Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

16
Measures in this catchment
WINEP, current record
16
Still active
not yet past their date
0
Assumed complete
completion date has passed
3
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104749 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Liskeard (Lodge Hill) STW
Due 2026-27East Looe River
08SW104750 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Liskeard (Lodge Hill) STW
Due 2026-27East Looe River
08SW104729 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
MENHENIOT STW
Due 2026-27Seaton
08SW104728 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
MENHENIOT STW
Due 2026-27Seaton
08SW104681 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Pelynt STW
Due 2026-27Polperro River
08SW104680 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Pelynt STW
Due 2026-27Polperro River
08SW104615 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
ST CLEER STW
Due 2026-27Seaton
08SW104616 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
ST CLEER STW
Due 2026-27Seaton
08SW104543 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
WIDEGATES STW
Due 2026-27Seaton
08SW104544 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WIDEGATES STW
Due 2026-27Seaton
08SW102001 · dWFD_NDLS_Chem1No deterioration
Cypermethrin standstill permit limit
LODGEHILL_STW_LISKEARD
Due 2026-27East Looe River
08SW102004 · aWFD_NDLS_Chem2No deterioration
Zinc (dissolved) permit limit
LODGEHILL_STW_LISKEARD
Due 2026-27East Looe River
08SW104999 · arEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
CROWS NEST STW_SO_DARITE
Due 2027-28CROWS NEST STW_SO_DARITE
08SW101426 · aEnvAct_IMP3Improvement
Reduction of spills to meet EnvAct_IMP drivers
BONE MILL SPS_PSCSOEO_LOOE
Due 2029-30BONE MILL SPS_PSCSOEO_LOOE
08SW101434 · aEnvAct_IMP3Improvement
Reduction of spills to meet EnvAct_IMP drivers
BULLER QUAY_CSO_LOOE
Due 2029-30BULLER QUAY_CSO_LOOE
08SW101666 · aEnvAct_IMP3Improvement
Reduction of spills to meet EnvAct_IMP drivers
WEST LOOE QUAY_CSO_LOOE
Due 2029-30WEST LOOE QUAY_CSO_LOOE

16 of 16 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.