Reduction tracker
Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.
The Storm Overflows Discharge Reduction Plan covers England only. The River Tywi is in Wales, which sets its own storm overflow targets. The figures below still show how often each overflow spills against its own baseline and against 10 spills a year, but that cap is England’s. Welsh annual returns start in 2022, so the baseline here is each overflow’s 2022 figure, not 2020.
What the plan is, and what it leaves out
The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:
- By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
- By 2045 — the remaining high-priority overflows.
- By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.
The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the EDM record: each overflow's counted spills per year — the standard 12/24-hour block figure, the same basis the cap is written in — against its 2022 baseline (the first Welsh annual return) and the 2050 cap of ~10, with the deadline its location implies.
Every overflow against its cap
Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.
| Overflow | Deadline | Baseline | Latest | Since baseline | vs cap | Trajectory | Verdict |
|---|---|---|---|---|---|---|---|
| Bronwydd Wwtw Storm Overflow DCWW687 | 2050 | 10 ·22 | 197 0 events | +1870% | 19.7× | Rising | |
| Llanfynydd Wwtw Storm Overflow DCWW1539 | 2050 | 173 ·22 | 169 0 events | -2% | 16.9× | Falling — behind | |
| Cilycwm Wwtw Storm Overflow DCWW1007 | 2050 | 270 ·22 | 162 0 events | -40% | 16.2× | Falling — behind | |
| Myddfai Storm Overflow DCWW1177 | 2050 | 127 ·22 | 138 0 events | +9% | 13.8× | Rising | |
| Llandovery Wwtw Storm Overflow DCWW1509 | 2050 | 136 ·22 | 134 0 events | -1% | 13.4× | Falling — behind | |
| Brechfa Overflow DCWW1576 | 2050 | 102 ·22 | 133 0 events | +30% | 13.3× | Rising | |
| Manordeilo Overflow DCWW1661 | 2050 | 113 ·22 | 130 0 events | +15% | 13× | Rising | |
| Old Station Road Storm Overflow DCWW2198 | 2050 | 82 ·22 | 125 0 events | +52% | 12.5× | Rising | |
| South of Roundabout A40 A485 Storm Overflow DCWW1571 | 2050 | 80 ·22 | 111 0 events | +39% | 11.1× | Rising | |
| Cwmduad Wwtw Storm Overflow DCWW2179 | 2050 | 96 ·22 | 109 0 events | +14% | 10.9× | Rising | |
| Llandeilo Near A483 Road Bridge Storm Overflow DCWW567 | 2050 | 100 ·22 | 105 0 events | +5% | 10.5× | Rising | |
| Heol Llangynnwr Carmarthen Overflow DCWW1823 | 2050 | 101 ·22 | 105 0 events | +4% | 10.5× | Rising | |
| Pothouse Wharf Storm Overflow DCWW794 | 2050 | 64 ·22 | 102 0 events | +59% | 10.2× | Rising | |
| Cynwyl Elfed Wwtw Storm Overflow DCWW2177 | 2050 | 42 ·22 | 97 0 events | +131% | 9.7× | Rising | |
| Salem Wwtw Storm Overflow DCWW1410 | 2050 | 124 ·22 | 97 0 events | -22% | 9.7× | Falling — behind | |
| Llanpumpsaint Wwtw Storm Overflow DCWW1205 | 2050 | 118 ·22 | 87 0 events | -26% | 8.7× | Falling — behind | |
| Carmarthen Bridge Storm Overflow DCWW1752 | 2050 | 61 ·22 | 86 0 events | +41% | 8.6× | Rising | |
| Llandeilo Yscubor Abad North Storm Overflow DCWW565 | 2050 | 81 ·22 | 82 0 events | +1% | 8.2× | Rising | |
| Felingwm Uchaf Wwtw Storm Overflow DCWW964 | 2050 | 108 ·22 | 79 0 events | -27% | 7.9× | Falling — behind | |
| Alltwallis Overflow DCWW1724 | 2050 | 45 ·22 | 78 0 events | +73% | 7.8× | Rising | |
| Llangain Storm Overflow DCWW896 | 2050 | 35 ·22 | 75 0 events | +114% | 7.5× | Rising | |
| Albion Near Railway Crossing Storm Overflow DCWW458 | 2050 | 80 ·22 | 73 0 events | -9% | 7.3× | Falling — behind | |
| Croes Y Ceiliog Overflow DCWW630 | 2050 | 49 ·22 | 71 0 events | +45% | 7.1× | Rising | |
| Brynmeillion Storm Overflow DCWW1885 | 2050 | 42 ·22 | 65 0 events | +55% | 6.5× | Rising | |
| Carmarthen Sticle Footpath Storm Overflow DCWW1022 | 2050 | 78 ·22 | 61 0 events | -22% | 6.1× | Falling — behind | |
| Job's Well Road Storm Overflow DCWW2229 | 2050 | 64 ·22 | 61 0 events | -5% | 6.1× | Falling — behind | |
| Talley Wwtw Overflow DCWW1083 | 2050 | 30 ·22 | 58 0 events | +93% | 5.8× | Rising | |
| Ferryside Storm Overflow DCWW2294 | 2050 | 31 ·22 | 54 0 events | +74% | 5.4× | Rising | |
| Ffarmers Wwtw Overflow DCWW1298 | 2050 | 5 ·22 | 54 0 events | +980% | 5.4× | Rising | |
| Caio Wwtw Overflow DCWW1660 | 2050 | 32 ·22 | 46 0 events | +44% | 4.6× | Rising | |
| Pontargothi Overflow DCWW2289 | 2050 | 48 ·22 | 45 0 events | -6% | 4.5× | Falling — behind | |
| Llandeilo of Station Road Storm Overflow DCWW566 | 2050 | 41 ·22 | 44 0 events | +7% | 4.4× | Rising | |
| Rhosmaen Storm Overflow DCWW492 | 2050 | 40 ·22 | 37 0 events | -8% | 3.7× | Falling — behind | |
| Abergorlech Storm Overflow DCWW1892 | 2050 | 1 ·22 | 34 0 events | +3300% | 3.4× | Rising | |
| Cwmdwyfran Storm Overflow DCWW410 | 2050 | 23 ·22 | 29 0 events | +26% | 2.9× | Rising | |
| Pont Cynwyl Storm Overflow DCWW505 | 2050 | 9 ·22 | 14 0 events | +56% | 1.4× | Rising | |
| Felinfran Overflow DCWW394 | 2050 | 2 ·22 | 12 0 events | +500% | 1.2× | Rising | |
| Pensarn Overflow DCWW1857 | 2050 | 3 ·23 | 8 0 events | +167% | 0.8× | Within the cap | |
| Llangain Pwntan Storm Overflow DCWW897 | 2050 | 20 ·22 | 6 1 events | -70% | 0.6× | Within the cap | |
| Llansawel No. 2 Storm Overflow DCWW890 | 2050 | 3 ·22 | 5 0 events | +67% | 0.5× | Within the cap | |
| Llangadog Off A4069 Storm Overflow DCWW561 | 2050 | 19 ·22 | 3 0 events | -84% | 0.3× | Within the cap | |
| Llansawel Wwtw Storm Overflow DCWW1200 | 2050 | 24 ·22 | 0 0 events | -100% | 0× | Within the cap | |
| No1 Llansawel Village Storm Overflow DCWW2090 | 2050 | 0 ·22 | 0 0 events | — | 0× | Within the cap |
What this is — and what it is not
This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2022 baseline and the 10/year cap. Counted spills use the standard 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →