Reduction tracker
Is each overflow actually spilling less? The reduction plan won't tell you per overflow — so we measure it from the spill record.
What the plan is, and what it leaves out
The Storm Overflows Discharge Reduction Plan is the government's plan — published in 2022 and expanded in September 2023 — to cut how often England's storm overflows discharge. It sets deadlines by category, not by overflow:
- By 2035 — overflows near every designated bathing water, and 75% of those near high-priority nature sites, must be improved.
- By 2045 — the remaining high-priority overflows.
- By 2050 — every storm overflow, with discharges capped at around 10 spills a year regardless of location.
The targets are due to be reviewed in 2027 — a commitment in the plan, not a statutory duty. But the plan sets no target for any individual overflow and publishes no per-overflow progress — only these whole-category deadlines, and it doesn't even publish which specific overflows are high-priority. So there is no official way to ask “is this overflow on track?” This page builds that view from the Environment Agency's EDM record: each overflow's counted spills per year — the EA's own 12/24-hour block figure, the same basis the cap is written in — against its 2020 baseline and the 2050 cap of ~10, with the deadline its location implies.
Every overflow against its cap
Ranked by the latest full year's spills. The deadline is derived from proximity to a designated site — indicative, not an official per-overflow target. The dotted line on each trajectory is the 10-spills cap.
| Overflow | Deadline | Baseline | Latest | Since baseline | vs cap | Trajectory | Verdict |
|---|---|---|---|---|---|---|---|
| Markyate STW TWL00292 | 2050 | 187 ·24 | 155 33 events | -17% | 15.5× | Falling — behind | |
| Gerrards Cross STW TWL00196 | 2050 | 144 ·24 | 88 68 events | -39% | 8.8× | Falling — behind | |
| Maple Lodge STW TWL00290 | 2050 | 124 ·24 | 35 22 events | -72% | 3.5× | Falling — behind | |
| Berkhamsted STW TWL00037 | 2050 | 157 ·24 | 35 48 events | -78% | 3.5× | Falling — behind | |
| Dagnall STW TWL00149 | 2050 | 53 ·24 | 17 20 events | -68% | 1.7× | Falling — behind | |
| Amersham Balancing Tanks/amersham Vale Stk TWL00009 | 2050 | 210 ·24 | 13 12 events | -94% | 1.3× | Nearly there | |
| Darkes Lane, Potters Bar TWL00545 | 2050 | 18 ·24 | 9 20 events | -50% | 0.9× | Within the cap | |
| Chesham STW TWL00089 | 2050 | 141 ·24 | 7 9 events | -95% | 0.7× | Within the cap | |
| Caddington STW TWL00068 | 2050 | 32 ·24 | 5 4 events | -84% | 0.5× | Within the cap | |
| Fulmer DriveCSO TWL00799 | 2050 | 30 ·24 | 5 6 events | -83% | 0.5× | Within the cap | |
| Iver (north) STW TWL00245 | 2050 | 1 ·24 | 0 0 events | -100% | 0× | — | Within the cap |
What this is — and what it is not
This is River Hub's measurement, not the plan's. The reduction plan publishes no target for an individual overflow and no per-overflow progress — so we compare each outlet's counted spills to its 2020 baseline and the 10/year cap. Counted spills use the Environment Agency's 12/24-hour block method — the figure the cap is actually written in — taken from the published annual return where we have it and computed the same way for the current year; the smaller “events” figure beneath each is River Hub's count of discrete discharges over 15 minutes, shown for context. The deadline shown is derived by proximity to a designated site, not an official determination, and the plan is a policy commitment rather than a statutory duty. A falling trend is progress, but only ≤10 by the deadline is compliance. Where 2020 data is thin the baseline falls back to the earliest year on record, shown beside it. How the two counts differ →