Who is fixing it

Reduction tracker

Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.

The Storm Overflows Discharge Reduction Plan covers England only. The Neath and Afan is in Wales, which sets its own storm overflow targets. The figures below still show how often each overflow spills against its own baseline and against 10 spills a year, but that cap is England’s. Welsh annual returns start in 2022, so the baseline here is each overflow’s 2022 figure, not 2020.

What the plan is, and what it leaves out

The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:

  • By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
  • By 2045 — the remaining high-priority overflows.
  • By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.

The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the EDM record: each overflow's counted spills per year — the standard 12/24-hour block figure, the same basis the cap is written in — against its 2022 baseline (the first Welsh annual return) and the 2050 cap of ~10, with the deadline its location implies.

48
Above the 2050 cap
of 58 tracked
34
Rising since baseline
trend is the wrong way
0
On a 2035 deadline
near a bathing water
10
Within the cap
≤10 spills in 2025

Every overflow against its cap

Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.

OverflowDeadlineBaselineLatestSince baselinevs capTrajectoryVerdict
Pontneddfechan Wwtw Storm Overflow
DCWW179
2050177 ·22
180
0 events
+2%18×Rising
Hirwaun Industrial Estate Wwtw Storm Overflow
DCWW1246
205015 ·22
170
0 events
+1033%17×Rising
Cymmer Storm Overflow
DCWW989
2050109 ·22
123
0 events
+13%12.3×Rising
Dulais Road Seven Sisters Storm Overflow
DCWW973
2050101 ·22
116
0 events
+15%11.6×Rising
Fairfield Neath Storm Overflow
DCWW1552
2050100 ·22
109
0 events
+9%10.9×Rising
Ynys March Crynant Storm Overflow
DCWW1565
2050140 ·22
101
0 events
-28%10.1×Falling — behind
Bryngyrnos Storm Overflow
DCWW2221
205088 ·22
100
0 events
+14%10×Rising
Ton-mawr Road Storm Overflow
DCWW1376
205092 ·22
92
0 events
0%9.2×Falling — behind
Gwaun Afan Storm Overflow
DCWW1265
205074 ·22
91
0 events
+23%9.1×Rising
Coelbren Storm Overflow
DCWW2024
205070 ·22
89
0 events
+27%8.9×Rising
Neath Abbey Ruins Southeast Storm Overflow
DCWW1173
205048 ·22
88
0 events
+83%8.8×Rising
Dulais Fach Road Storm Overflow
DCWW974
2050103 ·22
86
0 events
-17%8.6×Falling — behind
Cwmavon Road Cwmafan Storm Overflow
DCWW76
205083 ·22
85
0 events
+2%8.5×Rising
Old Road Skewen Storm Overflow
DCWW1455
205080 ·22
83
0 events
+4%8.3×Rising
Main Road Heol Ty Gwyn Storm Overflow
DCWW866
205039 ·22
82
0 events
+110%8.2×Rising
Godfrey Avenue Rear Storm Overflow
DCWW949
205070 ·22
78
0 events
+11%7.8×Rising
Heol Y Maes Storm Overflow
DCWW2330
205028 ·24
73
0 events
+161%7.3×Rising
Glyncorrwg Storm Overflow
DCWW1273
20500 ·22
73
0 events
—7.3×Rising
Farmers Road Storm Overflow
DCWW396
205068 ·22
68
0 events
0%6.8×Falling — behind
Moses Row Storm Overflow
DCWW1179
205073 ·22
67
0 events
-8%6.7×Falling — behind
Telecommunication Mast Cwmafan Storm Overflow
DCWW1078
205027 ·22
65
0 events
+141%6.5×Rising
Neath Quay Road Storm Overflow
DCWW363
205066 ·22
64
0 events
-3%6.4×Falling — behind
Ynys Street Storm Overflow
DCWW1671
205017 ·22
54
0 events
+218%5.4×Rising
Heol Hendre Bryncoch Storm Overflow
DCWW1253
205046 ·22
53
0 events
+15%5.3×Rising
Ynys Y Gored Storm Overflow
DCWW97
205052 ·22
53
0 events
+2%5.3×Rising
Heol Pendarren Storm Overflow
DCWW580
205027 ·22
48
0 events
+78%4.8×Rising
London Close Cwmafan Overflow
DCWW1825
205047 ·22
47
0 events
0%4.7×Falling — behind
Bryndulais Avenue Seven Sisters No 2 Storm Overflow
DCWW2252
205039 ·22
46
0 events
+18%4.6×Rising
Llandarcy Outfall Storm Overflow
DCWW568
205026 ·22
45
0 events
+73%4.5×Rising
Newbridge Road No 2 Port Talbot Storm Overflow
DCWW362
205067 ·22
43
0 events
-36%4.3×Falling — behind
Alder Terrace Storm Overflow
DCWW716
205055 ·22
42
0 events
-24%4.2×Falling — behind
Afan Way Storm Overflow
DCWW139
205039 ·22
38
0 events
-3%3.8×Falling — behind
Bethel Road Glynneath Storm Overflow
DCWW1616
205024 ·22
37
0 events
+54%3.7×Rising
Cynonville Overflow
DCWW1644
205013 ·22
36
0 events
+177%3.6×Rising
Conduit Street Port Talbot Storm Overflow
DCWW1002
205015 ·22
35
0 events
+133%3.5×Rising
B4434 Roundabout Resolven Storm Overflow
DCWW1061
205030 ·22
34
0 events
+13%3.4×Rising
Duke Street Margam Storm Overflow
DCWW1923
205015 ·22
34
0 events
+127%3.4×Rising
Afan Street Port Talbot Storm Overflow
DCWW140
20504 ·22
27
0 events
+575%2.7×Rising
Aberdulais Storm Overflow
DCWW460
205040 ·22
26
0 events
-35%2.6×Falling — behind
Llantwit Road Neath Storm Overflow
DCWW1199
205011 ·22
21
0 events
+91%2.1×Rising
Lonlas Storm Overflow
DCWW2193
205057 ·22
20
0 events
-65%2×Falling — behind
Pontrhydyfen Viaduct Storm Overflow
DCWW2206
205026 ·22
19
0 events
-27%1.9×Falling — behind
Blaengwynfi Tunnel Storm Overflow
DCWW451
205042 ·22
16
0 events
-62%1.6×Falling — behind
Main Road Bryncoch Storm Overflow
DCWW1615
20509 ·22
15
0 events
+67%1.5×Rising
Neath Hillside Lane Storm Overflow
DCWW1172
205013 ·22
15
0 events
+15%1.5×Rising
Longford Road Storm Overflow
DCWW880
205010 ·22
14
0 events
+40%1.4×Rising
Pwll Y Glaw Cwmafan Overflow
DCWW1632
20508 ·22
14
0 events
+75%1.4×Rising
Cimla Road Gnoll Brook Storm Overflow
DCWW1006
20504 ·22
12
0 events
+200%1.2×Rising
Heol Illtyd Storm Overflow
DCWW1252
20501 ·22
9
0 events
+800%0.9×Within the cap
Main Road Aberdulais No.1 Storm Overflow
DCWW1187
205014 ·22
7
0 events
-50%0.7×Within the cap
Cimla Common Storm Overflow
DCWW2298
20501 ·22
6
0 events
+500%0.6×Within the cap
Morgans Terrace Playground Pontrhydyfen Storm Overflow
DCWW2240
20500 ·22
5
1 events
—0.5×Within the cap
Caenant Terrace Storm Overflow
DCWW2222
20500 ·22
1
0 events
—0.1×Within the cap
Upper Cymmer Margam Street Storm Overflow
DCWW367
20501 ·25
1
0 events
0%0.1×—Within the cap
Cardonnel Road Storm Overflow
DCWW2325
20500 ·24
1
1 events
—0.1×Within the cap
New Road Skewen Storm Overflow
DCWW1169
20503 ·22
0
0 events
-100%0×Within the cap
Margam Ps Prince Street Overflow
DCWW1925
20500 ·22
0
0 events
—0×Within the cap
Bryndulais Avenue Seven Sisters No1 Storm Overflow
DCWW2207
20500 ·22
0
0 events
—0×Within the cap

What this is — and what it is not

This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2022 baseline and the 10/year cap. Counted spills use the standard 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →