What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100131a · db870ffb | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BODELWYDDAN MAIN SPS | Complete 2025-26 | Rhuddlan WwTW Storm Overflow |
| DCWW100193a · 2f8372a0 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ DENBIGH WWTW | Complete 2025-26 | Dalar Wen Denbigh Storm Overflow |
| DCWW100227a · 524e7a26 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ HENLLAN STW | Complete 2025-26 | Henllan WwTW Storm Overflow |
| DCWW100254a · 4cde28bf | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANDYRNOG | Complete 2025-26 | Llandyrnog WwTW Storm Overflow |
| DCWW100290a · c993faa0 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANSANNAN STW | Complete 2025-26 | Llansannan Storm Overflow |
| DCWW100351a · 2801b6c1 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PWLLGLAS STW | Complete 2025-26 | Pwll-Glas WwTW Storm Overflow |
| DCWW100362a · 79151da3 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ RHUDDLAN NETWORK STORAGE SPS | Complete 2025-26 | Rhuddlan WwTW Storm Overflow |
| DCWW100363a · 00cc1968 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ RHUDDLAN WWTW FINAL | Complete 2025-26 | Rhuddlan WwTW Storm Overflow |
| DCWW100367a · 846b17d7 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ RUTHIN STW (FINAL) | Complete 2025-26 | Ruthin WwTW Overflow |
| DCWW100370a · c5f40d83 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ST ASAPH STW | Complete 2025-26 | Roe Parc St Asaph Storm Overflow |
| DCWW102659a · c9a3000c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Brondyffyn CSO | Due 2026-27 | Brondyffyn Storm Overflow |
| DCWW100646a · 6a69d379 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ DENBIGH EGLWYSWEN | Due 2026-27 | Denbigh WwTW Storm Overflow |
| DCWW102658a · a1cc3be9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ DENBIGH FRONGOCH REAR MAGISTRATES COURT | Due 2026-27 | Beacons Road and Grove Road Denbigh Storm Overflow |
| DCWW102657a · 3fedadff | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ DENBIGH HENLLAN STREET | Due 2026-27 | Maes Mathonwy Denbigh Storm Overflow |
| DCWW102179a · 6faeac8c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ DENBIGH PLAS YN GREEN CSO | Due 2026-27 | Dalar Wen Denbigh Storm Overflow |
| DCWW102186a · c5fbb8b4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ HENLLAN (NR DENBIGH) STW | Due 2026-27 | Henllan WwTW Storm Overflow |
| DCWW101669a · db4031d5 | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. WQ LIXWM (WHEELER HILL) | Due 2026-27 | Water body only |
| DCWW101622a · c6cf922c | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. WQ Llanbedr (DC) | Due 2026-27 | Water body only |
| DCWW101674a · 272609b1 | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. WQ Llanfair Dyffryn Clwyd | Due 2026-27 | Water body only |
| DCWW101677a · 33994516 | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. WQ NANNERCH | Due 2026-27 | Water body only |
| DCWW100640a · 111e1333 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ RUTHIN | Due 2026-27 | Ruthin WwTW Overflow |
| DCWW102182a · 9e88d764 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RUTHIN ROAD CSO, Denbigh | Due 2026-27 | Denbigh Ruthin Road Storm Overflow |
| DCWW100388a · b3ddae7e | W_U_MON4 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows WQ TRECASTLE SWK | Due 2026-27 | Trefnant Storm Overflow |
| DCWW102660a · 1e0950ab | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ TREFNANT VILLAGE NRA TREFNANT STW | Due 2026-27 | Trefnant Storm Overflow |
| DCWW100391a · 122e34a5 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ TREFOR NORTH-WEST | Due 2026-27 | Trefnant Storm Overflow |
| DCWW101656a · ed00126c | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper WQ Bodtegwel (7CDC1090) | Due 2027-28 | Water body only |
| DCWW101668a · 9a8cb6db | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper WQ HENLLAN (7CDC0511) | Due 2027-28 | HENLLAN (Nr Denbigh) |
| DCWW100684a · e0cc48b3 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ DENBIGH EGLWYSWEN | Due 2027-28 | Denbigh WwTW Storm Overflow |
| DCWW101582a · ddae5c26 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Abbey Road CSO | Due 2029-30 | Abbey Road Denbigh Storm Overflow |
| DCWW102239a · 699a0d96 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Berthglyd CSO Abergele | Due 2029-30 | Berth Glyd Storm Overflow |
| DCWW101582a · bf1c9ca0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BETHEL SSO NO. 3 | Due 2029-30 | B5382 Llangernyw Storm Overflow |
| DCWW101235a · 5e89b574 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BODELWYDDAN MAIN PS | Due 2029-30 | Bodelwyddan Storm Tanks Storm Overflow |
| DCWW102469a · 25485908 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BODELWYDDAN STORM TANKS | Due 2029-30 | Bodelwyddan Storm Tanks Storm Overflow |
| DCWW100466a · 47a69378 | W_EEL_IMP1 | Improvement | Implementation of actions to improve abstractions and outfalls to prevent the entrainment of eels and to address barriers to passage of eels WR Bryn Aled | Due 2029-30 | Water body only |
| DCWW101389a · cf004d1b | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BRYNFORD MAIN SEWAGE PUMPING STATION NO. 1, BRYNFORD, CLWYD | Due 2029-30 | Water body only |
| DCWW101487a · 06db975e | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Cae Sarn SPS serving Cae Sarn Dyffryn, Groeslon, Gwynedd, LL54 7TQ | Due 2029-30 | Dyserth WwTW Storm Overflow |
| DCWW100631a · 5fa2154c | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ CLAWDD-NEWYDD | Due 2029-30 | Clawddnewydd WwTW Storm Overflow |
| DCWW101582a · a6e9304a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CLIFTON PARK CSO NO.2 | Due 2029-30 | Clifton Park Road Rhyl Storm Overflow 2 |
| DCWW101582a · 69ea7b05 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Coast Road PS Rhyl | Due 2029-30 | Rhyl Coast Road Storm Overflow |
| DCWW101582a · 827aa093 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO AT GAMEKEEPER PH, LOWER STREET, ST ASAPH | Due 2029-30 | High Street St Asaph Storm Overflow |
| DCWW101582a · c951be3a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Towyn SPS 3114 Coventry Camp | Due 2029-30 | Towyn Storm Overflow |
| DCWW101376a · 5db6d863 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CWTTIR LANE SPS, ST ASAPH | Due 2029-30 | Water body only |
| DCWW101406a · 216bee10 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Dalar Wen Sewage Pumping Station | Due 2029-30 | Dalar Wen Denbigh Storm Overflow |
| DCWW102496a · a038e7be | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ DENBIGH STW | Due 2029-30 | Dalar Wen Denbigh Storm Overflow |
| DCWW101430a · 027165e6 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ DYSERTH BAY FOUL SPS CSO, THE BOULEVARD, PRESTATYN | Due 2029-30 | The Boulevard Prestatyn Storm Overflow |
| DCWW102500a · b584a6eb | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ DYSERTH STW | Due 2029-30 | Dyserth WwTW Storm Overflow |
| DCWW101257a · 0c0d6ad0 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ EO, FORYD RD, KINMEL BAY, CLWYD | Due 2029-30 | Foryd Road and Dinas Avenue Kimmel Bay Overflow |
| DCWW101259a · 4b75abb0 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ FAIRLANDS ESTATE PUMPING STATION RHODFA ANWYL, RHUDDLAN, CLWYD | Due 2029-30 | Ffordd Ffynnon Rhuddlan Storm Overflow |
| DCWW101582a · 139a208e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Fford Aber CSO Ffordd Ffynnon, Rhuddlan, Denbighshire | Due 2029-30 | Ffordd Ffynnon Rhuddlan Storm Overflow |
| DCWW101345a · 03e39cda | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ FFORDD PEN Y MAES PUMPING STATION | Due 2029-30 | Brondyffyn Storm Overflow |
| DCWW101582a · f8705403 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ KERFOOT CARAVAN PARK CSO | Due 2029-30 | Towyn Road Storm Overflow |
| DCWW100697a · 496369ee | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANDYRNOG | Due 2029-30 | Llandyrnog WwTW Storm Overflow |
| DCWW102828a · 5c5070f4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANDYRNOG STW | Due 2029-30 | Llandyrnog WwTW Storm Overflow |
| DCWW101582a · e1a33814 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANFAIR DC STW | Due 2029-30 | Llanfair Dyffryn Clwyd WwTW Storm Overflow |
| DCWW102503a · e6f36df9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANFAIR TALHAIARN STW | Due 2029-30 | Llanfair Talhaiarn WwTW Storm Overflow |
| DCWW101221a · b00e28e7 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANGERNYW PS | Due 2029-30 | B5382 Llangernyw Storm Overflow |
| DCWW101582a · dd5053f6 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llangernyw SPS | Due 2029-30 | B5382 Llangernyw Storm Overflow |
| DCWW100676a · aa97c9a8 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANSANNAN | Due 2029-30 | Llansannan Storm Overflow |
| DCWW101582a · 58c69cca | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llansannan Ddol CSO | Due 2029-30 | Llansannan Storm Overflow |
| DCWW101262a · 17a61234 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MAES OWEN PUMPING STATION, BODELWYDDAN, CLWYD | Due 2029-30 | Water body only |
| DCWW102819a · dbf9da33 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Maes Y Llan CSO Abergale | Due 2029-30 | Maes Y Llan Storm Overflow |
| DCWW101333a · 7e8658d9 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MAES-Y-LLAN CSO, MAES-Y-LLAN, TOWYN | Due 2029-30 | Towyn Road Storm Overflow |
| DCWW101369a · 6e926597 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MARINE PARK PUMPING STATION, RHYL | Due 2029-30 | Southwest of York Close Prestatyn Overflow |
| DCWW101390a · e084c23c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ NAID-Y-MARCH SEWAGE PUMPING STATION NO. 2 | Due 2029-30 | Water body only |
| DCWW101425a · beeacf0e | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ NANNERCH PS | Due 2029-30 | Nannerch Storm Overflow |
| DCWW101582a · c3d6d5ff | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Nannerch SPS | Due 2029-30 | Nannerch Storm Overflow |
| DCWW101263a · 113949c3 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ NANT HALL ROAD SEWAGE PUMPING STATION, PRESTATYN, CLWYD | Due 2029-30 | Nant Hall Road Overflow |
| DCWW101264a · 1878a0f1 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ NANT HALL ROAD SEWAGE PUMPING STATION, PRESTATYN, CLWYD | Due 2029-30 | Ffordd Parc Bodnant Prestatyn Overflow |
| DCWW101582a · 3e8f5168 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Nantlle PS | Due 2029-30 | B5382 Llangernyw Storm Overflow |
| DCWW101582a · 8de8de7f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Panton Hall CSO Barker's Well Lane, Lenton Pool, Denbigh, | Due 2029-30 | Panton Hall Denbigh Storm Overflow |
| DCWW101582a · 4e2efbc7 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Pentre Llanrhaedr PS | Due 2029-30 | Pentre Llanrhaeadr Storm Overflow |
| DCWW101427a · 97751159 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PENTRE LLANRHAEDR PS | Due 2029-30 | Pentre Llanrhaeadr Storm Overflow |
| DCWW101383a · 69651c8c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PENTRE LLANRHAIADR SEWAGE PUMPING STATION | Due 2029-30 | Pentre Llanrhaeadr Storm Overflow |
| DCWW101582a · a89c3351 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PRESTATYN MALL PS | Due 2029-30 | Prestatyn The Mall Storm Overflow |
| DCWW101431a · 81e593fd | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PRESTATYN MALL PS | Due 2029-30 | Prestatyn The Mall Storm Overflow |
| DCWW101582a · 8a35ce80 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PRESTATYN MELIDEN ROAD - SSO | Due 2029-30 | Meliden Road Prestatyn Storm Overflow |
| DCWW102806a · 2281acfe | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PRESTATYN NANT HALL ROAD | Due 2029-30 | Ffordd Parc Bodnant Prestatyn Overflow |
| DCWW101582a · c8b2787a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PRESTATYN NANT PS | Due 2029-30 | Marine Road East Storm Overflow |
| DCWW101429a · c7681c4e | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PRESTATYN NANT PS | Due 2029-30 | Ffordd Parc Bodnant Prestatyn Overflow |
| DCWW101582a · 8b22ddf4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PRESTATYN PURBECK PS | Due 2029-30 | Victoria Road Prestatyn Storm Overflow |
| DCWW101432a · caf70d02 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PRESTATYN PURBECK PS | Due 2029-30 | Victoria Road Prestatyn Storm Overflow |
| DCWW101371a · 54b9c80d | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Prestatyn Sewage Pumping Station | Due 2029-30 | Llanasa Headworks Storm Overflow |
| DCWW101582a · 30ed53e8 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PRESTATYN SPS MARINE RD EAST | Due 2029-30 | Llanasa Headworks Storm Overflow |
| DCWW100639a · be9f38af | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ PWLL-GLAS (RUTHIN) | Due 2029-30 | Pwll-Glas WwTW Storm Overflow |
| DCWW101582a · b6d0465d | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PWLLGLAS STW | Due 2029-30 | Pwll-Glas WwTW Inlet Storm Overflow |
| DCWW101315a · bcb6bbff | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ RESIDENTIAL DEVELOPMENT AT PARC HANES, OFF ST ASAPH AVENUE, KINMEL BAY, RHYL, LL18 5FE | Due 2029-30 | Water body only |
| DCWW101393a · 1506e032 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ RHES-Y-CAE SEWAGE PUMPING STATION | Due 2029-30 | Water body only |
| DCWW101266a · f82cb497 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ RHODFA GLENYS SEWAGE PUMPING STATION, ST Asaph | Due 2029-30 | Water body only |
| DCWW100679a · dd4e95ad | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ RHUDDLAN | Due 2029-30 | Rhuddlan WwTW Storm Overflow |
| DCWW101582a · d248444e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Rhuddlan CSO | Due 2029-30 | Rhuddlan Storm Overflow |
| DCWW101382a · 0b1f5ddf | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ RHUDDLAN SEWAGE TREATMENT WORKS STORM TANK | Due 2029-30 | Rhuddlan WwTW Storm Overflow |
| DCWW102617a · 3710126e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RHYL MARINE LAKE OUTFALL | Due 2029-30 | Clifton Park Road Rhyl Storm Overflow 2 |
| DCWW102820a · cfca7aaa | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RHYL WESTBOURNE GROVE (RESERVOIR) NRA | Due 2029-30 | Westbourne Grove Storm Overflow |
| DCWW101394a · 9dcb290a | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ROE PARC CSO, ST Asaph, DENBIGHSHIRE | Due 2029-30 | Roe Parc St Asaph Storm Overflow |
| DCWW102486a · 631bedf5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RUTHIN STW | Due 2029-30 | Ruthin WwTW Overflow |
| DCWW102495a · feb87dbd | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ RUTHIN STW SETTLED STORM | Due 2029-30 | Ruthin WwTW Overflow |
| DCWW101582a · 8dd3e195 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Settled Storm Sewage at Pwllglas WwTW | Due 2029-30 | Pwll-Glas WwTW Storm Overflow |
| DCWW101395a · 035ae47f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ SEVEN SISTERS ROAD, PRESTATYN | Due 2029-30 | Bastion Road Prestatyn Overflow |
| DCWW101316a · 02ffb634 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ST ASAPH BUSINESS PARK, TRB DRIVE, DENBIGHSHIRE, LL17 0LJ | Due 2029-30 | Water body only |
| DCWW101582a · 0c91391e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ St Asaph Roe Parc CSO | Due 2029-30 | Roe Parc St Asaph Storm Overflow |
| DCWW101271a · c9dae6cb | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ THE VILLAGE, BODELWYDDAN, SEWAGE PUMPING STATION | Due 2029-30 | Water body only |
| DCWW101582a · c2c5e700 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Towyn Gors Road PS | Due 2029-30 | Towyn Road Storm Overflow |
| DCWW101223a · 2dc72bb0 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Towyn Gors Road PS | Due 2029-30 | Towyn Road Storm Overflow |
| DCWW100680a · 8f607b8d | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ TREFNANT | Due 2029-30 | Trefnant Storm Overflow |
| DCWW101260a · 70f2defb | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ TY NEWYDD PUMPING STATION | Due 2029-30 | Tynewydd Road Storm Overflow |
| DCWW101367a · e59545b8 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ WESTBOURNE AVENUE SEWAGE PUMPING STATION, RHYL | Due 2029-30 | Westbourne Grove Storm Overflow |
| DCWW101582a · 97d582c3 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ YSCEIFIOG CSO | Due 2029-30 | Ysceifiog Storm Overflow |
| DCWW101392a · 8a6f67d5 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ YSCEIFIOG SEWAGE PUMPING STATION | Due 2029-30 | Ysceifiog Storm Overflow |
108 of 108 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.