What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SW104749 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Liskeard (Lodge Hill) STW | Due 2026-27 | East Looe River |
| 08SW104750 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Liskeard (Lodge Hill) STW | Due 2026-27 | East Looe River |
| 08SW104729 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) MENHENIOT STW | Due 2026-27 | Seaton |
| 08SW104728 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) MENHENIOT STW | Due 2026-27 | Seaton |
| 08SW104681 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Pelynt STW | Due 2026-27 | Polperro River |
| 08SW104680 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) Pelynt STW | Due 2026-27 | Polperro River |
| 08SW104615 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) ST CLEER STW | Due 2026-27 | Seaton |
| 08SW104616 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) ST CLEER STW | Due 2026-27 | Seaton |
| 08SW104543 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) WIDEGATES STW | Due 2026-27 | Seaton |
| 08SW104544 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) WIDEGATES STW | Due 2026-27 | Seaton |
| 08SW102001 · d | WFD_NDLS_Chem1 | No deterioration | Cypermethrin standstill permit limit LODGEHILL_STW_LISKEARD | Due 2026-27 | East Looe River |
| 08SW102004 · a | WFD_NDLS_Chem2 | No deterioration | Zinc (dissolved) permit limit LODGEHILL_STW_LISKEARD | Due 2026-27 | East Looe River |
| 08SW104999 · ar | EnvAct_INV4 | Investigation | Investigation to meet EnvAct INV4 Driver CROWS NEST STW_SO_DARITE | Due 2027-28 | CROWS NEST STW_SO_DARITE |
| 08SW101426 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers BONE MILL SPS_PSCSOEO_LOOE | Due 2029-30 | BONE MILL SPS_PSCSOEO_LOOE |
| 08SW101434 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers BULLER QUAY_CSO_LOOE | Due 2029-30 | BULLER QUAY_CSO_LOOE |
| 08SW101666 · a | EnvAct_IMP3 | Improvement | Reduction of spills to meet EnvAct_IMP drivers WEST LOOE QUAY_CSO_LOOE | Due 2029-30 | WEST LOOE QUAY_CSO_LOOE |
16 of 16 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.