Reduction tracker
Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.
The Storm Overflows Discharge Reduction Plan covers England only. The Thaw and Cadoxton is in Wales, which sets its own storm overflow targets. The figures below still show how often each overflow spills against its own baseline and against 10 spills a year, but that cap is England’s. Welsh annual returns start in 2022, so the baseline here is each overflow’s 2022 figure, not 2020.
What the plan is, and what it leaves out
The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:
- By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
- By 2045 — the remaining high-priority overflows.
- By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.
The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the EDM record: each overflow's counted spills per year — the standard 12/24-hour block figure, the same basis the cap is written in — against its 2022 baseline (the first Welsh annual return) and the 2050 cap of ~10, with the deadline its location implies.
Every overflow against its cap
Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.
| Overflow | Deadline | Baseline | Latest | Since baseline | vs cap | Trajectory | Verdict |
|---|---|---|---|---|---|---|---|
| Cowbridge Llanbethian Wwtw Storm Overflow DCWW1736 | 2050 | 90 ·22 | 137 0 events | +52% | 13.7× | Rising | |
| Trerhyngyll Overflow DCWW2347 | 2050 | 40 ·25 | 40 0 events | 0% | 4× | — | Falling — behind |
| Stonylands Storm Overflow DCWW469 | 2050 | 29 ·22 | 34 0 events | +17% | 3.4× | Rising | |
| Whitewell Road 2 Storm Overflow DCWW1434 | 2050 | 14 ·22 | 24 0 events | +71% | 2.4× | Rising | |
| Sully Moors Road Storm Overflow DCWW744 | 2050 | 6 ·22 | 21 0 events | +250% | 2.1× | Rising | |
| St Cadoc's Avenue Dinas Powys Storm Overflow DCWW2253 | 2050 | 6 ·22 | 13 0 events | +117% | 1.3× | Rising | |
| Wenvoe Overflow DCWW831 | 2050 | 19 ·22 | 13 0 events | -32% | 1.3× | Nearly there | |
| Robins Lane Storm Overflow DCWW483 | 2050 | 6 ·22 | 11 0 events | +83% | 1.1× | Rising | |
| Cwm Barry Storm Overflow DCWW77 | 2050 | 2 ·22 | 10 0 events | +400% | 1× | Within the cap | |
| Daniel Street 1 Storm Overflow DCWW986 | 2050 | 1 ·22 | 8 0 events | +700% | 0.8× | Within the cap | |
| Pontypridd Road Storm Overflow DCWW178 | 2050 | 1 ·22 | 8 0 events | +700% | 0.8× | Within the cap | |
| Coldbrook Road Tank Storm Overflow DCWW643 | 2050 | 1 ·22 | 7 0 events | +600% | 0.7× | Within the cap | |
| Weycock Cross Storm Overflow DCWW1442 | 2050 | 0 ·22 | 7 0 events | — | 0.7× | Within the cap | |
| Nant Talwg Storm Overflow DCWW216 | 2050 | 1 ·22 | 6 0 events | +500% | 0.6× | Within the cap | |
| Whitewell Road 1 Storm Overflow DCWW801 | 2050 | 2 ·22 | 5 0 events | +150% | 0.5× | Within the cap | |
| Maple Road Storm Overflow DCWW240 | 2050 | 5 ·22 | 5 0 events | 0% | 0.5× | Within the cap | |
| Coldbrook Road East 1 Storm Overflow DCWW422 | 2050 | 5 ·22 | 5 0 events | 0% | 0.5× | Within the cap | |
| Broad Street Barry Storm Overflow DCWW107 | 2050 | 4 ·22 | 4 0 events | 0% | 0.4× | Within the cap | |
| Coldbrook Road East 2 Storm Overflow DCWW421 | 2050 | 5 ·22 | 4 0 events | -20% | 0.4× | Within the cap | |
| Countess Place Penarth Overflow DCWW2116 | 2050 | 7 ·22 | 4 0 events | -43% | 0.4× | Within the cap | |
| Torbay Terrace Junction Storm Overflow DCWW452 | 2050 | 0 ·22 | 3 1 events | — | 0.3× | Within the cap | |
| Station Road East Wenvoe Storm Overflow DCWW749 | 2050 | 1 ·22 | 3 0 events | +200% | 0.3× | Within the cap | |
| Price Avenue Storm Overflow DCWW792 | 2050 | 3 ·22 | 3 0 events | 0% | 0.3× | Within the cap | |
| Porthkerry Storm Overflow DCWW176 | 2050 | 4 ·22 | 2 0 events | -50% | 0.2× | Within the cap | |
| Junction of Claude Road West And Severn Avenue Barry Storm Overflow DCWW289 | 2050 | 0 ·22 | 2 0 events | — | 0.2× | Within the cap | |
| Harbour Road Barry Town Storm Overflow DCWW304 | 2050 | 2 ·22 | 2 0 events | 0% | 0.2× | Within the cap | |
| Atlantic Trading Estate Storm Overflow DCWW137 | 2050 | 1 ·22 | 1 0 events | 0% | 0.1× | Within the cap | |
| Fontygary Fonmon Park Road Storm Overflow DCWW2067 | 2050 | 0 ·22 | 1 0 events | — | 0.1× | Within the cap | |
| Paget Road Barry Storm Overflow DCWW202 | 2050 | 0 ·22 | 1 0 events | — | 0.1× | Within the cap | |
| Llanharry Storm Overflow DCWW893 | 2050 | 1 ·22 | 1 0 events | 0% | 0.1× | Within the cap | |
| Nant Talwg Way Storm Overflow DCWW215 | 2050 | 1 ·22 | 0 0 events | -100% | 0× | Within the cap | |
| Llantwit Major Beach Road Storm Overflow DCWW255 | 2050 | 2 ·22 | 0 0 events | -100% | 0× | Within the cap | |
| Tredogan Storm Overflow DCWW417 | 2050 | 0 ·22 | 0 0 events | — | 0× | Within the cap | |
| Argae Lane Storm Overflow DCWW714 | 2050 | 0 ·22 | 0 0 events | — | 0× | Within the cap | |
| Millfield Drive Storm Overflow DCWW2052 | 2050 | 1 ·22 | 0 0 events | -100% | 0× | Within the cap | |
| Cowbridge Street Barry Storm Overflow DCWW2053 | 2050 | 0 ·22 | 0 0 events | — | 0× | Within the cap | |
| Llantwit Major Beach Road Settled Storm Overflow DCWW30 | 2050 | 28 ·22 | 0 0 events | -100% | 0× | Within the cap | |
| Hillary Rise Rear Storm Overflow DCWW1719 | 2050 | 0 ·22 | 0 0 events | — | 0× | Within the cap | |
| Barry Lakeside Overflow DCWW129 | 2050 | 1 ·22 | 0 0 events | -100% | 0× | Within the cap |
What this is — and what it is not
This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2022 baseline and the 10/year cap. Counted spills use the standard 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →