Reduction tracker
Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.
What the plan is, and what it leaves out
The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:
- By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
- By 2045 — the remaining high-priority overflows.
- By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.
The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the Environment Agency's EDM record: each overflow's counted spills per year — the EA's own 12/24-hour block figure, the same basis the cap is written in — against its 2020 baseline and the 2050 cap of ~10, with the deadline its location implies.
Every overflow against its cap
Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.
| Overflow | Deadline | Baseline | Latest | Since baseline | vs cap | Trajectory | Verdict |
|---|---|---|---|---|---|---|---|
| Church Hanborough STW TWL00098 | 2050 | 158 ·24 | 88 167 events | -44% | 8.8× | Falling — behind | |
| Primrose Court (moreton-in-marsh) pumping station TWL00726 | 2050 | 138 ·24 | 77 95 events | -44% | 7.7× | Falling — behind | |
| Milton-under-wychwood STW TWL00303 | 2050 | 152 ·24 | 67 62 events | -56% | 6.7× | Falling — behind | |
| Bledington STW TWL00042 | 2050 | 114 ·24 | 50 20 events | -56% | 5× | Falling — behind | |
| Chadlington STW TWL00079 | 2050 | 84 ·24 | 35 42 events | -58% | 3.5× | Falling — behind | |
| Combe STW TWL00110 | 2050 | 130 ·24 | 30 40 events | -77% | 3× | Falling — behind | |
| Little Compton STW TWL00268 | 2050 | 69 ·24 | 30 28 events | -57% | 3× | Falling — behind | |
| Broadwell STW TWL00057 | 2050 | 58 ·24 | 27 19 events | -53% | 2.7× | Falling — behind | |
| Woodstock STW TWL00462 | 2050 | 41 ·24 | 21 45 events | -49% | 2.1× | Falling — behind | |
| Chipping Norton STW TWL00094 | 2050 | 56 ·24 | 21 17 events | -63% | 2.1× | Falling — behind | |
| The Mill (kingham) pumping station TWL00252 | 2050 | 23 ·24 | 17 37 events | -26% | 1.7× | Falling — behind | |
| Middle Barton STW TWL00298 | 2050 | 44 ·24 | 15 18 events | -66% | 1.5× | Nearly there | |
| Finstock STW TWL00184 | 2050 | 38 ·24 | 13 12 events | -66% | 1.3× | Nearly there | |
| Moreton-in-marsh TWL00136 | 2050 | 10 ·24 | 9 15 events | -10% | 0.9× | Within the cap | |
| Charlbury STW TWL00083 | 2050 | 22 ·24 | 7 10 events | -68% | 0.7× | Within the cap | |
| Near Sezincote Lodge TWL00804 | 2050 | 28 ·24 | 4 1 events | -86% | 0.4× | Within the cap |
What this is — and what it is not
This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2020 baseline and the 10/year cap. Counted spills use the Environment Agency's 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →