What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SW104992 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Altarnun STW | Due 2026-27 | Penpont Water |
| 08SW104991 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Altarnun STW | Due 2026-27 | Penpont Water |
| 08SW104977 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BEALS MILL STW | Due 2026-27 | Lower river inny |
| 08SW104976 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) BEALS MILL STW | Due 2026-27 | Lower river inny |
| 08SW104815 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) GUNNISLAKE STW | Due 2026-27 | Lower River Tamar |
| 08SW104816 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) GUNNISLAKE STW | Due 2026-27 | Lower River Tamar |
| 08SW104808 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HARROWBARROW STW | Due 2026-27 | Cotehele Stream |
| 08SW104807 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) HARROWBARROW STW | Due 2026-27 | Cotehele Stream |
| 08SW104754 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Lewannick STW | Due 2026-27 | Penpont Water |
| 08SW104753 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Lewannick STW | Due 2026-27 | Penpont Water |
| 08SW104726 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) METHERELL STW | Due 2026-27 | Cotehele Stream |
| 08SW104727 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) METHERELL STW | Due 2026-27 | Cotehele Stream |
| 08SW104720 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) MILTON ABBOT STW | Due 2026-27 | Lower River Tamar |
| 08SW104721 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) MILTON ABBOT STW | Due 2026-27 | Lower River Tamar |
| 08SW104589 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) STOKE CLIMSLAND STW | Due 2026-27 | Lower River Tamar |
| 08SW104590 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) STOKE CLIMSLAND STW | Due 2026-27 | Lower River Tamar |
| 08SW104999 · ds | EnvAct_INV4 | Investigation | Investigation to meet EnvAct INV4 Driver SALTASH ROAD SPS_PSCSOEO_PLYMOUTH | Due 2027-28 | SALTASH ROAD SPS_PSCSOEO_PLYMOUTH |
| 08SW101417 · a | EnvAct_IMP2 | Improvement | Reduction of spills to meet EnvAct_IMP drivers BARBICAN TANKS_CSOEO_PLYMOUTH | Due 2029-30 | BARBICAN TANKS_CSOEO_PLYMOUTH |
| 08SW101438 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers CAMBRIDGE LANE_CSO_PLYMOUTH | Due 2029-30 | CAMBRIDGE LANE_CSO_PLYMOUTH |
| 08SW102925 · a | EE_IMP | Improvement | Eel screening requirement (Abstraction) Eel Abstraction - Gunnislake | Due 2029-30 | Lower River Tamar |
| 08SW101544 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers MARKET STREET SPS_PSCSOEO_KINGSAND | Due 2029-30 | MARKET STREET SPS_PSCSOEO_KINGSAND |
| 08SW101543 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers MARKET STREET SPS_PSCSOEO_KINGSAND | Due 2029-30 | MARKET STREET SPS_PSCSOEO_KINGSAND |
| 08SW104299 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers OCEAN COURT SPS_PSCSOEO_PLYMOUTH | Due 2029-30 | OCEAN COURT SPS_PSCSOEO_PLYMOUTH |
| 08SW101635 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers THE SQUARE CAWSAND_PSCSOEO_CAWSAND | Due 2029-30 | THE SQUARE CAWSAND_PSCSOEO_CAWSAND |
24 of 24 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.