What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08TW100558 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BLEDINGTON STW | Complete 2025-26 | Bledington STW |
| 08TW100565 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BROADWELL STW | Complete 2025-26 | Broadwell STW |
| 08TW100571 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CHADLINGTON STW | Complete 2025-26 | Chadlington STW |
| 08TW100573 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CHARLBURY STW | Complete 2025-26 | Charlbury STW |
| 08TW100702 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CHIPPING NORTON STW | Complete 2025-26 | Chipping Norton STW |
| 08TW100581 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CHURCH HANBOROUGH STW | Complete 2025-26 | Church Hanborough STW |
| 08TW100584 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) COMBE STW | Complete 2025-26 | Combe STW |
| 08TW100605 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) FINSTOCK STW | Complete 2025-26 | Finstock STW |
| 08TW100711 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) LITTLE COMPTON STW | Complete 2025-26 | Little Compton STW |
| 08TW100642 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) MIDDLE BARTON STW | Complete 2025-26 | Middle Barton STW |
| 08TW100644 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) MILTON UNDER WYCHWOOD STW | Complete 2025-26 | Littlestock Stream to tributary of Evenlode at Shipton |
| 08TW100645 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) MORETON IN MARSH STW (Last in Line Overflow off site) | Complete 2025-26 | Evenlode (Compton Bk to Bledington Bk) and 4 Shires |
| 08TW100725 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) SHOTTESWELL STW | Complete 2025-26 | Dorn (Source to Glyme) |
| 08TW100731 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) WOODSTOCK STW | Complete 2025-26 | Woodstock STW |
| 08TW100419 · a | U_MON4 | Monitoring | Install and run event-duration monitoring BLEDINGTON STW | Due 2026-27 | Bledington STW |
| 08TW100299 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) BROADWELL STW | Due 2026-27 | Broadwell STW |
| 08TW100422 · a | U_MON4 | Monitoring | Install and run event-duration monitoring CHADLINGTON STW | Due 2026-27 | Chadlington STW |
| 08TW101579 · a | U_MON4 | Monitoring | Install and run event-duration monitoring CHARLBURY STW | Due 2026-27 | Charlbury STW |
| 08TW100312 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) CHIPPING NORTON STW | Due 2026-27 | Chipping Norton STW |
| 08TW100315 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) CHURCH HANBOROUGH STW | Due 2026-27 | Church Hanborough STW |
| 08TW100427 · a | U_MON4 | Monitoring | Install and run event-duration monitoring COMBE STW | Due 2026-27 | Combe STW |
| 08TW101589 · a | U_MON4 | Monitoring | Install and run event-duration monitoring FINSTOCK STW | Due 2026-27 | Finstock STW |
| 08TW100359 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) LITTLE COMPTON STW | Due 2026-27 | Little Compton STW |
| 08TW101599 · a | U_MON4 | Monitoring | Install and run event-duration monitoring MIDDLE BARTON STW | Due 2026-27 | Middle Barton STW |
| 08TW101601 · a | U_MON4 | Monitoring | Install and run event-duration monitoring MILTON UNDER WYCHWOOD STW | Due 2026-27 | Littlestock Stream to tributary of Evenlode at Shipton |
| 08TW100444 · a | U_MON4 | Monitoring | Install and run event-duration monitoring MORETON IN MARSH STW (Last in Line Overflow off site) | Due 2026-27 | Evenlode (Compton Bk to Bledington Bk) and 4 Shires |
| 08TW100380 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) SHOTTESWELL STW | Due 2026-27 | Dorn (Source to Glyme) |
| 08TW100410 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) WOODSTOCK STW | Due 2026-27 | Woodstock STW |
| 08TW100489 · a | WFD_NDLS_Chem1 | No deterioration | Milton-under-Wychwood STW cypermethrin load standstill limit Milton-under-Wychwood STW | Due 2026-27 | Milton-Under-Wychwood STW |
| 08TW100092 · a | WFD_NDLS_Chem2 | No deterioration | Moreton-in-Marsh STW, cypermethrin, 0.000557 ug Reduce cypermethrin loading | Due 2026-27 | Evenlode (Compton Bk to Bledington Bk) and 4 Shires |
| 08TW100073 · a | WFD_NDLS_Chem2 | No deterioration | Church Hanborough STW, cypermethrin, 0.000819ug Reduce cypermethrin loading | Due 2026-27 | Evenlode (Glyme to Thames) |
| 08TW100475 · a | WFD_NDLS_Chem1 | No deterioration | Church Hanborough STW zinc load standstill permit limit Reduce metal loading at Church Hanborough STW | Due 2026-27 | Evenlode (Glyme to Thames) |
| 08TW100129 · a | WFD_NDLS_Chem2 | No deterioration | Moreton-in-Marsh STW, Nonylphenol, 0.48 ug Reduce Nonylphenol loading | Due 2026-27 | Evenlode (Compton Bk to Bledington Bk) and 4 Shires |
| 08TW101108 · tj | EnvAct_INV4 | Investigation | Storm Overflows investigation LITTLE COMPTON STW- Storm Overflows investigation | Due 2027-28 | Little Compton Brook and tributaries (Source to Evenlode) |
| 08TW101108 · ah | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at BLEDINGTON STW | Due 2027-28 | Evenlode (Bledington to Glyme confluence) |
| 08TW101108 · am | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at CHADLINGTON STW | Due 2027-28 | Evenlode (Bledington to Glyme confluence) |
| 08TW101108 · at | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at COMBE STW | Due 2027-28 | Evenlode (Bledington to Glyme confluence) |
| 08TW100204 · a | WFD_INV | Investigation | Investigate the cause of the spills WFD Investigation of in river Dissolved Oxygen to inform future action | Due 2027-28 | Westcote Brook (source to Evenlode at Bledington) |
| 08TW101108 · tr | EnvAct_INV4 | Investigation | Storm Overflows investigation WOODSTOCK STW- Storm Overflows investigation | Due 2027-28 | Glyme (Dorn confluence to Evenlode) |
| 08TW100879 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Broadwell STW Broadwell STW Phosphorus load recution | Due 2029-30 | Evenlode (Compton Bk to Bledington Bk) and 4 Shires |
| 08TW100488 · a | WFD_ND_CHEM3 | No deterioration | Middleton Cheney STW cypermethrin no det and load standstill limit Middleton Cheney STW | Due 2029-30 | Littlestock Stream to tributary of Evenlode at Shipton |
| 08TW100950 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Ash Ridge (Wokingham) STW also known as Wokingham STW Reduce Phosphorus Loadings at Ash Ridge (Wokingham) STW | Due 2029-30 | Glyme (Dorn confluence to Evenlode) |
| 08TW100873 · a | EnvAct_IMP1 | Improvement | 1 mg/l Phosphorus permit at Bledington STW Reduce Phosphorus Loadings at Bledington STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW100883 · a | EnvAct_IMP1 | Improvement | 0.45 mg/l Phosphorus permit at Chadlington STW Reduce Phosphorus Loadings at Chadlington STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW100885 · a | EnvAct_IMP1 | Improvement | 2 mg/l Phosphorus permit at Charlbury STW Reduce Phosphorus Loadings at Charlbury STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW100888 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit with stretch target of 0.2 mg/l at Chipping Norton STW Reduce Phosphorus Loadings at Chipping Norton STW | Due 2029-30 | Cornwell Brook and tributaries (Source to Evenlode) |
| 08TW100889 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Church Hanborough STW Reduce Phosphorus Loadings at Church Hanborough STW | Due 2029-30 | Evenlode (Glyme to Thames) |
| 08TW101888 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Earlswood STW also known as Reigate STW Reduce Phosphorus Loadings at Earlswood STW | Due 2029-30 | Cornwell Brook and tributaries (Source to Evenlode) |
| 08TW100903 · a | EnvAct_IMP1 | Improvement | 0.6 mg/l Phosphorus permit at Finstock STW Reduce Phosphorus Loadings at Finstock STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW100916 · a | EnvAct_IMP1 | Improvement | 0.4 mg/l Phosphorus permit at Little Compton STW Reduce Phosphorus Loadings at Little Compton STW | Due 2029-30 | Little Compton Brook and tributaries (Source to Evenlode) |
| 08TW100918 · a | EnvAct_IMP1 | Improvement | 1 mg/l Phosphorus permit at Longborough STW Reduce Phosphorus Loadings at Longborough STW | Due 2029-30 | Evenlode (Source to Four Shires S) and Longborough Stream |
| 08TW100922 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Milton-Under-Wychwood STW Reduce Phosphorus Loadings at Milton-Under-Wychwood STW | Due 2029-30 | Littlestock Stream to tributary of Evenlode at Shipton |
| 08TW100923 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Moreton-in-Marsh STW Reduce Phosphorus Loadings at Moreton-in-Marsh STW | Due 2029-30 | Evenlode (Compton Bk to Bledington Bk) and 4 Shires |
| 08TW100982 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: 1,011m of sewer relining, 50m3 storage, 0.41Ha SUDS IA Removal, No screen required Storm Overflows action at BLEDINGTON STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW100989 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: 1,166m of sewer relining, 90m3 storage, 0.48Ha SUDS IA Removal, 20m3 screen Storm Overflows action at CHADLINGTON STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW101016 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: 1,400m of sewer relining, 0.57Ha SUDS IA Removal, 20m3 screen Storm Overflows action at CHARLBURY STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW100997 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: 648m of sewer relining, 0.26Ha SUDS IA Removal, No screen required Storm Overflows action at COMBE STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW101018 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: 639m3 storage, 20m3 screen Storm Overflows action at FINSTOCK STW | Due 2029-30 | Evenlode (Bledington to Glyme confluence) |
| 08TW101023 · a | EnvAct_IMP2 | Improvement | Option C1: Solution in AMP 08: 648m of sewer relining, 27m3 storage, 0.26Ha SUDS IA Removal, No screen required Storm Overflows action at LITTLE COMPTON STW | Due 2029-30 | Little Compton Brook and tributaries (Source to Evenlode) |
59 of 59 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.