Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

108
Measures in this catchment
NEP, current record
98
Still active
not yet past their date
10
Assumed complete
completion date has passed
16
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100131a · db870ffbW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BODELWYDDAN MAIN SPS
Complete 2025-26Rhuddlan WwTW Storm Overflow
DCWW100193a · 2f8372a0W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
DENBIGH WWTW
Complete 2025-26Dalar Wen Denbigh Storm Overflow
DCWW100227a · 524e7a26W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
HENLLAN STW
Complete 2025-26Henllan WwTW Storm Overflow
DCWW100254a · 4cde28bfW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANDYRNOG
Complete 2025-26Llandyrnog WwTW Storm Overflow
DCWW100290a · c993faa0W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANSANNAN STW
Complete 2025-26Llansannan Storm Overflow
DCWW100351a · 2801b6c1W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PWLLGLAS STW
Complete 2025-26Pwll-Glas WwTW Storm Overflow
DCWW100362a · 79151da3W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
RHUDDLAN NETWORK STORAGE SPS
Complete 2025-26Rhuddlan WwTW Storm Overflow
DCWW100363a · 00cc1968W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
RHUDDLAN WWTW FINAL
Complete 2025-26Rhuddlan WwTW Storm Overflow
DCWW100367a · 846b17d7W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
RUTHIN STW (FINAL)
Complete 2025-26Ruthin WwTW Overflow
DCWW100370a · c5f40d83W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ST ASAPH STW
Complete 2025-26Roe Parc St Asaph Storm Overflow
DCWW102659a · c9a3000cW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Brondyffyn CSO
Due 2026-27Brondyffyn Storm Overflow
DCWW100646a · 6a69d379W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
DENBIGH EGLWYSWEN
Due 2026-27Denbigh WwTW Storm Overflow
DCWW102658a · a1cc3be9W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DENBIGH FRONGOCH REAR MAGISTRATES COURT
Due 2026-27Beacons Road and Grove Road Denbigh Storm Overflow
DCWW102657a · 3fedadffW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DENBIGH HENLLAN STREET
Due 2026-27Maes Mathonwy Denbigh Storm Overflow
DCWW102179a · 6faeac8cW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DENBIGH PLAS YN GREEN CSO
Due 2026-27Dalar Wen Denbigh Storm Overflow
DCWW102186a · c5fbb8b4W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
HENLLAN (NR DENBIGH) STW
Due 2026-27Henllan WwTW Storm Overflow
DCWW101669a · db4031d5W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
LIXWM (WHEELER HILL)
Due 2026-27Water body only
DCWW101622a · c6cf922cW_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
Llanbedr (DC)
Due 2026-27Water body only
DCWW101674a · 272609b1W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
Llanfair Dyffryn Clwyd
Due 2026-27Water body only
DCWW101677a · 33994516W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
NANNERCH
Due 2026-27Water body only
DCWW100640a · 111e1333W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
RUTHIN
Due 2026-27Ruthin WwTW Overflow
DCWW102182a · 9e88d764W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RUTHIN ROAD CSO, Denbigh
Due 2026-27Denbigh Ruthin Road Storm Overflow
DCWW100388a · b3ddae7eW_U_MON4Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows
WQ
TRECASTLE SWK
Due 2026-27Trefnant Storm Overflow
DCWW102660a · 1e0950abW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
TREFNANT VILLAGE NRA TREFNANT STW
Due 2026-27Trefnant Storm Overflow
DCWW100391a · 122e34a5W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TREFOR NORTH-WEST
Due 2026-27Trefnant Storm Overflow
DCWW101656a · ed00126cW_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper
WQ
Bodtegwel (7CDC1090)
Due 2027-28Water body only
DCWW101668a · 9a8cb6dbW_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper
WQ
HENLLAN (7CDC0511)
Due 2027-28HENLLAN (Nr Denbigh)
DCWW100684a · e0cc48b3W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
DENBIGH EGLWYSWEN
Due 2027-28Denbigh WwTW Storm Overflow
DCWW101582a · ddae5c26W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Abbey Road CSO
Due 2029-30Abbey Road Denbigh Storm Overflow
DCWW102239a · 699a0d96W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Berthglyd CSO Abergele
Due 2029-30Berth Glyd Storm Overflow
DCWW101582a · bf1c9ca0W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BETHEL SSO NO. 3
Due 2029-30B5382 Llangernyw Storm Overflow
DCWW101235a · 5e89b574W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BODELWYDDAN MAIN PS
Due 2029-30Bodelwyddan Storm Tanks Storm Overflow
DCWW102469a · 25485908W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BODELWYDDAN STORM TANKS
Due 2029-30Bodelwyddan Storm Tanks Storm Overflow
DCWW100466a · 47a69378W_EEL_IMP1Improvement
Implementation of actions to improve abstractions and outfalls to prevent the entrainment of eels and to address barriers to passage of eels
WR
Bryn Aled
Due 2029-30Water body only
DCWW101389a · cf004d1bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BRYNFORD MAIN SEWAGE PUMPING STATION NO. 1, BRYNFORD, CLWYD
Due 2029-30Water body only
DCWW101487a · 06db975eW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Cae Sarn SPS serving Cae Sarn Dyffryn, Groeslon, Gwynedd, LL54 7TQ
Due 2029-30Dyserth WwTW Storm Overflow
DCWW100631a · 5fa2154cW_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
CLAWDD-NEWYDD
Due 2029-30Clawddnewydd WwTW Storm Overflow
DCWW101582a · a6e9304aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CLIFTON PARK CSO NO.2
Due 2029-30Clifton Park Road Rhyl Storm Overflow 2
DCWW101582a · 69ea7b05W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Coast Road PS Rhyl
Due 2029-30Rhyl Coast Road Storm Overflow
DCWW101582a · 827aa093W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO AT GAMEKEEPER PH, LOWER STREET, ST ASAPH
Due 2029-30High Street St Asaph Storm Overflow
DCWW101582a · c951be3aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Towyn SPS 3114 Coventry Camp
Due 2029-30Towyn Storm Overflow
DCWW101376a · 5db6d863W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CWTTIR LANE SPS, ST ASAPH
Due 2029-30Water body only
DCWW101406a · 216bee10W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Dalar Wen Sewage Pumping Station
Due 2029-30Dalar Wen Denbigh Storm Overflow
DCWW102496a · a038e7beW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DENBIGH STW
Due 2029-30Dalar Wen Denbigh Storm Overflow
DCWW101430a · 027165e6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
DYSERTH BAY FOUL SPS CSO, THE BOULEVARD, PRESTATYN
Due 2029-30The Boulevard Prestatyn Storm Overflow
DCWW102500a · b584a6ebW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DYSERTH STW
Due 2029-30Dyserth WwTW Storm Overflow
DCWW101257a · 0c0d6ad0W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
EO, FORYD RD, KINMEL BAY, CLWYD
Due 2029-30Foryd Road and Dinas Avenue Kimmel Bay Overflow
DCWW101259a · 4b75abb0W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
FAIRLANDS ESTATE PUMPING STATION RHODFA ANWYL, RHUDDLAN, CLWYD
Due 2029-30Ffordd Ffynnon Rhuddlan Storm Overflow
DCWW101582a · 139a208eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Fford Aber CSO Ffordd Ffynnon, Rhuddlan, Denbighshire
Due 2029-30Ffordd Ffynnon Rhuddlan Storm Overflow
DCWW101345a · 03e39cdaW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
FFORDD PEN Y MAES PUMPING STATION
Due 2029-30Brondyffyn Storm Overflow
DCWW101582a · f8705403W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
KERFOOT CARAVAN PARK CSO
Due 2029-30Towyn Road Storm Overflow
DCWW100697a · 496369eeW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANDYRNOG
Due 2029-30Llandyrnog WwTW Storm Overflow
DCWW102828a · 5c5070f4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANDYRNOG STW
Due 2029-30Llandyrnog WwTW Storm Overflow
DCWW101582a · e1a33814W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANFAIR DC STW
Due 2029-30Llanfair Dyffryn Clwyd WwTW Storm Overflow
DCWW102503a · e6f36df9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANFAIR TALHAIARN STW
Due 2029-30Llanfair Talhaiarn WwTW Storm Overflow
DCWW101221a · b00e28e7W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANGERNYW PS
Due 2029-30B5382 Llangernyw Storm Overflow
DCWW101582a · dd5053f6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llangernyw SPS
Due 2029-30B5382 Llangernyw Storm Overflow
DCWW100676a · aa97c9a8W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANSANNAN
Due 2029-30Llansannan Storm Overflow
DCWW101582a · 58c69ccaW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llansannan Ddol CSO
Due 2029-30Llansannan Storm Overflow
DCWW101262a · 17a61234W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MAES OWEN PUMPING STATION, BODELWYDDAN, CLWYD
Due 2029-30Water body only
DCWW102819a · dbf9da33W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Maes Y Llan CSO Abergale
Due 2029-30Maes Y Llan Storm Overflow
DCWW101333a · 7e8658d9W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MAES-Y-LLAN CSO, MAES-Y-LLAN, TOWYN
Due 2029-30Towyn Road Storm Overflow
DCWW101369a · 6e926597W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MARINE PARK PUMPING STATION, RHYL
Due 2029-30Southwest of York Close Prestatyn Overflow
DCWW101390a · e084c23cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
NAID-Y-MARCH SEWAGE PUMPING STATION NO. 2
Due 2029-30Water body only
DCWW101425a · beeacf0eW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
NANNERCH PS
Due 2029-30Nannerch Storm Overflow
DCWW101582a · c3d6d5ffW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Nannerch SPS
Due 2029-30Nannerch Storm Overflow
DCWW101263a · 113949c3W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
NANT HALL ROAD SEWAGE PUMPING STATION, PRESTATYN, CLWYD
Due 2029-30Nant Hall Road Overflow
DCWW101264a · 1878a0f1W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
NANT HALL ROAD SEWAGE PUMPING STATION, PRESTATYN, CLWYD
Due 2029-30Ffordd Parc Bodnant Prestatyn Overflow
DCWW101582a · 3e8f5168W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Nantlle PS
Due 2029-30B5382 Llangernyw Storm Overflow
DCWW101582a · 8de8de7fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Panton Hall CSO Barker's Well Lane, Lenton Pool, Denbigh,
Due 2029-30Panton Hall Denbigh Storm Overflow
DCWW101582a · 4e2efbc7W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pentre Llanrhaedr PS
Due 2029-30Pentre Llanrhaeadr Storm Overflow
DCWW101427a · 97751159W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PENTRE LLANRHAEDR PS
Due 2029-30Pentre Llanrhaeadr Storm Overflow
DCWW101383a · 69651c8cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PENTRE LLANRHAIADR SEWAGE PUMPING STATION
Due 2029-30Pentre Llanrhaeadr Storm Overflow
DCWW101582a · a89c3351W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PRESTATYN MALL PS
Due 2029-30Prestatyn The Mall Storm Overflow
DCWW101431a · 81e593fdW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PRESTATYN MALL PS
Due 2029-30Prestatyn The Mall Storm Overflow
DCWW101582a · 8a35ce80W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PRESTATYN MELIDEN ROAD - SSO
Due 2029-30Meliden Road Prestatyn Storm Overflow
DCWW102806a · 2281acfeW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PRESTATYN NANT HALL ROAD
Due 2029-30Ffordd Parc Bodnant Prestatyn Overflow
DCWW101582a · c8b2787aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PRESTATYN NANT PS
Due 2029-30Marine Road East Storm Overflow
DCWW101429a · c7681c4eW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PRESTATYN NANT PS
Due 2029-30Ffordd Parc Bodnant Prestatyn Overflow
DCWW101582a · 8b22ddf4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PRESTATYN PURBECK PS
Due 2029-30Victoria Road Prestatyn Storm Overflow
DCWW101432a · caf70d02W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PRESTATYN PURBECK PS
Due 2029-30Victoria Road Prestatyn Storm Overflow
DCWW101371a · 54b9c80dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Prestatyn Sewage Pumping Station
Due 2029-30Llanasa Headworks Storm Overflow
DCWW101582a · 30ed53e8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PRESTATYN SPS MARINE RD EAST
Due 2029-30Llanasa Headworks Storm Overflow
DCWW100639a · be9f38afW_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
PWLL-GLAS (RUTHIN)
Due 2029-30Pwll-Glas WwTW Storm Overflow
DCWW101582a · b6d0465dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PWLLGLAS STW
Due 2029-30Pwll-Glas WwTW Inlet Storm Overflow
DCWW101315a · bcb6bbffW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RESIDENTIAL DEVELOPMENT AT PARC HANES, OFF ST ASAPH AVENUE, KINMEL BAY, RHYL, LL18 5FE
Due 2029-30Water body only
DCWW101393a · 1506e032W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHES-Y-CAE SEWAGE PUMPING STATION
Due 2029-30Water body only
DCWW101266a · f82cb497W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHODFA GLENYS SEWAGE PUMPING STATION, ST Asaph
Due 2029-30Water body only
DCWW100679a · dd4e95adW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
RHUDDLAN
Due 2029-30Rhuddlan WwTW Storm Overflow
DCWW101582a · d248444eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Rhuddlan CSO
Due 2029-30Rhuddlan Storm Overflow
DCWW101382a · 0b1f5ddfW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHUDDLAN SEWAGE TREATMENT WORKS STORM TANK
Due 2029-30Rhuddlan WwTW Storm Overflow
DCWW102617a · 3710126eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RHYL MARINE LAKE OUTFALL
Due 2029-30Clifton Park Road Rhyl Storm Overflow 2
DCWW102820a · cfca7aaaW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RHYL WESTBOURNE GROVE (RESERVOIR) NRA
Due 2029-30Westbourne Grove Storm Overflow
DCWW101394a · 9dcb290aW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ROE PARC CSO, ST Asaph, DENBIGHSHIRE
Due 2029-30Roe Parc St Asaph Storm Overflow
DCWW102486a · 631bedf5W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RUTHIN STW
Due 2029-30Ruthin WwTW Overflow
DCWW102495a · feb87dbdW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RUTHIN STW SETTLED STORM
Due 2029-30Ruthin WwTW Overflow
DCWW101582a · 8dd3e195W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Settled Storm Sewage at Pwllglas WwTW
Due 2029-30Pwll-Glas WwTW Storm Overflow
DCWW101395a · 035ae47fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
SEVEN SISTERS ROAD, PRESTATYN
Due 2029-30Bastion Road Prestatyn Overflow
DCWW101316a · 02ffb634W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ST ASAPH BUSINESS PARK, TRB DRIVE, DENBIGHSHIRE, LL17 0LJ
Due 2029-30Water body only
DCWW101582a · 0c91391eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
St Asaph Roe Parc CSO
Due 2029-30Roe Parc St Asaph Storm Overflow
DCWW101271a · c9dae6cbW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
THE VILLAGE, BODELWYDDAN, SEWAGE PUMPING STATION
Due 2029-30Water body only
DCWW101582a · c2c5e700W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Towyn Gors Road PS
Due 2029-30Towyn Road Storm Overflow
DCWW101223a · 2dc72bb0W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Towyn Gors Road PS
Due 2029-30Towyn Road Storm Overflow
DCWW100680a · 8f607b8dW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
TREFNANT
Due 2029-30Trefnant Storm Overflow
DCWW101260a · 70f2defbW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TY NEWYDD PUMPING STATION
Due 2029-30Tynewydd Road Storm Overflow
DCWW101367a · e59545b8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
WESTBOURNE AVENUE SEWAGE PUMPING STATION, RHYL
Due 2029-30Westbourne Grove Storm Overflow
DCWW101582a · 97d582c3W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
YSCEIFIOG CSO
Due 2029-30Ysceifiog Storm Overflow
DCWW101392a · 8a6f67d5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
YSCEIFIOG SEWAGE PUMPING STATION
Due 2029-30Ysceifiog Storm Overflow

108 of 108 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.