Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

80
Measures in this catchment
NEP, current record
77
Still active
not yet past their date
3
Assumed complete
completion date has passed
6
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100151a · cd7ea226W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CARDIFF CENTRAL SPS TREMORFA
Complete 2025-26Cardiff Central Storm Overflow
DCWW100152a · 1ab31fddW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CARDIFF EAST DISTRICT LONG OUTFALL
Complete 2025-26Cardiff Eastern Short Sea Outfall Storm Overflow
DCWW100153a · b0e364b4W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CARDIFF EASTERN DISTRICT
Complete 2025-26Cardiff Eastern Short Sea Outfall Storm Overflow
DCWW102154a · f1f97defW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cardiff Hathwood Road, Heathway Junction
Due 2026-27Heathwood Road Storm Overflow
DCWW102152a · c3facf46W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARDIFF KIMBERLEY ROAD SWO 5
Due 2026-27Cardiff Kimberley Road Storm Overflow
DCWW101529a · 4fd78074W_FISH_IMP1Improvement
Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage.
Fish
Fish Barrier Mitigation at asset 50115136
Due 2026-27Water body only
DCWW102625a · 704dc52bW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Jct. Penylan Rd/Kimberley Rd CSO Cardiff
Due 2026-27Cardiff Pen-y-lan Road Storm Overflow
DCWW101564a · e8894913W_FISH_IMP1Improvement
Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage.
Fish
50000850 (YstradMynach A472CSO)
Due 2029-30Water body only
DCWW102363a · 16473693W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
64 Commercial Street Senghenydd CSO
Due 2029-30Commercial Street Senghenydd Storm Overflow
DCWW101582a · f62c429cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
86 Nantgarw Rd CSO
Due 2029-30Nantgawr Road Storm Overflow
DCWW101582a · 458f0477W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
A CSO 700M SE OF PLAS MACHEN COTAGE
Due 2029-30Plas Machen Storm Overflow
DCWW101582a · 25a0eb6bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
A CSO AT PONTLOTTYN
Due 2029-30Pontlottyn Old Gasworks Storm Overflow
DCWW101582a · e92abeb4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
A CSO AT YSTRAD MYNACH BRIDGE
Due 2029-30Ystrad Mynach Bridge Storm Overflow
DCWW100814a · a99b1dbdW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
A SPS, A Residential Development of 5 houses off Morgan St, Caerphilly
Due 2029-30Nantgawr Road Storm Overflow
DCWW100829a · 359b2decW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
A SPS, CARDIFF CENTRAL SEWAGE PUMPING STATION, TREMORFA, CARDIFF
Due 2029-30Cardiff Central Storm Overflow
DCWW101582a · 0f34adc5W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Aberbargoed CSO
Due 2029-30Sannan Street Storm Overflow
DCWW101582a · 0ef25c32W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Abertridwr Coed Cae Road 1 CSO
Due 2029-30Coedcae Road Abertridwr Storm Overflow
DCWW101582a · e7cec036W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Asset No. 32207 Celtic Steel Factory CSO
Due 2029-30Coopers Court Storm Overflow
DCWW101582a · 91070b6eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Ball Lane CSO
Due 2029-30Ball Lane Storm Overflow
DCWW101582a · b7dba80fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Bargoed Colliery CSO
Due 2029-30Bargoed Station Road Storm Overflow
DCWW101937a · 9942d089W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
BARGOED OLD COLLIERY WASHERY ADJACENT TO
Due 2029-30Bargoed Old Colliery Washery Storm Overflow
DCWW102331a · 0a525ea9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BASSALEG NEAR VICARAGE GLEBE HOUSE
Due 2029-30Forge Road Bassaleg Storm Overflow
DCWW102311a · 0a6fb883W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BEDWAS CAERPHILLY BYPASS AT TESCO
Due 2029-30Caerphilly Bypass Supermarket Storm Overflow
DCWW101582a · 95586719W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BEDWAS SUNNYBANK FARM CSO
Due 2029-30Pentwyngwyn Road Storm Overflow
DCWW101582a · 9844c37cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Began Road CSO
Due 2029-30Began Road Cardiff Storm Overflow
DCWW102451a · 925c5854W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BLACKWOOD CWMGELLI
Due 2029-30Bryngoleu Street Blackwood Overflow
DCWW102686a · a7b02231W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BRITHDIR NEAR STATION
Due 2029-30Brithdir Station Storm Overflow
DCWW102563a · a8fce57bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cardiff Central SPS CSO
Due 2029-30Ocean Park Storm Overflow
DCWW102564a · d12394afW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cardiff Eastern District CSO
Due 2029-30Cardiff Eastern Long Sea Outfall Storm Overflow
DCWW102565a · ab315fefW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARDIFF EASTERN DISTRICT PS
Due 2029-30Cardiff Eastern Long Sea Outfall Storm Overflow
DCWW102288a · 5cc0349fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARDIFF ST MELLONS BRIDGE ROAD
Due 2029-30St. Mellons Bridge Road Storm Overflow
DCWW101582a · f431daedW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Combined Sewer Overflow at Rear of 33 Church Street
Due 2029-30Church Street Rear Ystrad Mynnach Storm Overflow
DCWW101582a · c2051529W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Combined Sewer Overflow Serving Greenway, Bedwas House Industrial Estate, Bedwas
Due 2029-30Greenway Bedwas Storm Overflow
DCWW101582a · fcbde830W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO AT ABERBARGOED VIADUCT
Due 2029-30Factory Road Field Storm Overflow
DCWW101582a · f4de7222W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Bassaleg Forge Lane near Nos 5 & 6
Due 2029-30Forge Lane Bassaleg Storm Overflow
DCWW101582a · bf3aa8a8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Glan-yr-Afon Nursing Home 1
Due 2029-30Ford Road Pengam Storm Overflow
DCWW101582a · 2e7282edW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Lansbury Park Estate
Due 2029-30Bedwas Road Storm Overflow
DCWW101582a · c1ff95f2W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Trelyn Park
Due 2029-30Trelyn Park Storm Overflow
DCWW101582a · fd344df0W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO NEAR RHYMNEY STATION
Due 2029-30Rhymney Walk Storm Overflow
DCWW102336a · 58405b64W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CWM LAS CSO
Due 2029-30Cwm Las Storm Overflow
DCWW102276a · d783d0e6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ELLIOTS TOWN PRIMARY SCHOOL NEW CSO
Due 2029-30New Tredegar Business Park West Storm Overflow
DCWW100778a · 8b7ebc05W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
EMERGENCY SPS AT BLOSSOM DRIVE LISVANE
Due 2029-30Water body only
DCWW102322a · f967e786W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Factory Road, Viaduct CSO Bargoed
Due 2029-30Bargoed Viaduct Storm Overflow
DCWW101582a · 0459b563W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Fishponds Road No22 CSO, Llanrumey
Due 2029-30Ball Lane Storm Overflow
DCWW101582a · 18f4fa01W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Fleur-de-Lys - Rear of Glanddu CSO
Due 2029-30Glan-y-nant Riverside Path Storm Overflow
DCWW101582a · 0f9458b9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Forge Engineering CSO, Bedwas
Due 2029-30Pant Glas Industrial Estate Storm Overflow
DCWW102294a · 36c9dcdeW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Forge Road, Machen
Due 2029-30Forge Road Storm Overflow
DCWW101443a · ef0d5a34W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Glyn Derw Sewage Pumping Station, Bargoed
Due 2029-30Water body only
DCWW102365a · fc5f2087W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Graig-Y-Fedw CSO Abertridwr
Due 2029-30Graig-Y-Fedw Storm Overflow
DCWW101582a · 7261b7edW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Hartland Road PS
Due 2029-30Hartland Road Storm Overflow
DCWW101582a · 5af810e4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
High St CSO, Glan-y-Nant
Due 2029-30High Street Gant-y-nant Storm Overflow
DCWW100766a · cbec106aW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LAND AT PONTYPANDY FARM CAERPHILLY - EMERGENCY
Due 2029-30Caerphilly Bypass Supermarket Storm Overflow
DCWW101467a · 7df3f38cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MAESGLAS PSTN, OFF MAESGLAS AVENUE, MAESGLAS, NEWPORT, NP9 3BW
Due 2029-30Maesglas Storage Storm Overflow
DCWW101466a · bfcaad02W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Melin Dwr SPS, Melin Dwr, Draethen, Caerphilly, NP10 8GL
Due 2029-30Water body only
DCWW101582a · 66e7aff8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
New Road CSO, Hengoed
Due 2029-30New Road Roundabout Storm Overflow
DCWW101582a · ab247781W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
New Tredegar Birch Grove
Due 2029-30Birchgrove New Tredegar Storm Overflow
DCWW101582a · bf1917bfW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Newport Rd CSO, Trethomas
Due 2029-30Riverside Park Trethomas Storm Overflow
DCWW102696a · d1a70184W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
OCEAN PARK PS TREMORFA SO
Due 2029-30Ocean Park Storm Overflow
DCWW101582a · a2139480W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Old Prince Albert Hotel CSO, Hengoed
Due 2029-30Victoria Road Fleur-De-Lis Storm Overflow
DCWW102324a · b82518edW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PENGAM HIGH STREET NEAR BRIDGE
Due 2029-30River Terrace Pengham Storm Overflow
DCWW102325a · 8955e304W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PENGAM WOODLAND PLACE
Due 2029-30Woodland Place Storm Overflow
DCWW101936a · fb097871W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Penpedairheol Oaks End Close D/S F/Brdg
Due 2029-30Oaks End Close Footbridge Storm Overflow
DCWW101582a · 23ad5355W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pontlottyn Recreation Ground CSO
Due 2029-30Pontlottyn Recreation Ground Storm Overflow
DCWW100804a · 95593baaW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PROPOSED RESIDENTIAL DEVELOPMENT, LAND ADJACENT TO TWYN ROAD, YSTRAD MYNACH, HENGOED, CF82 7FG
Due 2029-30Coopers Court Storm Overflow
DCWW102326a · a0dd1c84W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
REAR OF MARGARET STREET, GILFACH
Due 2029-30Basin Football Field Storm Overflow
DCWW101582a · dce75412W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Rear of Williams St CSO
Due 2029-30William Street Fleur-de-lis Storm Overflow
DCWW101940a · b6f021b9W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
RHYMNEY ABERTYSSWG U/S TROED-RHIW-FUWCH
Due 2029-30Abertysswg Troedrhiwfuwch Storm Overflow
DCWW101582a · d01e1803W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Rhymney Carno St Bute House CSO
Due 2029-30Carno Street Storm Overflow
DCWW102275a · b51e6ff6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RHYMNEY REAR OF MEMORIAL HOSPITAL
Due 2029-30The Terrace Rhymney Storm Overflow
DCWW100854a · 18604ae0W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Roman Gate SPS, Roman Gate, Gelligaer, Caerphilly, CF82 8FT
Due 2029-30Water body only
DCWW101582a · b58fd278W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Rumney Hill CSO
Due 2029-30Dowlands Way Cardiff Storm Overflow
DCWW102269a · bbaf126aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
S/O 63 BEDWELLTY ROAD CSO ABERBARGOED
Due 2029-30Water body only
DCWW102343a · 6768ed9cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
SENGHENYDD CSO
Due 2029-30Senghenydd Storm Overflow
DCWW102706a · 6c7f0067W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
SENGHENYDD REAR GARDEN 3 WINDSOR PLACE
Due 2029-30Windsor Place Storm Overflow
DCWW100831a · 9525ac68W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Settled Storm overflow at Cardiff Eastern District PS
Due 2029-30Cardiff Eastern Short Sea Outfall Storm Overflow
DCWW100765a · e1340404W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
THE COEDKERNEW SEWAGE PUMPING STATION
Due 2029-30Water body only
DCWW101582a · 33aed8e1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Tredegar Park Golf Club CSO
Due 2029-30Carnegie Court Storm Overflow
DCWW101582a · 5aa350c6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Tredomen AFC CSO, Ystrad Mynach
Due 2029-30Twyn Road Ystrad Mynach Storm Overflow
DCWW101945a · 4317c0c4W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Trelyn Lane CSO, Fleur-De-Lis
Due 2029-30Trelyn Lane Storm Overflow
DCWW102350a · 65d408afW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Woodland, B4263/Bryn Siriol, Caerphilly
Due 2029-30Bryn Siriol Storm Overflow

80 of 80 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.