYDD (NR CARMARTHEN) STW
Due 2026-27Bronwydd WwTW Storm Overflow
DCWW102193a · 1239caf8W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen - Towy Works CSO
Due 2026-27Carmarthen Bridge Storm Overflow
DCWW102192a · 53bdb9ccW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARMARTHEN POTHOUSE WHARF PS
Due 2026-27Pothouse Wharf Storm Overflow
DCWW100685a · f73455ffW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
FFAIRFACH
Due 2027-28Ffairfach WwTW Storm Overflow
DCWW100647a · 9c050f07W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
FFAIRFACH
Due 2027-28Ffairfach WwTW Storm Overflow
DCWW100637a · 9b8fea6aW_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
NANTGAREDIG
Due 2027-28Pont-ar-gothi & Nantgaredig WwTW Storm Overflow
DCWW100925a · 2203c783W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERGORLECH PUMPING STATION
Due 2029-30Abergorlech Storm Overflow
DCWW101820a · 487b7b32W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
ABERGORLECH WASTEWATER TREATMENT WORK
Due 2029-30Water body only
DCWW100972a · d4e99765W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERGWILI PS NEAR RUGBY FIELD
Due 2029-30South of Roundabout A40 A485 Storm Overflow
DCWW100985a · 56038406W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ALBION P.S.
Due 2029-30Albion Near Railway Crossing Storm Overflow
DCWW100928a · e0728a6fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ALLTWALIS SPS
Due 2029-30Alltwallis Overflow
DCWW101056a · d13fada5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ASHFIELD ROW PUMPING STATION, ASHFIELD ROW, LLANGADOG
Due 2029-30Ashfield Llangadog Storm Overflow
DCWW100920a · 6b391deaW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BRECHFA STW
Due 2029-30Brechfa Overflow
DCWW101814a · d753b132W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
BRECHFA STW
Due 2029-30Water body only
DCWW102568a · a31b7c42W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Brickyard Lane SPS EO
Due 2029-30Brickyard Lane Storm Overflow
DCWW101020a · 83493cfeW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BRONWYDD SEWAGE TREATMENT WORKS, BRONWYDD, CARMARTHEN
Due 2029-30Bronwydd WwTW Storm Overflow
DCWW102403a · d9196a5aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BRYNMEILLION PS EOF
Due 2029-30Brynmeillion Storm Overflow
DCWW101084a · a3c25815W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BRYNMEILLION SPS, LLANPUMPSAINT
Due 2029-30Brynmeillion Storm Overflow
DCWW101821a · 8554f6f4W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CAIO STW
Due 2029-30Water body only
DCWW102663a · 076af2fbW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Camarthen Parc Hinds SPS CSO
Due 2029-30Old Priory Road Storm Overflow
DCWW102529a · b77ac40bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen - Jobswell Road
Due 2029-30Job's Well Road Storm Overflow
DCWW102569a · acf2c9b8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen - Old Station Road
Due 2029-30Old Station Road Storm Overflow
DCWW102556a · ba1fe6a9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen - Sticle Path
Due 2029-30Carmarthen Sticle Footpath Storm Overflow
DCWW101582a · c2429eb4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen Market CSO
Due 2029-30Pothouse Wharf Storm Overflow
DCWW101582a · 4751e7efW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen Near Fire Station CSO
Due 2029-30Russell Terrace Storm Overflow
DCWW101582a · c18b1893W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen Old Llansteffan Rd CSO
Due 2029-30Old Llansteffan Road Carmarthen Storm Overflow
DCWW101007a · ef6c9402W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Carmarthen Old Llansteffan Road CSO
Due 2029-30Old Llansteffan Road Carmarthen Storm Overflow
DCWW102247a · 55acf9b4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Carmarthen Pentremeurig Rd
Due 2029-30Pentremeurig Road 1 Storm Overflow
DCWW101817a · debf8443W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CILYCWM STW
Due 2029-30Water body only
DCWW102410a · c4dd0f3aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CONWYL ELFED STW
Due 2029-30Cynwyl Elfed WwTW Storm Overflow
DCWW101812a · 457f436fW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CWM IFOR STW
Due 2029-30Water body only
DCWW101812b · 4adf44fcW_HR_AMM_T_IMP1Improvement
Ammonia reduction to meet numeric permit limit Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
CWM IFOR STW
Due 2029-30Water body only
DCWW101452a · d43a76daW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Cwmduad WWTW
Due 2029-30Cwmduad WwTW Storm Overflow
DCWW102249a · 33081892W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cwmdwyfran SPS EO
Due 2029-30Cwmdwyfran Storm Overflow
DCWW101815a · 4e30df4bW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CWRT HENRI STW
Due 2029-30Water body only
DCWW101822a · b8dab3d8W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CYNGHORDY STW
Due 2029-30Water body only
DCWW101582a · d7cd3ddeW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cynwyl Village Bridge
Due 2029-30Pont Cynwyl Storm Overflow
DCWW100932a · 163f243fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
FARMERS STW SPS EO
Due 2029-30Ffarmers WwTW Overflow
DCWW101026a · b5b0f8c0W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
FELIN FRAN PUMPING STATIOPN, LLANGADOG, DYFED
Due 2029-30Felinfran Overflow
DCWW101823a · 29d9cb5cW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
FELINGWM STW
Due 2029-30Water body only
DCWW101816a · e1bbc6b0W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
FFAIRFACH STW
Due 2029-30Water body only
DCWW101582a · ef944f41W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Golden Grove WwTW Inlet CSO Llandie
Due 2029-30Golden Grove WwTW Storm Overflow
DCWW101582a · 0ce2d8f1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Jewsons CSO Tanerdy Carmarthen
Due 2029-30Tanerdy Storm Overflow
DCWW102376a · 3de4ba89W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llandeilo - Off Station Road
Due 2029-30Llandeilo of Station Road Storm Overflow
DCWW101472a · e4c12c98W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Llandovery No 1 SPS
Due 2029-30Llandovery Storm Overflow
DCWW101809a · 3223399aW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANDOVERY WWTW
Due 2029-30Water body only
DCWW100922a · 30c29b90W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANEGWAD SPS
Due 2029-30Water body only
DCWW101813a · 14ac664eW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANFYNYDD STW
Due 2029-30Water body only
DCWW101813b · cbee5b0eW_HR_AMM_T_IMP1Improvement
Ammonia reduction to meet numeric permit limit Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
LLANFYNYDD STW
Due 2029-30Water body only
DCWW100686a · 7712c21aW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANGADOG
Due 2029-30Llangadog WwTW Storm Overflow
DCWW100649a · f0688388W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANGADOG
Due 2029-30Llangadog WwTW Storm Overflow
DCWW102726a · 8206a63bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llangadog - Off A4069 (Common)
Due 2029-30Llangadog Off A4069 Storm Overflow
DCWW101807a · 53fe0a70W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANGADOG STW
Due 2029-30Water body only
DCWW102575a · 17ca25cbW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANGAIN PWNTAN PS
Due 2029-30Llangain Pwntan Storm Overflow
DCWW102524a · f64ecca7W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANPUMPSAINT PS
Due 2029-30Llanpumpsaint WwTW Storm Overflow
DCWW100929a · f9e9b1aaW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANPUMPSAINT PUMPING STATION, LLANPUMSAINT, NR. CARMARTHEN
Due 2029-30Llanpumpsaint WwTW Storm Overflow
DCWW101011a · 76e1739bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANSADWRN PUMPING STATION
Due 2029-30Llansadwrn Storm Overflow
DCWW101582a · 3ea8c6b4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANSAWEL . .
Due 2029-30No1 Llansawel Village Storm Overflow
DCWW102416a · 7df77666W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANSAWEL STW STORM CSO
Due 2029-30Llansawel WwTW Storm Overflow
DCWW101582a · 3c804b39W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llansawel Village CSO No2
Due 2029-30Llansawel No. 2 Storm Overflow
DCWW101819a · 67d0bc4dW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANSAWEL WASTEWATER TREATMENT WORKS
Due 2029-30Water body only
DCWW100896a · dae568fcW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANWRDA SPS
Due 2029-30Water body only
DCWW101125a · e0ea91dfW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MEYSYDD Y COLEG SPS, CARMARTHEN, SA31 3GR
Due 2029-30Water body only
DCWW101582a · e883a93eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Morfa Lane CSO, Carmarthen
Due 2029-30Morfa Lane Carmarthen Storm Overflow
DCWW100894a · ce25af02W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MORFA LANE, CARMARTHEN
Due 2029-30Morfa Lane Carmarthen Storm Overflow
DCWW100911a · c228bc65W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MYDDFAI PS, Llandovery , ,
Due 2029-30Myddfai Storm Overflow
DCWW101818a · 30d516d0W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
MYDDFAI STW
Due 2029-30Water body only
DCWW101582a · bcdc862aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Myddfai Village Sewerage Scheme CSO
Due 2029-30Myddfai Storm Overflow
DCWW101582a · b322d83bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Old Priory Row CSO Parc Hinds PS C
Due 2029-30Parc Hinds Storm Overflow
DCWW100915a · 2f3f37ddW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Pencoed Farm SPS, at Llangain No 1 Carmarthenshire
Due 2029-30Llangain Storm Overflow
DCWW101582a · 370df6fcW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pencoed Farm SPS, Llangain
Due 2029-30Llangain Storm Overflow
DCWW101475a · 5065ef91W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PENIEL PUMPING STATION, PENIEL, CARMARTHEN, DYFED
Due 2029-30Peniel Overflow
DCWW101582a · 0d07f995W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pentremeurig Road CSO
Due 2029-30Pentremeurig Road 2 Storm Overflow
DCWW101582a · f20f1c5bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pont-ar-Gothi & Nantgaredig Wastewater Treatment Works
Due 2029-30Pont-ar-gothi & Nantgaredig WwTW Storm Overflow
DCWW100921a · 650cef56W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PONTARGOTHI SPS
Due 2029-30Pontargothi Overflow
DCWW101810a · 3c2a88bdW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
PONTARGOTHI WWTW
Due 2029-30Water body only
DCWW100895a · b582465fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
POTHOUSE WHARF SPS
Due 2029-30Pothouse Wharf Storm Overflow
DCWW100955a · a26693deW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PUMPING STATION NO 1, IDOLE CWMFFRWD SEWERAGE SCHEME
Due 2029-30Croes Y Ceiliog Overflow
DCWW100954a · 5b241dc5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PUMPING STATION NO 5, IDOLE CWMFFRWD SEWERAGE SCHEME
Due 2029-30Water body only
DCWW100931a · a29c4eb2W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PUMPSAINT STW - EMERGENCY DISCHARGE
Due 2029-30Water body only
DCWW100986a · 9f3ebc07W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Pwntan SPS, Llangain, Carmathenshire
Due 2029-30Llangain Pwntan Storm Overflow
DCWW101824a · bf06fd01W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. for P and Ammonia
WQ
RHANDIRMWYN
Due 2029-30Water body only
DCWW102382a · 574bb11cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RHOSMAEN PS
Due 2029-30Rhosmaen Storm Overflow
DCWW100699a · 213ed8daW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
SALEM
Due 2029-30Salem WwTW Storm Overflow
DCWW100654a · a7d24fd4W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
SALEM
Due 2029-30Salem WwTW Storm Overflow
DCWW101811a · 1736229dW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
SALEM STW
Due 2029-30Water body only
DCWW101961a · 9740d41aW_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Salem WwTW
Due 2029-30Salem WwTW Storm Overflow
DCWW100893a · c43ad8a8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
SSO at BRICKYARD LANE PUMPING STATION, BRICKYARD LANE, CARMARTHEN
Due 2029-30Water body only
DCWW101582a · 4dc01f6bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Storm Overflow at Bronwydd Wastewater Treatment Works
Due 2029-30Bronwydd WwTW Storm Overflow
DCWW101096a · 1b1d85b6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TALLEY STW INLET SPS
Due 2029-30Talley WwTW Overflow
DCWW101808a · 4575a5e1W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
TALLEY WWTW
Due 2029-30Water body only
DCWW100914a · 3711e8a8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TREVAUGHAN SWO
Due 2029-30Russell Terrace Storm Overflow

107 of 107 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.