Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

52
Measures in this catchment
WINEP, current record
52
Still active
not yet past their date
0
Assumed complete
completion date has passed
9
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104985 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Axminster (Kilmington) STW
Due 2026-27Lower Axe
08SW104986 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Axminster (Kilmington) STW
Due 2026-27Lower Axe
08SW104949 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
BRANSCOMBE STW
Due 2026-27Branscombe stream
08SW104950 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BRANSCOMBE STW
Due 2026-27Branscombe stream
08SW104936 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BROADWINDSOR STW
Due 2026-27Upper Axe
08SW104935 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
BROADWINDSOR STW
Due 2026-27Upper Axe
08SW104886 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
COLYTON + COLYFORD STW
Due 2026-27Lower Axe
08SW104885 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
COLYTON + COLYFORD STW
Due 2026-27Lower Axe
08SW104504 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Drimpton STW: Drimpton Pumping Station
Due 2026-27Upper Axe
08SW104505 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Drimpton STW: Drimpton Pumping Station
Due 2026-27Upper Axe
08SW104800 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
HAWKCHURCH STW
Due 2026-27Blackwater River
08SW104799 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
HAWKCHURCH STW
Due 2026-27Blackwater River
08SW100029 · aWFD_INV_WRFlowInvestigation
Flow investigation, Kit Brook and wider River Axe catchment. Hook and Cotley Springs.
Kit Brook abstraction
Due 2026-27Kit Brook
08SW104737 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
LYME REGIS (UPLYME) STW
Due 2026-27Lim
08SW104738 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
LYME REGIS (UPLYME) STW
Due 2026-27Lim
08SW104484 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Lyme Regis STW: Gun Cliff Pumping Station, Lyme Regis
Due 2026-27Lim
08SW104713 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
MUSBURY + WHITFORD STW
Due 2026-27Lower Axe
08SW104712 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
MUSBURY + WHITFORD STW
Due 2026-27Lower Axe
08SW104692 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Offwell STW
Due 2026-27Offwell Brook
08SW104693 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Offwell STW
Due 2026-27Offwell Brook
08SW104582 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
TATWORTH STW
Due 2026-27Forton Brook
08SW104581 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
TATWORTH STW
Due 2026-27Forton Brook
08SW104574 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
THORNCOMBE STW
Due 2026-27Upper Axe
08SW104573 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
THORNCOMBE STW
Due 2026-27Upper Axe
08SW104539 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Wilmington STW
Due 2026-27Umborne Brook
08SW104540 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Wilmington STW
Due 2026-27Umborne Brook
08SW104535 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
WINSHAM STW
Due 2026-27Upper Axe
08SW104536 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WINSHAM STW
Due 2026-27Upper Axe
08SW100100 · aBW_NDNo deterioration
2 spills 50m3 aggregated
GOSLINGS BRIDGE_CSO_LYME REGIS
Due 2026-27GOSLINGS BRIDGE_CSO_LYME REGIS
08SW100100 · bBW_NDNo deterioration
2 spills 50m3 aggregated
GUN CLIFF SPST_PSCSOEO_LYME REGIS
Due 2026-27GUN CLIFF SPST_PSCSOEO_LYME REGIS
08SW100100 · cBW_NDNo deterioration
2 spills 50m3 aggregated
HORN BRIDGE SPST_PSCSOEO_LYME REGIS
Due 2026-27HORN BRIDGE SPST_PSCSOEO_LYME REGIS
08SW100100 · dBW_NDNo deterioration
2 spills 50m3 aggregated
JERICHO_CSO_LYME REGIS
Due 2026-27JERICHO_CSO_LYME REGIS
08SW100100 · eBW_NDNo deterioration
2 spills 50m3 aggregated
MILL LN_CSO_UPLYME
Due 2026-27MILL LN_CSO_UPLYME
08SW100100 · gBW_NDNo deterioration
2 spills 50m3 aggregated
UPLYME STW_SSO_UPLYME
Due 2026-27UPLYME STW_SSO_UPLYME
08SW104999 · anEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
COLYTON STW_SSO_COLYTON
Due 2027-28COLYTON STW_SSO_COLYTON
08SW104999 · bmEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
GOSLINGS BRIDGE_CSO_LYME REGIS
Due 2027-28GOSLINGS BRIDGE_CSO_LYME REGIS
08SW104285 · eEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
HORN BRIDGE SPST_PSCSOEO_LYME REGIS
Due 2027-28HORN BRIDGE SPST_PSCSOEO_LYME REGIS
08SW104285 · dEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
JERICHO_CSO_LYME REGIS
Due 2027-28JERICHO_CSO_LYME REGIS
08SW104999 · gbEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
KILMINGTON STW_SSO_AXMINSTER
Due 2027-28KILMINGTON STW_SSO_AXMINSTER
08SW104999 · ciEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
MILL LN_CSO_UPLYME
Due 2027-28MILL LN_CSO_UPLYME
08SW104999 · cqEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
MUSBURY & WHITFORD STW_SO_WHITFORD
Due 2027-28Lower Axe
08SW104999 · dmEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
RAILWAY STATION_CSO_AXMINSTER
Due 2027-28RAILWAY STATION_CSO_AXMINSTER
08SW104999 · ffEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
WHITFORD ROAD_CSO_MUSBURY
Due 2027-28WHITFORD ROAD_CSO_MUSBURY
08SW101509 · aHD_IMP_NNImprovement
New or tightened P consent
KILMINGTON_STW_AXMINSTER
Due 2027-28Yarty
08SW100151 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
BRANSCOMBE STW_SSO_BRANSCOMBE
Due 2029-30BRANSCOMBE STW_SSO_BRANSCOMBE
08SW103002 · aEnvAct_IMP3Improvement
Reduction of spills to meet EnvAct_IMP drivers
HARBOUR ROAD SPS_PSCSOEO_SEATON
Due 2029-30HARBOUR ROAD SPS_PSCSOEO_SEATON
08SW101523 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
KILMINGTON STW_SSO_AXMINSTER
Due 2029-30KILMINGTON STW_SSO_AXMINSTER
08SW102148 · cU_IMP2Improvement
P limit for HD – 1mg. monitoring only
KILMINGTON_STW_AXMINSTER
Due 2029-30Lower Axe
08SW100105 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
MUSBURY & WHITFORD STW_SO_WHITFORD
Due 2029-30Lower Axe
08SW100106 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
RAILWAY STATION_CSO_AXMINSTER
Due 2029-30RAILWAY STATION_CSO_AXMINSTER
08SW102113 · jU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
DALWOOD_STW_DALWOOD
Due 2030-31Corry Brook
08SW102113 · zU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
STOCKLAND_STW_STOCKLAND
Due 2030-31Yarty

52 of 52 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.