Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme (England) and National Environment Programme (Wales) is how the Environment Agency and Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the EA and NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

114
Measures in this catchment
WINEP and NEP, current record
86
Still active
not yet past their date
28
Assumed complete
completion date has passed
21
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW101672a · 6beb1a17W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
llanddewi rhydderch
Complete 2025-26Water body only
08DC100226 · tU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Eardisley STW
Complete 2025-26EARDISLEY
08DC100227 · uU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Eardisley STW
Complete 2025-26EARDISLEY
08DC100227 · vU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
EIGN STW
Complete 2025-26Wye - Bredwardine Br to Hampton Bishop
08DC100226 · uU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
EIGN STW
Complete 2025-26Wye - Bredwardine Br to Hampton Bishop
08DC100227 · pU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
FOWNHOPE STW
Complete 2025-26FOWNHOPE
08DC100226 · pU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
FOWNHOPE STW
Complete 2025-26FOWNHOPE
08DC100226 · bU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Lower Cleeve STW Ross on Wye
Complete 2025-26Wye - Hampton Bishop to conf Kerne Br
08DC100227 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Lower Cleeve STW Ross on Wye
Complete 2025-26Wye - Hampton Bishop to conf Kerne Br
08DC100226 · cU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Lydbrook STW
Complete 2025-26Wye - conf Walford Bk to Bigsweir Br
08DC100227 · lU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Lydbrook STW
Complete 2025-26Wye - conf Walford Bk to Bigsweir Br
08DC100227 · nU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Newland STW
Complete 2025-26Wye - conf Walford Bk to Bigsweir Br
08DC100226 · gU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Newland STW
Complete 2025-26Wye - conf Walford Bk to Bigsweir Br
08DC100226 · hU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Peterchurch STW
Complete 2025-26PETERCHURCH
08DC100227 · dU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Peterchurch STW
Complete 2025-26PETERCHURCH
08DC100227 · eU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
PONTRILAS STW
Complete 2025-26PONTRILAS
08DC100226 · iU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
PONTRILAS STW
Complete 2025-26PONTRILAS
08DC100227 · qU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
ROTHERWAS STW
Complete 2025-26Wye - Bredwardine Br to Hampton Bishop
08DC100226 · jU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Ruardean STW
Complete 2025-26Wye - conf Walford Bk to Bigsweir Br
08DC100227 · fU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Ruardean STW
Complete 2025-26Wye - conf Walford Bk to Bigsweir Br
08DC100226 · abU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Wilton SPS
Complete 2025-26WILTON
08DC100227 · acU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Wilton SPS
Complete 2025-26WILTON
DCWW100217a · baa64d49W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
GLASBURY STW GLASBURY NR HAY ON WYE
Complete 2025-26Glasbury WwTW Settled Storm Overflow
DCWW100300a · ad6cdb79W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLYSWEN STW CHURCH ROAD LLYSWEN
Complete 2025-26Llyswen WwTW Storm Overflow
DCWW100305a · 97529188W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
MANORBIER TRANSFER PS MANORBIER
Complete 2025-26Wyesham Monmouth WwTW Storm Overflow
DCWW100311a · 49e89560W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
MONMOUTH STW REDBROOK ROAD MONMOUTH
Complete 2025-26Wyesham Monmouth WwTW Storm Overflow
DCWW100324a · 53362d0dW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PANDY STW PANDY MONMOUTHSHIRE
Complete 2025-26Pandy WwTW Inlet Overflow.
DCWW100103a · c7728eadW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TINTERN STW
Complete 2025-26Tintern WwTW Overflow
08DC100232 · aWFD_NDINV_WRFlowInvestigation
Investigation into unused abstraction licence at Alton Court borehole
Alton Court borehole investigation
Due 2026-27Rudhall Bk - source to conf R Wye
08DC100226 · adU_MON3Monitoring
MCERTS certified overflow operation monitor (U_MON3b)
Homs Road PS CSO
Due 2026-27Wye - Hampton Bishop to conf Kerne Br
08DC100227 · adU_MON4Monitoring
U_MON4c - install flow meter inc civils
Homs Road PS CSO
Due 2026-27Wye - Hampton Bishop to conf Kerne Br
08DC100228 · aWFD_NDINV_WRFlowInvestigation
Investigation into abstraction licence - Vowchurch boreholes
Vowchurch boreholes
Due 2026-27Dore - source to conf R Monmow
DCWW102189a · a3beb223W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CHEPSTOW NORTH PS EOF
Due 2026-27Chepstow North Storm Overflow
08DC100014 · aU_IMP6Improvement
Increase storm tank capacity as per criteria
Hereford Eign WWTW
Due 2026-27Wye - Bredwardine Br to Hampton Bishop
DCWW101675a · 8d975d51W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
Llanvapley
Due 2026-27Water body only
DCWW102118a · 0b4e6be3W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
MONMOUTH 2
Due 2026-27North Hillcrest Road Monmouth Overflow
08DC100239 · cf25YEP_INVInvestigation
Investigations to reduce storm overflow spills at BARTON_ROAD_COMBINED_SEWER_OVERFLOW to protect the environment so that they have no local adverse ecological impact.
BARTON_ROAD_COMBINED_SEWER_OVERFLOW
Due 2027-28Yazor Bk - source to conf R Wye
08DC100239 · cg25YEP_INVInvestigation
Investigations to reduce storm overflow spills at BELMONT_ROUNDABOUT_CSO to protect the environment so that they have no local adverse ecological impact.
BELMONT_ROUNDABOUT_CSO
Due 2027-28Wye - Bredwardine Br to Hampton Bishop
08DC100239 · ch25YEP_INVInvestigation
Investigations to reduce storm overflow spills at BRAMPTON_STREET_CSO to protect the environment so that they have no local adverse ecological impact.
BRAMPTON_STREET_CSO
Due 2027-28Rudhall Bk - source to conf R Wye
08DC100239 · ci25YEP_INVInvestigation
Investigations to reduce storm overflow spills at CAWDOR_ARCH_COMBINED_SEWER_OVERFLOW to protect the environment so that they have no local adverse ecological impact.
CAWDOR_ARCH_COMBINED_SEWER_OVERFLOW
Due 2027-28Rudhall Bk - source to conf R Wye
08DC100239 · cj25YEP_INVInvestigation
Investigations to reduce storm overflow spills to protect the environment so that they have no local adverse ecological impact.
EIGN_1B_COMBINED_SEWER_OVERFLOW
Due 2027-28Wye - Bredwardine Br to Hampton Bishop
08DC100239 · ck25YEP_INVInvestigation
Investigations to reduce storm overflow spills at EIGN_WASTEWATER_TREATMENT_WORKS to protect the environment so that they have no local adverse ecological impact.
EIGN_WASTEWATER_TREATMENT_WORKS
Due 2027-28Wye - Bredwardine Br to Hampton Bishop
08DC100239 · ce25YEP_INVInvestigation
Investigations to reduce storm overflow spills to protect the environment so that they have no local adverse ecological impact.
ELMS_ROAD_COMBINED_SEWER_OVERFLOW
Due 2027-28Yazor Bk - source to conf R Wye
08DC100239 · cl25YEP_INVInvestigation
Investigations to reduce storm overflow spills at FOWNHOPE_SEWAGE_TREATMENT_WORKS to protect the environment so that they have no local adverse ecological impact.
FOWNHOPE_SEWAGE_TREATMENT_WORKS
Due 2027-28FOWNHOPE
08DC100239 · cm25YEP_INVInvestigation
Investigations to reduce storm overflow spills at GRANDSTAND_ROAD_CSO to protect the environment so that they have no local adverse ecological impact.
GRANDSTAND_ROAD_CSO
Due 2027-28Ferndale Road Storm Overflow
08DC100239 · cn25YEP_INVInvestigation
Investigations to reduce storm overflow spills at GREAT_HOUGH_BROOK_CSO to protect the environment so that they have no local adverse ecological impact.
GREAT_HOUGH_BROOK_CSO
Due 2027-28Wye - conf Walford Bk to Bigsweir Br
08DC100239 · co25YEP_INVInvestigation
Investigations to reduce storm overflow spills at GREYFRIARS_BRIDGE_CSO to protect the environment so that they have no local adverse ecological impact.
GREYFRIARS_BRIDGE_CSO
Due 2027-28Wye - Bredwardine Br to Hampton Bishop
08DC100239 · cp25YEP_INVInvestigation
Investigations to reduce storm overflow spills at HOMS_ROAD_PUMPING_STATION_CSO to protect the environment so that they have no local adverse ecological impact.
HOMS_ROAD_PUMPING_STATION_CSO
Due 2027-28Wye - Hampton Bishop to conf Kerne Br
08DC100239 · cq25YEP_INVInvestigation
Investigations to reduce storm overflow spills to protect the environment so that they have no local adverse ecological impact.
HOPE_AND_ANCHOR_CSO
Due 2027-28Wye - Hampton Bishop to conf Kerne Br
08DC100239 · cr25YEP_INVInvestigation
Investigations to reduce storm overflow spills at JOYFORD_MILL_PUMPING_STATION to protect the environment so that they have no local adverse ecological impact.
JOYFORD_MILL_PUMPING_STATION
Due 2027-28Wye - conf Walford Bk to Bigsweir Br
08DC100239 · cs25YEP_INVInvestigation
Investigations to reduce storm overflow spills at LOWER_LYDBROOK_RIVER_WYE_CSO to protect the environment so that they have no local adverse ecological impact.
LOWER_LYDBROOK_RIVER_WYE_CSO
Due 2027-28Wye - conf Walford Bk to Bigsweir Br
08DC100239 · ct25YEP_INVInvestigation
Investigations to reduce storm overflow spills at LYDBROOK_SEWAGE_TREATMENT_WORKS_SSO to protect the environment so that they have no local adverse ecological impact.
LYDBROOK_SEWAGE_TREATMENT_WORKS_SSO
Due 2027-28Wye - conf Walford Bk to Bigsweir Br
08DC100239 · cu25YEP_INVInvestigation
Investigations to reduce storm overflow spills at MISS_CHAVES_COMBINED_SEWER_OVERFLOW to protect the environment so that they have no local adverse ecological impact.
MISS_CHAVES_COMBINED_SEWER_OVERFLOW
Due 2027-28Yazor Bk - source to conf R Wye
08DC100239 · cv25YEP_INVInvestigation
Investigations to reduce storm overflow spills at NEWLAND_SEWAGE_TREATMENT_WORKS to protect the environment so that they have no local adverse ecological impact.
NEWLAND_SEWAGE_TREATMENT_WORKS
Due 2027-28Wye - conf Walford Bk to Bigsweir Br
08DC100239 · bu25YEP_INVInvestigation
Investigations to reduce storm overflow spills at PETERCHURCH_WASTEWATER_TREATMENT_WK to protect the environment so that they have no local adverse ecological impact.
PETERCHURCH_WASTEWATER_TREATMENT_WK
Due 2027-28PETERCHURCH
08DC100239 · bv25YEP_INVInvestigation
Investigations to reduce storm overflow spills at PONTRILAS_WASTEWATER_TREATMENT_WRKS to protect the environment so that they have no local adverse ecological impact.
PONTRILAS_WASTEWATER_TREATMENT_WRKS
Due 2027-28PONTRILAS
08DC100239 · cw25YEP_INVInvestigation
Investigations to reduce storm overflow spills at PUMPING_STATION_AT_MOCCAS_STW to protect the environment so that they have no local adverse ecological impact.
PUMPING_STATION_AT_MOCCAS_STW
Due 2027-28Preston Bk - source to conf R Wye
08DC100239 · cx25YEP_INVInvestigation
Investigations to reduce storm overflow spills at ROSS_LOWER_CLEEVE_WWTW to protect the environment so that they have no local adverse ecological impact.
ROSS_LOWER_CLEEVE_WWTW
Due 2027-28Wye - Hampton Bishop to conf Kerne Br
08DC100239 · cy25YEP_INVInvestigation
Investigations to reduce storm overflow spills at RUARDEAN_STW to protect the environment so that they have no local adverse ecological impact.
RUARDEAN_STW
Due 2027-28Wye - conf Walford Bk to Bigsweir Br
08DC100239 · da25YEP_INVInvestigation
Investigations to reduce storm overflow spills at SPS_AT_EARDISLEY_STW to protect the environment so that they have no local adverse ecological impact.
SPS_AT_EARDISLEY_STW
Due 2027-28Willersley Bk - source to conf R Wye
08DC100239 · dc25YEP_INVInvestigation
Investigations to reduce storm overflow spills at ST_MARTINS_ALLOTMENTS_CSO__HEREFORD to protect the environment so that they have no local adverse ecological impact.
ST_MARTINS_ALLOTMENTS_CSO__HEREFORD
Due 2027-28Wye - Bredwardine Br to Hampton Bishop
08DC100239 · dd25YEP_INVInvestigation
Investigations to reduce storm overflow spills at STATION_ST_COMBINED_SEWER_OVERFLOW to protect the environment so that they have no local adverse ecological impact.
STATION_ST_COMBINED_SEWER_OVERFLOW
Due 2027-28Rudhall Bk - source to conf R Wye
08DC100239 · de25YEP_INVInvestigation
Investigations to reduce storm overflow spills at THREE_ELMS_ROAD_CSO to protect the environment so that they have no local adverse ecological impact.
THREE_ELMS_ROAD_CSO
Due 2027-28Yazor Bk - source to conf R Wye
08DC100239 · df25YEP_INVInvestigation
Investigations to reduce storm overflow spills at WHITECROSS_ROAD_CSO__HEREFORD to protect the environment so that they have no local adverse ecological impact.
WHITECROSS_ROAD_CSO__HEREFORD
Due 2027-28Wye - Bredwardine Br to Hampton Bishop
08DC100239 · dg25YEP_INVInvestigation
Investigations to reduce storm overflow spills at WILTON_SEWAGE_PUMPING_STATION to protect the environment so that they have no local adverse ecological impact.
WILTON_SEWAGE_PUMPING_STATION
Due 2027-28WILTON
08DC100002 · aU_IMP7Improvement
Upgrade septic tank primary treated effluent to secondary treated effluent capable of delivering 40/60 BOD/SS
ORCOP Septic Tank
Due 2027-28Garren Bk - source to conf Gamber Bk
DCWW100721a · 4a94c283W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BOUGHROOD PS
Due 2029-30Water body only
DCWW100773a · 97da98b6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BRIDLEWAY SPS, CROSSWAY GREEN, CHEPSTOW
Due 2029-30Water body only
DCWW100840a · ae5101c6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Bryn-Y-Gwenin SPS, Nr Abergavenny
Due 2029-30Bryngwenin Overflow
DCWW100821a · 28e87e3cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CHEPSTOW NORTH (FAIRFIELD) SEWAGE PUMPING STATION, CHEPSTOW
Due 2029-30Chepstow Fairfield Storm Overflow
DCWW100822a · 2f19d012W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CHEPSTOW NORTH SEWAGE PUMPING STATION, THE BACK, CHEPSTOW
Due 2029-30Chepstow North Storm Overflow
DCWW100824a · 5f59e8feW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CHEPSTOW SOUTH SEWAGE PUMPING STATION, HUNGER PILL STW SITE, CHEPSTOW
Due 2029-30Hunger Pill Overflow
DCWW100755a · ad7ed5b7W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CHURCH LANE SEWAGE PUMPING STATION, LLYSWEN
Due 2029-30Church Lane Storm Overflow
08DC100147 · aWFD_IMPgImprovement
WWTW improvement under WFD - Permit values
Clehonger STW
Due 2029-30Cage Bk - source to conf R Wye
DCWW101582a · 54a41b5cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Welsh Street Chepstow
Due 2029-30Welsh Street Storm Overflow
DCWW101721a · f9a6bd29W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. for P and Ammonia
WQ
DINGESTOW STW DINGESTOW MONMOUTH
Due 2029-30Water body only
DCWW102561a · e47352b3W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
FAIRFIELD SPS CSO, Sedbury
Due 2029-30Chepstow Fairfield Storm Overflow
08DC100007 · aWFD_IMP_PHYSHABImprovement
Address impacts from water company owned / utilised structures that are creating a physical obstruction to migratory fish
Fish Barrier Mitigation at Asset no.
Due 2029-30Yazor Bk - source to conf R Wye
DCWW101725a · e43e6325W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
FRONCYSYLLTE STW
Due 2029-30LLANFIHANGEL PANDY
DCWW101689a · 2f22a2feW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
GLASBURY STW
Due 2029-30Water body only
DCWW101689b · b29bbb13W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
GLASBURY STW
Due 2029-30GLASBURY
DCWW101582a · 962c53acW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Glasbury STW Glasbury Nr Hay On Wye
Due 2029-30Glasbury WwTW Settled Storm Overflow
DCWW101730a · bcccb77dW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. for P and Ammonia
WQ
Grosmont Wastewater Treatment Works
Due 2029-30Water body only
DCWW100862a · 82aab958W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Hay on Wye (Warren Close) SPS
Due 2029-30Warren Close Overflow
DCWW100849a · ff0abea8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
HAY ON WYE SEWAGE PUMPING STATION
Due 2029-30Broad Street Storm Overflow
DCWW101582a · 64a9d355W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Hay-on-Wye (Warren Close) SPS
Due 2029-30Warren Close Overflow
DCWW102562a · e7e09376W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
HUNGER PILL PS EOF
Due 2029-30Hunger Pill Overflow
08DC100148 · aWFD_IMPgImprovement
WWTW improvement under WFD - Permit values
Kingstone & Madley STW
Due 2029-30Cage Bk - source to conf R Wye
08DC100153 · aWFD_IMPgImprovement
WWTW improvement under WFD - Permit values
Little Dewchurch
Due 2029-30Wriggle Bk - source to conf R Wye
DCWW101723a · 21121645W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLYSWEN SEWAGE TREATMENT WORKS
Due 2029-30Water body only
DCWW101723b · 495162bfW_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
LLYSWEN STW
Due 2029-30LLYSWEN VILLAGE
DCWW102341a · eed2d2f3W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llyswen STW CSO
Due 2029-30Church Lane Storm Overflow
DCWW102301a · 2ff563dcW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLYSWEN VILLAGE CHURCH LANE PS
Due 2029-30Church Lane Storm Overflow
DCWW101446a · 62c21d93W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Mathern Sewage Pumping Station, Mathern Village, Chepstow
Due 2029-30Mathern Storm Overflow
DCWW101582a · c518622cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Mathern SPS
Due 2029-30Mathern Storm Overflow
DCWW100743b · a60a34e5W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
MONMOUTH STW
Due 2029-30MONMOUTH STW STW
DCWW102287a · dcc8ed46W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
MONMOUTH TOWN PS
Due 2029-30Blestium Street Monmouth Storm Overflow
DCWW100743a · 0c2c9bc9W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MONMOUTH TOWN PUMPING STATION
Due 2029-30Blestium Street Monmouth Storm Overflow
DCWW100744a · f295edccW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MONMOUTH WYEBRIDGE SPS
Due 2029-30North Hillcrest Road Monmouth Overflow
08DC100154 · aWFD_IMPgImprovement
WWTW improvement under WFD - Permit values
Much Dewchurch STW
Due 2029-30MUCH DEWCHURCH
DCWW100859a · 8910c0e5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
OSBASTON PUMPING STATION
Due 2029-30Water body only
DCWW101731a · 0b965b88W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
PANDY STW PANDY MONMOUTHSHIRE
Due 2029-30LLANFIHANGEL PANDY
DCWW101731b · 2c1c7f53W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
PANDY STW  PANDY  MONMOUTHSHIRE
Due 2029-30LLANFIHANGEL PANDY
DCWW102237a · 848547afW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pandy STW Overflow SO
Due 2029-30Pandy WwTW Inlet Overflow.
DCWW101944a · ef6b0e51W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Pandy WwTW
Due 2029-30Pandy WwTW Inlet Overflow.
DCWW101582a · c95ec6b3W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pwllmeyric SPS (CSO)
Due 2029-30Pwllmeyric Storm Overflow
DCWW102559a · 848d220eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RAGLAN WAY CSO, CHEPSTOW
Due 2029-30Raglan Way Storm Overflow
DCWW100858a · 9cf37455W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ROSS LOWER CLEEVE WWTW in England
Due 2029-30Ross Lower Cleeve Storm Overflow
DCWW101582a · 862484e7W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Thornwell Road CSO
Due 2029-30Raglan Way Storm Overflow
DCWW101469a · a60b9183W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Tintern Main SPS
Due 2029-30Tintern Main Road Storm Overflow
DCWW100852a · af789465W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
UPPER REDBROOK PUMPING STATION, ADJ TO A466 OPP BUSH HOUSE, REDBROOK
Due 2029-30Water body only
DCWW101582a · b5a36a33W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
WARREN SLADE SEWAGE PUMPING STATION
Due 2029-30Raglan Way Storm Overflow
DCWW101447a · 0aa2d58bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Warren Slade SPS, opp No 13 Bluebell Drive, Bulwark, Chepstow, NP16 5TP
Due 2029-30Raglan Way Storm Overflow
08DC100149 · aWFD_IMPgImprovement
WWTW improvement under WFD - Permit values
Woolhope Village STW
Due 2029-30How Caple Bk - source to conf R Wye

114 of 114 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.