What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08TW100529 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Burstow wwtw | Complete 2025-26 | Burstow Stream |
| 08TW100530 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Crawley wwtw | Complete 2025-26 | Tilgate Brook and Gatwick Stream at Crawley |
| 08TW100531 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Esher wwtw | Complete 2025-26 | Esher STW |
| 08TW100533 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Holmwood wwtw | Complete 2025-26 | Leigh Brook |
| 08TW100537 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Merstham wwtw | Complete 2025-26 | Redhill Brook |
| 08TW101563 · a | U_MON4 | Monitoring | Install and run event-duration monitoring Burstow wwtw | Due 2026-27 | Burstow Stream |
| 08TW100320 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Crawley wwtw | Due 2026-27 | Tilgate Brook and Gatwick Stream at Crawley |
| 08TW100330 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Esher wwtw | Due 2026-27 | Esher STW |
| 08TW100348 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Holmwood wwtw | Due 2026-27 | Leigh Brook |
| 08TW101565 · a | U_MON4 | Monitoring | Install and run event-duration monitoring Merstham wwtw | Due 2026-27 | Redhill Brook |
| 08TW100377 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Rusper wwtw | Due 2026-27 | Baldhorns Brook |
| 08TW100484 · a | WFD_NDLS_Chem1 | No deterioration | Holmwood STW cypermethrin load standstill limit Holmwood STW | Due 2026-27 | Holmwood STW |
| 08TW100142 · a | WFD_NDLS_Chem2 | No deterioration | new PFOS limit PFOS Crawley STW | Due 2026-27 | Tilgate Brook and Gatwick Stream at Crawley |
| 08TW100067 · a | WFD_NDLS_Chem1 | No deterioration | Burstow STW, cypermethrin, 0.0011949 ug Reduce cypermethrin loading | Due 2026-27 | Burstow Stream |
| 08TW100089 · a | WFD_NDLS_Chem2 | No deterioration | Merstham STW, cypermethrin, 0.001 ug Reduce cypermethrin loading | Due 2026-27 | Redhill Brook |
| 08TW100056 · a | WFD_NDLS_Chem2 | No deterioration | Burstow STW, aluminium (total), 1156.4 Reduce metal loading | Due 2026-27 | Burstow Stream |
| 08TW100059 · a | WFD_NDLS_Chem2 | No deterioration | Merstham STW, copper (dissolved), 6.33 Reduce metal loading | Due 2026-27 | Redhill Brook |
| 08TW100127 · a | WFD_NDLS_Chem2 | No deterioration | Merstham STW, Nonylphenol, 0.55µg/l Reduce Nonylphenol loading | Due 2026-27 | Redhill Brook |
| 08TW101545 · b | WFD_INV_CHEM | Investigation | PFOS investigation - Crawley STW 4a Investigation to develop and trial a framework that meets statutory requirements | Due 2027-28 | Tilgate Brook and Gatwick Stream at Crawley |
| 08TW101108 · gb | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at BROCKHAM BRIDGE SPS | Due 2027-28 | Tanners Brook (Holmewood to River Mole confluence at Brockham) |
| 08TW101108 · fx | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at BURSTOW STW | Due 2027-28 | Burstow Stream |
| 08TW101108 · gm | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at COMMONSIDE SPS | Due 2027-28 | Downside Ditches and Bookham Brook |
| 08TW101108 · be | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at ESHER STW | Due 2027-28 | Mole (Hersham to R. Thames conf at East Molesey) |
| 08TW101108 · bo | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at HOLMWOOD STW | Due 2027-28 | Leigh Brook |
| 08TW101108 · ga | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at RUSPER STW | Due 2027-28 | Baldhorns Brook |
| 08TW101108 · az | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at SALFORDS , SURREY SPS | Due 2027-28 | Salfords Stream (Salfords to River Mole confluence) |
| 08TW101108 · gc | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at SPOOKS HILL, NORTH HOLMWOOD CSO | Due 2027-28 | Tanners Brook (Holmewood to River Mole confluence at Brockham) |
| 08TW100203 · a | WFD_INV_MOD | Investigation | Investigate the cause of the spills WFD Investigation of in river Ecological Status to inform future action | Due 2027-28 | Rythe |
| 08TW100200 · a | WFD_INV_MOD | Investigation | Investigate the cause of the spills WFD Investigation of in river Ecological Status to inform future action | Due 2027-28 | Pipp Brook |
| 10TW100024 · a | U_IMP4 | Improvement | Storm Overflows improvements at HOLMWOOD STW Storm Overflows action at HOLMWOOD STW | Due 2027-28 | Leigh Brook |
| 08TW100893 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit with stretch target of 0.1 mg/l at Crawley STW Reduce Phosphorus Loadings at Crawley STW | Due 2029-30 | Tilgate Brook and Gatwick Stream at Crawley |
| 08TW100902 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Esher STW Reduce Phosphorus Loadings at Esher STW | Due 2029-30 | Esher STW |
| 08TW101113 · a | ENVAct_IMP2 | Improvement | Default scheme: Investigation and Solution in AMP 8: 1,285m3 storage, 20m3 screen Storm Overflows action at Burstow STW SPS | Due 2029-30 | Burstow Stream |
| 08TW101078 · a | ENVAct_IMP2 | Improvement | Default scheme: Investigation and Solution in AMP 8: 1,285m3 storage, No screen required Storm Overflows action at Rusper Stw | Due 2029-30 | Baldhorns Brook |
34 of 34 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.