Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

52
Measures in this catchment
NEP, current record
43
Still active
not yet past their date
9
Assumed complete
completion date has passed
6
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100246a · ed8df738W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANBRYNMAIR STW LLANBRYNMAIR
Complete 2025-26Llanddarog Overflow
DCWW100247a · 91a95063W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANDDAROG WWTW LLANDDAROG CARMARTH
Complete 2025-26Llanddarog Overflow
DCWW100279a · 6d14d370W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANGYNDEYRN STW
Complete 2025-26Llangyndeyrn WwTW Storm Overflow
DCWW100326a · 1c528865W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PEMBREY WASTEWATER TREATMENT WORKS
Complete 2025-26Pembrey WwTW Storm Overflow
DCWW100340a · a3dc80e0W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PONT HENRI INCLINE CSO (PONTYATES 1 of 3)
Complete 2025-26Ponthenri Storm Overflow
DCWW100346a · 097d92dbW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PONTYATES SPS
Complete 2025-26Pontyates Heol Y Meinciau Storm Overflow
DCWW100347a · 2e05c595W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PONTYBEREM WWTW PONTYBEREM CARMS
Complete 2025-26Pontyberem WwTW Storm Overflow
DCWW100398a · 3a5ab5f2W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TRIMSARAN WWTW SPUDDER BRIDGE RD
Complete 2025-26Trimsaran WwTW Inlet Storm Overflow
DCWW100400a · 01db4721W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TY COCH SPS
Complete 2025-26Tycoch Storm Overflow
DCWW101582a · 6def5c0dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Ashburnham Road CSO
Due 2029-30Burry Port Ashburnham Road Storm Overflow
DCWW101135a · bc5d6503W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ASHBURNHAM SPS, BURRY PORT
Due 2029-30Ashburnham Storm Overflow
DCWW101476a · 5f28ba43W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Burry Port PS
Due 2029-30Burry Port Shoreline Overflow
DCWW101975a · f24b77afW_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Cefneithin - Blaenhirwaun
Due 2029-30Carmarthen Road Cefneithin Storm Overflow
DCWW102405a · 0f6bcccdW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cefneithin Road CSO, Ddol Las
Due 2029-30Cefneithin Road Ddol Las Storm Overflow
DCWW100880a · 03a8d72fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CWM CAPEL PS BURRY PORT
Due 2029-30Cwm Capel Overflow
DCWW102433a · 7f56b995W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cwm Mawr - Gwendraeth Arms
Due 2029-30Cwm Mawr Heol Cwmbach Storm Overflow
DCWW100940a · 72861733W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Garn Farm PSEO
Due 2029-30Water body only
DCWW101133a · 2e2a4ff0W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GARREG SEWAGE PUMPING STATION
Due 2029-30Kidwelly Garreg Storm Overflow
DCWW101477a · 95a70b60W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Heol ddu SPS
Due 2029-30Heol Ddu Storm Overflow
DCWW101582a · 53b4d003W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Heol Ddu SPS
Due 2029-30Heol Ddu Storm Overflow
DCWW101582a · 67c54d1cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
HEOL NAZARETH 2 CSO
Due 2029-30Next to Heol Y Meinciau Bridge Pontyates Storm Overflow
DCWW101582a · e34263e1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
HEOL WAUN Y CLUN CSO TRIMSARAN
Due 2029-30Trimsaran Heol Llanelli Storm Overflow
DCWW102426a · 86e00009W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
HEOL Y BRYN CSO, PONTYBEREM
Due 2029-30Heol Y Bryn Storm Overflow
DCWW102437a · 626bdf56W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
KIDWELLY GARREG PS
Due 2029-30Kidwelly Garreg Storm Overflow
DCWW101582a · b691afceW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LINKS PEMBREY PS EMERG , ,
Due 2029-30Pembrey Links Storm Overflow
DCWW100943a · 8feaadfaW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LINKS PEMBREY PS EMERGENCY
Due 2029-30Pembrey Links Storm Overflow
DCWW100633a · 2187e68eW_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANDDAROG
Due 2029-30Llanddarog Overflow
DCWW102246a · 4b284f00W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANDDAROG SPS CSO
Due 2029-30Llanddarog Storm Overflow
DCWW101474a · 03addd47W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDDAROG STW, LLANDDAROG, CARMARTHEN, DYFED
Due 2029-30Llanddarog Overflow
DCWW100698a · 5070f648W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANGYNDEYRN
Due 2029-30Llangyndeyrn WwTW Storm Overflow
DCWW102708a · 12d9c3a9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANGYNDEYRN PS INTO R GWENDRAETH FACH
Due 2029-30Llangyndeyrn Storm Overflow
DCWW100705a · 807de8b3W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Maes y Capel SPS, Maes y Capel, Pembrey, Carmarthenshire, SA16 0EG
Due 2029-30Burry Port Ashburnham Road Storm Overflow
DCWW100868a · cb8cd530W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Mynnydd Cerrig PS
Due 2029-30Mynydd Cerrig Storm Overflow
DCWW101128a · b08a65c5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
New Pontyberem PS CSO
Due 2029-30Pontyberem Storm Overflow
DCWW101582a · 82f94642W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Parc y Dai CSO
Due 2029-30Parc y Dai No 2 Drefach Storm Overflow
DCWW101582a · e66ead00W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Parc Y Dai No1 CSO Drefach
Due 2029-30Parc y Dai No1 Drefach Storm Overflow
DCWW101968a · b53c9a1eW_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Parc y-Dai No1 CSO, Drefach
Due 2029-30Parc y Dai No1 Drefach Storm Overflow
DCWW101582a · 0adc5f42W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PEMBREY WWTW CSO
Due 2029-30Pembrey WwTW Storm Overflow
DCWW102435a · b1e5eef1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Ponthenri - Felin Fach
Due 2029-30Ponthenri Storm Overflow
DCWW102436a · 62f5ac65W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pontyates - Opp.Fire Station
Due 2029-30Pontyates Heol Y Meinciau Storm Overflow
DCWW102425a · b08b893fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PONTYATES ABOVE MAIN ROAD BRIDGE INTO GW
Due 2029-30Next to Heol Y Meinciau Bridge Pontyates Storm Overflow
DCWW100870a · b05a63c8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Pontyates SPS, Pontyates
Due 2029-30Next to Heol Y Meinciau Bridge Pontyates Storm Overflow
DCWW101977a · d1e46768W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Pontyberem No2 SPS
Due 2029-30Pontyberem Storm Overflow
DCWW102434a · 14dd3a9bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pontyberem STW CSO
Due 2029-30Pontyberem WwTW Inlet Storm Overflow
DCWW102245a · 67fb64a4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PORTHYRHYD PS INTO TRIBUTARY OF GWENDRAE
Due 2029-30Porthyrhyd Storm Overflow
DCWW101582a · fc977503W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Settled Storm Overflow at Llanddarog Wastewater Treatment Works
Due 2029-30Llanddarog Overflow
DCWW101582a · c76fbd06W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Settled Storm Overflow at Llangyndeyrn Wastewater Treatment Works
Due 2029-30Llangyndeyrn WwTW Storm Overflow
DCWW100881a · 42eb9a25W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
SHORELINE PS BURRY PORT
Due 2029-30Burry Port Shoreline Overflow
DCWW100878a · 2d63fc80W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
SSO AT STATION ROAD P.S. KIDWELL
Due 2029-30Station Road Kidwelly Overflow
DCWW101976a · dfa47dbcW_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Tom Jones Nursery CSO
Due 2029-30Cefneithin Road Gorslas Storm Overflow
DCWW102407a · bab3fb2dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Tumble - 27 Rhosnewydd
Due 2029-30Rhosnewydd Tumble Storm Overflow
DCWW101134a · 79e0b586W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TYCOCH SEWAGE PUMPING STATION, KIDWELLY
Due 2029-30Tycoch Storm Overflow

52 of 52 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.