What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100151a · cd7ea226 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CARDIFF CENTRAL SPS TREMORFA | Complete 2025-26 | Cardiff Central Storm Overflow |
| DCWW100152a · 1ab31fdd | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CARDIFF EAST DISTRICT LONG OUTFALL | Complete 2025-26 | Cardiff Eastern Short Sea Outfall Storm Overflow |
| DCWW100153a · b0e364b4 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CARDIFF EASTERN DISTRICT | Complete 2025-26 | Cardiff Eastern Short Sea Outfall Storm Overflow |
| DCWW102154a · f1f97def | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Cardiff Hathwood Road, Heathway Junction | Due 2026-27 | Heathwood Road Storm Overflow |
| DCWW102152a · c3facf46 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CARDIFF KIMBERLEY ROAD SWO 5 | Due 2026-27 | Cardiff Kimberley Road Storm Overflow |
| DCWW101529a · 4fd78074 | W_FISH_IMP1 | Improvement | Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage. Fish Fish Barrier Mitigation at asset 50115136 | Due 2026-27 | Water body only |
| DCWW102625a · 704dc52b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Jct. Penylan Rd/Kimberley Rd CSO Cardiff | Due 2026-27 | Cardiff Pen-y-lan Road Storm Overflow |
| DCWW101564a · e8894913 | W_FISH_IMP1 | Improvement | Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage. Fish 50000850 (YstradMynach A472CSO) | Due 2029-30 | Water body only |
| DCWW102363a · 16473693 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ 64 Commercial Street Senghenydd CSO | Due 2029-30 | Commercial Street Senghenydd Storm Overflow |
| DCWW101582a · f62c429c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ 86 Nantgarw Rd CSO | Due 2029-30 | Nantgawr Road Storm Overflow |
| DCWW101582a · 458f0477 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ A CSO 700M SE OF PLAS MACHEN COTAGE | Due 2029-30 | Plas Machen Storm Overflow |
| DCWW101582a · 25a0eb6b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ A CSO AT PONTLOTTYN | Due 2029-30 | Pontlottyn Old Gasworks Storm Overflow |
| DCWW101582a · e92abeb4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ A CSO AT YSTRAD MYNACH BRIDGE | Due 2029-30 | Ystrad Mynach Bridge Storm Overflow |
| DCWW100814a · a99b1dbd | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ A SPS, A Residential Development of 5 houses off Morgan St, Caerphilly | Due 2029-30 | Nantgawr Road Storm Overflow |
| DCWW100829a · 359b2dec | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ A SPS, CARDIFF CENTRAL SEWAGE PUMPING STATION, TREMORFA, CARDIFF | Due 2029-30 | Cardiff Central Storm Overflow |
| DCWW101582a · 0f34adc5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Aberbargoed CSO | Due 2029-30 | Sannan Street Storm Overflow |
| DCWW101582a · 0ef25c32 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Abertridwr Coed Cae Road 1 CSO | Due 2029-30 | Coedcae Road Abertridwr Storm Overflow |
| DCWW101582a · e7cec036 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Asset No. 32207 Celtic Steel Factory CSO | Due 2029-30 | Coopers Court Storm Overflow |
| DCWW101582a · 91070b6e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Ball Lane CSO | Due 2029-30 | Ball Lane Storm Overflow |
| DCWW101582a · b7dba80f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Bargoed Colliery CSO | Due 2029-30 | Bargoed Station Road Storm Overflow |
| DCWW101937a · 9942d089 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ BARGOED OLD COLLIERY WASHERY ADJACENT TO | Due 2029-30 | Bargoed Old Colliery Washery Storm Overflow |
| DCWW102331a · 0a525ea9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BASSALEG NEAR VICARAGE GLEBE HOUSE | Due 2029-30 | Forge Road Bassaleg Storm Overflow |
| DCWW102311a · 0a6fb883 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BEDWAS CAERPHILLY BYPASS AT TESCO | Due 2029-30 | Caerphilly Bypass Supermarket Storm Overflow |
| DCWW101582a · 95586719 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BEDWAS SUNNYBANK FARM CSO | Due 2029-30 | Pentwyngwyn Road Storm Overflow |
| DCWW101582a · 9844c37c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Began Road CSO | Due 2029-30 | Began Road Cardiff Storm Overflow |
| DCWW102451a · 925c5854 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BLACKWOOD CWMGELLI | Due 2029-30 | Bryngoleu Street Blackwood Overflow |
| DCWW102686a · a7b02231 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BRITHDIR NEAR STATION | Due 2029-30 | Brithdir Station Storm Overflow |
| DCWW102563a · a8fce57b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Cardiff Central SPS CSO | Due 2029-30 | Ocean Park Storm Overflow |
| DCWW102564a · d12394af | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Cardiff Eastern District CSO | Due 2029-30 | Cardiff Eastern Long Sea Outfall Storm Overflow |
| DCWW102565a · ab315fef | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CARDIFF EASTERN DISTRICT PS | Due 2029-30 | Cardiff Eastern Long Sea Outfall Storm Overflow |
| DCWW102288a · 5cc0349f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CARDIFF ST MELLONS BRIDGE ROAD | Due 2029-30 | St. Mellons Bridge Road Storm Overflow |
| DCWW101582a · f431daed | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Combined Sewer Overflow at Rear of 33 Church Street | Due 2029-30 | Church Street Rear Ystrad Mynnach Storm Overflow |
| DCWW101582a · c2051529 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Combined Sewer Overflow Serving Greenway, Bedwas House Industrial Estate, Bedwas | Due 2029-30 | Greenway Bedwas Storm Overflow |
| DCWW101582a · fcbde830 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO AT ABERBARGOED VIADUCT | Due 2029-30 | Factory Road Field Storm Overflow |
| DCWW101582a · f4de7222 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Bassaleg Forge Lane near Nos 5 & 6 | Due 2029-30 | Forge Lane Bassaleg Storm Overflow |
| DCWW101582a · bf3aa8a8 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Glan-yr-Afon Nursing Home 1 | Due 2029-30 | Ford Road Pengam Storm Overflow |
| DCWW101582a · 2e7282ed | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Lansbury Park Estate | Due 2029-30 | Bedwas Road Storm Overflow |
| DCWW101582a · c1ff95f2 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Trelyn Park | Due 2029-30 | Trelyn Park Storm Overflow |
| DCWW101582a · fd344df0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO NEAR RHYMNEY STATION | Due 2029-30 | Rhymney Walk Storm Overflow |
| DCWW102336a · 58405b64 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CWM LAS CSO | Due 2029-30 | Cwm Las Storm Overflow |
| DCWW102276a · d783d0e6 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ELLIOTS TOWN PRIMARY SCHOOL NEW CSO | Due 2029-30 | New Tredegar Business Park West Storm Overflow |
| DCWW100778a · 8b7ebc05 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ EMERGENCY SPS AT BLOSSOM DRIVE LISVANE | Due 2029-30 | Water body only |
| DCWW102322a · f967e786 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Factory Road, Viaduct CSO Bargoed | Due 2029-30 | Bargoed Viaduct Storm Overflow |
| DCWW101582a · 0459b563 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Fishponds Road No22 CSO, Llanrumey | Due 2029-30 | Ball Lane Storm Overflow |
| DCWW101582a · 18f4fa01 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Fleur-de-Lys - Rear of Glanddu CSO | Due 2029-30 | Glan-y-nant Riverside Path Storm Overflow |
| DCWW101582a · 0f9458b9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Forge Engineering CSO, Bedwas | Due 2029-30 | Pant Glas Industrial Estate Storm Overflow |
| DCWW102294a · 36c9dcde | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Forge Road, Machen | Due 2029-30 | Forge Road Storm Overflow |
| DCWW101443a · ef0d5a34 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Glyn Derw Sewage Pumping Station, Bargoed | Due 2029-30 | Water body only |
| DCWW102365a · fc5f2087 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Graig-Y-Fedw CSO Abertridwr | Due 2029-30 | Graig-Y-Fedw Storm Overflow |
| DCWW101582a · 7261b7ed | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Hartland Road PS | Due 2029-30 | Hartland Road Storm Overflow |
| DCWW101582a · 5af810e4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ High St CSO, Glan-y-Nant | Due 2029-30 | High Street Gant-y-nant Storm Overflow |
| DCWW100766a · cbec106a | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LAND AT PONTYPANDY FARM CAERPHILLY - EMERGENCY | Due 2029-30 | Caerphilly Bypass Supermarket Storm Overflow |
| DCWW101467a · 7df3f38c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MAESGLAS PSTN, OFF MAESGLAS AVENUE, MAESGLAS, NEWPORT, NP9 3BW | Due 2029-30 | Maesglas Storage Storm Overflow |
| DCWW101466a · bfcaad02 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Melin Dwr SPS, Melin Dwr, Draethen, Caerphilly, NP10 8GL | Due 2029-30 | Water body only |
| DCWW101582a · 66e7aff8 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ New Road CSO, Hengoed | Due 2029-30 | New Road Roundabout Storm Overflow |
| DCWW101582a · ab247781 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ New Tredegar Birch Grove | Due 2029-30 | Birchgrove New Tredegar Storm Overflow |
| DCWW101582a · bf1917bf | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Newport Rd CSO, Trethomas | Due 2029-30 | Riverside Park Trethomas Storm Overflow |
| DCWW102696a · d1a70184 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ OCEAN PARK PS TREMORFA SO | Due 2029-30 | Ocean Park Storm Overflow |
| DCWW101582a · a2139480 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Old Prince Albert Hotel CSO, Hengoed | Due 2029-30 | Victoria Road Fleur-De-Lis Storm Overflow |
| DCWW102324a · b82518ed | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PENGAM HIGH STREET NEAR BRIDGE | Due 2029-30 | River Terrace Pengham Storm Overflow |
| DCWW102325a · 8955e304 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PENGAM WOODLAND PLACE | Due 2029-30 | Woodland Place Storm Overflow |
| DCWW101936a · fb097871 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Penpedairheol Oaks End Close D/S F/Brdg | Due 2029-30 | Oaks End Close Footbridge Storm Overflow |
| DCWW101582a · 23ad5355 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Pontlottyn Recreation Ground CSO | Due 2029-30 | Pontlottyn Recreation Ground Storm Overflow |
| DCWW100804a · 95593baa | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PROPOSED RESIDENTIAL DEVELOPMENT, LAND ADJACENT TO TWYN ROAD, YSTRAD MYNACH, HENGOED, CF82 7FG | Due 2029-30 | Coopers Court Storm Overflow |
| DCWW102326a · a0dd1c84 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ REAR OF MARGARET STREET, GILFACH | Due 2029-30 | Basin Football Field Storm Overflow |
| DCWW101582a · dce75412 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Rear of Williams St CSO | Due 2029-30 | William Street Fleur-de-lis Storm Overflow |
| DCWW101940a · b6f021b9 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ RHYMNEY ABERTYSSWG U/S TROED-RHIW-FUWCH | Due 2029-30 | Abertysswg Troedrhiwfuwch Storm Overflow |
| DCWW101582a · d01e1803 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Rhymney Carno St Bute House CSO | Due 2029-30 | Carno Street Storm Overflow |
| DCWW102275a · b51e6ff6 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RHYMNEY REAR OF MEMORIAL HOSPITAL | Due 2029-30 | The Terrace Rhymney Storm Overflow |
| DCWW100854a · 18604ae0 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Roman Gate SPS, Roman Gate, Gelligaer, Caerphilly, CF82 8FT | Due 2029-30 | Water body only |
| DCWW101582a · b58fd278 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Rumney Hill CSO | Due 2029-30 | Dowlands Way Cardiff Storm Overflow |
| DCWW102269a · bbaf126a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ S/O 63 BEDWELLTY ROAD CSO ABERBARGOED | Due 2029-30 | Water body only |
| DCWW102343a · 6768ed9c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ SENGHENYDD CSO | Due 2029-30 | Senghenydd Storm Overflow |
| DCWW102706a · 6c7f0067 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ SENGHENYDD REAR GARDEN 3 WINDSOR PLACE | Due 2029-30 | Windsor Place Storm Overflow |
| DCWW100831a · 9525ac68 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Settled Storm overflow at Cardiff Eastern District PS | Due 2029-30 | Cardiff Eastern Short Sea Outfall Storm Overflow |
| DCWW100765a · e1340404 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ THE COEDKERNEW SEWAGE PUMPING STATION | Due 2029-30 | Water body only |
| DCWW101582a · 33aed8e1 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Tredegar Park Golf Club CSO | Due 2029-30 | Carnegie Court Storm Overflow |
| DCWW101582a · 5aa350c6 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Tredomen AFC CSO, Ystrad Mynach | Due 2029-30 | Twyn Road Ystrad Mynach Storm Overflow |
| DCWW101945a · 4317c0c4 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Trelyn Lane CSO, Fleur-De-Lis | Due 2029-30 | Trelyn Lane Storm Overflow |
| DCWW102350a · 65d408af | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Woodland, B4263/Bryn Siriol, Caerphilly | Due 2029-30 | Bryn Siriol Storm Overflow |
80 of 80 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.