Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

11
Measures in this catchment
WINEP, current record
11
Still active
not yet past their date
0
Assumed complete
completion date has passed
3
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104922 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CALLINGTON (NEW) STW
Due 2026-27Lower River Lynher
08SW104921 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
CALLINGTON (NEW) STW
Due 2026-27Lower River Lynher
08SW104708 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
New Quethiock STW
Due 2026-27Tiddy
08SW104709 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
New Quethiock STW
Due 2026-27Tiddy
08SW104676 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
PILLATON STW
Due 2026-27Lower River Lynher
08SW104677 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
PILLATON STW
Due 2026-27Lower River Lynher
08SW104650 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
RILLA MILL STW
Due 2026-27Lower River Lynher
08SW104649 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
RILLA MILL STW
Due 2026-27Lower River Lynher
08SW104297 · aU_IMP4Improvement
To comply with UWWTR
GOLBERDON STW_SO_GOLBERDON
Due 2027-28GOLBERDON STW_SO_GOLBERDON
08SW104298 · aU_IMP4Improvement
To comply with UWWTR
NORTH HILL STW_SO_NORTH HILL
Due 2027-28NORTH HILL STW_SO_NORTH HILL
08SW102100 · gU_IMP1Improvement
Increased monitoring
CALLINGTON_STW_CALLINGTON
Due 2030-31Lower River Lynher

11 of 11 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.