Reduction tracker
Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.
The Storm Overflows Discharge Reduction Plan covers England only. The Lower Wye and Monnow crosses the border: its English overflows come under the plan, and its Welsh ones under Wales’s own targets. Every overflow here is Dŵr Cymru’s, whose annual returns start in 2022, so the baseline is each overflow’s 2022 figure, not 2020.
What the plan is, and what it leaves out
The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:
- By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
- By 2045 — the remaining high-priority overflows.
- By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.
The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the EDM record: each overflow's counted spills per year — the standard 12/24-hour block figure, the same basis the cap is written in — against its 2020 baseline and the 2050 cap of ~10, with the deadline its location implies.
Every overflow against its cap
Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.
| Overflow | Deadline | Baseline | Latest | Since baseline | vs cap | Trajectory | Verdict |
|---|---|---|---|---|---|---|---|
| Chepstow North Storm Overflow DCWW431 | 2050 | 67 ·22 | 59 0 events | -12% | 5.9× | Falling — behind | |
| Sedbury Storm Overflow DCWW773 | 2050 | 56 ·22 | 59 0 events | +5% | 5.9× | Rising | |
| Wye Street Storm Overflow DCWW472 | 2050 | 42 ·22 | 56 0 events | +33% | 5.6× | Rising | |
| Eign Wwtw Inlet Storm Overflow DCWW1895 | 2050 | 36 ·22 | 47 0 events | +31% | 4.7× | Rising | |
| Broad Street Storm Overflow DCWW106 | 2050 | 168 ·22 | 40 0 events | -76% | 4× | Falling — behind | |
| Plough Lane Storm Overflow DCWW2323 | 2050 | 12 ·24 | 40 0 events | +233% | 4× | Rising | |
| Pontrilas Wwtw Storm Overflow DCWW2276 | 2050 | 65 ·22 | 37 0 events | -43% | 3.7× | Falling — behind | |
| Bryngwenin Overflow DCWW682 | 2050 | 123 ·22 | 35 0 events | -72% | 3.5× | Falling — behind | |
| St. Martins Allotments Storm Overflow DCWW754 | 2050 | 29 ·22 | 31 0 events | +7% | 3.1× | Rising | |
| Newland Wwtw No1 Storm Overflow DCWW2155 | 2050 | 35 ·22 | 29 0 events | -17% | 2.9× | Falling — behind | |
| Wyebank Road Storm Overflow DCWW468 | 2050 | 17 ·22 | 28 0 events | +65% | 2.8× | Rising | |
| Moccas Wwtw Storm Overflow DCWW850 | 2050 | 30 ·22 | 21 0 events | -30% | 2.1× | Falling — behind | |
| Ross Lower Cleeve Storm Overflow DCWW1782 | 2050 | 7 ·22 | 21 0 events | +200% | 2.1× | Rising | |
| Tintern Main Road Storm Overflow DCWW710 | 2050 | 210 ·22 | 20 0 events | -90% | 2× | Falling — behind | |
| Glasbury Wwtw Storm Overflow DCWW2332 | 2050 | 3 ·22 | 20 0 events | +567% | 2× | Rising | |
| Church Lane Storm Overflow DCWW654 | 2050 | 67 ·22 | 18 0 events | -73% | 1.8× | Falling — behind | |
| Mathern Storm Overflow DCWW1865 | 2050 | 2 ·22 | 17 0 events | +750% | 1.7× | Rising | |
| Greyfriars Bridge Storm Overflow DCWW2007 | 2050 | 122 ·22 | 15 0 events | -88% | 1.5× | Nearly there | |
| Longtown Storm Overflow DCWW879 | 2050 | 10 ·22 | 12 0 events | +20% | 1.2× | Rising | |
| Peterchurch Wwtw Storm Overflow DCWW2156 | 2050 | 12 ·22 | 12 0 events | 0% | 1.2× | Nearly there | |
| Barton Road Storm Overflow DCWW706 | 2050 | 9 ·22 | 6 0 events | -33% | 0.6× | Within the cap | |
| Smallbrook Road Storm Overflow DCWW1405 | 2050 | 0 ·22 | 3 0 events | — | 0.3× | Within the cap | |
| Lydbrook Storm Overflow DCWW246 | 2050 | 2 ·22 | 3 0 events | +50% | 0.3× | Within the cap | |
| Raglan Way Storm Overflow DCWW1421 | 2050 | 3 ·22 | 1 0 events | -67% | 0.1× | Within the cap | |
| Lower Lydbrook Storm Overflow DCWW249 | 2050 | 0 ·22 | 1 0 events | — | 0.1× | Within the cap | |
| Ashburton Road Ross-on-wye Overflow DCWW1383 | 2050 | 1 ·22 | 0 0 events | -100% | 0× | Within the cap | |
| Leymans Field Overflow DCWW916 | 2050 | 0 ·22 | 0 0 events | — | 0× | Within the cap | |
| Pandy Wwtw Inlet Overflow. DCWW1450 | 2050 | 52 ·22 | 0 0 events | -100% | 0× | Within the cap |
What this is — and what it is not
This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2020 baseline and the 10/year cap. Counted spills use the standard 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →