What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100106a · 9c6fa816 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ABERAERON | Complete 2025-26 | Waterloo Street Aberaeron Overflow |
| DCWW100113a · 5c2e5121 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ABERPORTH | Complete 2025-26 | Aberporth WwTW Storm Overflow |
| DCWW100180a · ff79647c | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CROSS INN / NEBO STW | Complete 2025-26 | Nebo WwTW Storm Overflow |
| DCWW100270a · 21f30b04 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANGEFNI STW LLANGEFNI ANGLESEY | Complete 2025-26 | Llwyncelyn WwTW Storm Overflow |
| DCWW100280a · 984fe4ab | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANINA WWTW/LL OLD H'DWATERS PS | Complete 2025-26 | Llanina Point Storm Overflow |
| DCWW100286a · fbd63d8e | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANRHYSTUD WWTW CEREDIGION | Complete 2025-26 | Llanrhystud WwTW Storm Overflow |
| DCWW100298a · e5a00a70 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLWYNCELYN STW | Complete 2025-26 | Llwyncelyn WwTW Storm Overflow |
| DCWW102126a · fbf2fb3f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANON (NR NEBO) STW | Due 2026-27 | Water body only |
| DCWW100689a · bd810041 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LLWYNCELYN (S OF ABERAERON) | Due 2027-28 | Llwyncelyn WwTW Storm Overflow |
| DCWW100652a · 09f3bea1 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ LLWYNCELYN (S OF ABERAERON) | Due 2027-28 | Llwyncelyn WwTW Storm Overflow |
| DCWW101582a · 4ce11a29 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ABERAERON PS EOF | Due 2029-30 | Waterloo Street Aberaeron Overflow |
| DCWW101074a · 1c926d13 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ABERAERON SPS, FORESHORE CAR PARK, ABERAERON | Due 2029-30 | Waterloo Street Aberaeron Overflow |
| DCWW101075a · f511591c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ABERAERON STW, INLET PUMPING STATION, DOLWEN, LAMPETER ROAD, ABERAERON | Due 2029-30 | Waterloo Street Aberaeron Overflow |
| DCWW101582a · 978e9afc | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ABERARTH Sewage Pumping Station | Due 2029-30 | Aberarth Storm Overflow |
| DCWW101119a · 17b951de | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ABERARTH SEWAGE PUMPING STATION | Due 2029-30 | Aberarth Storm Overflow |
| DCWW102740a · 5fb0ad2f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ABERPORTH HEADLAND E/O | Due 2029-30 | Aberporth Headland Overflow |
| DCWW101032a · cadaab22 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ABERPORTH HEADLAND PS ABERPORTH | Due 2029-30 | Aberporth Headland Overflow |
| DCWW100998a · d5725f98 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Aberporth No 1 Pumping Station | Due 2029-30 | Aberporth No. 1 Storm Overflow |
| DCWW101031a · f79906de | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ABERPORTH STW ABERPORTH , | Due 2029-30 | Aberporth WwTW Storm Overflow |
| DCWW102549a · 3325dd7e | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BRYNOG ARMS PH YSTRAD AERON SPS CSO | Due 2029-30 | Ystrad Aeron Storm Overflow |
| DCWW101456a · 4673a24d | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Brynog Arms PS, Ystrad Aeron, Ceredigion | Due 2029-30 | Ystrad Aeron Storm Overflow |
| DCWW101124a · 4a678ae9 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CEI BACH SPS, NEWQUAY | Due 2029-30 | Ceibach Storm Overflow |
| DCWW101582a · 7ae3d27a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Cross Inn / Nebo STW Settled Storm | Due 2029-30 | Nebo WwTW Storm Overflow |
| DCWW100692a · 837ce387 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ CROSS INN & NEBO | Due 2029-30 | Nebo WwTW Storm Overflow |
| DCWW101473a · 21296b9c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CSO & EO at Aberporth PS No 2 Austins | Due 2029-30 | Aberporth No. 2 Storm Overflow |
| DCWW101582a · d28f3ae4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO and EO at Cei Bach SPS | Due 2029-30 | Ceibach Storm Overflow |
| DCWW101582a · 09070b06 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Toad Hall Bridge Street, Aberaeron, Ceredigion, | Due 2029-30 | Heol Y Farchnad Road Storm Overflow |
| DCWW101582a · e8b2f6bd | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Ffos-y-ffin CSO | Due 2029-30 | Ffos-y-ffin Storm Overflow |
| DCWW101582a · 5ed0fb24 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANARTH BRIDGE CSO LLANARTH CERE'N | Due 2029-30 | Llanarth Bridge Storm Overflow |
| DCWW102723a · fb9af08b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANGRANOG CSO | Due 2029-30 | Llangranog Beach Storm Overflow |
| DCWW102415a · 9dd1c504 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANINA STW EOF | Due 2029-30 | Llanina Point Storm Overflow |
| DCWW101116a · 80d73f51 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANINA WwTW OLD HEADWATER PS | Due 2029-30 | Llanina Point Storm Overflow |
| DCWW101115a · f562678f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANINA WwTW PS | Due 2029-30 | Llanina Point Storm Overflow |
| DCWW101582a · ab5fd0e5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANINA WWTW PS LLANINA NEW QUAY | Due 2029-30 | Llanina Point Storm Overflow |
| DCWW102374a · 9cdab909 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANRHYSTUD STW | Due 2029-30 | Llanrhystud WwTW Storm Overflow |
| DCWW100935a · 66841509 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANRHYSTUD WwTW INLET SPS | Due 2029-30 | Llanrhystud WwTW Storm Overflow |
| DCWW101122a · 6c436c9c | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANSAINTFFRAID SEWAGE PUMPING STATION | Due 2029-30 | Water body only |
| DCWW101582a · 10954ad0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llwyncelyn STW Settled Storm | Due 2029-30 | Llwyncelyn WwTW Storm Overflow |
| DCWW101089a · 22b43649 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Mill View SPS, Llangranog, Ceredigion | Due 2029-30 | Mill View Llangranog Storm Overflow |
| DCWW101582a · d92d7e3d | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Mydroilyn WwTW Storm Overflow | Due 2029-30 | Mydroilyn WwTW Storm Overflow |
| DCWW101582a · 44ecb18a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PUMPING STATION ADJ TO NANT HAWEN | Due 2029-30 | Mill View Llangranog Storm Overflow |
| DCWW100962a · dd1c9432 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ROCK STREET PS, NEW QUAY | Due 2029-30 | Wellington Place Car Park Storm Overflow |
| DCWW100977a · c5605bd7 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Ship Inn Car Park PS, Llangranog | Due 2029-30 | Llangranog Beach Storm Overflow |
| DCWW101582a · 9f8bdbed | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Tresaith CSO | Due 2029-30 | Lower Tresaith Storm Overflow |
| DCWW100964a · 7167dacd | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ WATER ST, ABERAERON | Due 2029-30 | Peniel Lane Storm Overflow |
| DCWW101582a · 2819c656 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ WATER ST.SWO.ABERAERON ABERAE | Due 2029-30 | Peniel Lane Storm Overflow |
| DCWW101582a · de4120b8 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Wellington St CSO Abera Ab | Due 2029-30 | Harbour Lane Junction Storm Overflow |
| DCWW100963a · 04e3c5d8 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ WELLINGTON ST, ABERAERON | Due 2029-30 | Harbour Lane Junction Storm Overflow |
48 of 48 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.