River Hub
Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

48
Measures in this catchment
NEP, current record
41
Still active
not yet past their date
7
Assumed complete
completion date has passed
3
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100106a · 9c6fa816W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ABERAERON
Complete 2025-26Waterloo Street Aberaeron Overflow
DCWW100113a · 5c2e5121W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ABERPORTH
Complete 2025-26Aberporth WwTW Storm Overflow
DCWW100180a · ff79647cW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CROSS INN / NEBO STW
Complete 2025-26Nebo WwTW Storm Overflow
DCWW100270a · 21f30b04W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANGEFNI STW LLANGEFNI ANGLESEY
Complete 2025-26Llwyncelyn WwTW Storm Overflow
DCWW100280a · 984fe4abW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANINA WWTW/LL OLD H'DWATERS PS
Complete 2025-26Llanina Point Storm Overflow
DCWW100286a · fbd63d8eW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANRHYSTUD WWTW CEREDIGION
Complete 2025-26Llanrhystud WwTW Storm Overflow
DCWW100298a · e5a00a70W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLWYNCELYN STW
Complete 2025-26Llwyncelyn WwTW Storm Overflow
DCWW102126a · fbf2fb3fW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANON (NR NEBO) STW
Due 2026-27Water body only
DCWW100689a · bd810041W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLWYNCELYN (S OF ABERAERON)
Due 2027-28Llwyncelyn WwTW Storm Overflow
DCWW100652a · 09f3bea1W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLWYNCELYN (S OF ABERAERON)
Due 2027-28Llwyncelyn WwTW Storm Overflow
DCWW101582a · 4ce11a29W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ABERAERON PS EOF
Due 2029-30Waterloo Street Aberaeron Overflow
DCWW101074a · 1c926d13W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERAERON SPS, FORESHORE CAR PARK, ABERAERON
Due 2029-30Waterloo Street Aberaeron Overflow
DCWW101075a · f511591cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERAERON STW, INLET PUMPING STATION, DOLWEN, LAMPETER ROAD, ABERAERON
Due 2029-30Waterloo Street Aberaeron Overflow
DCWW101582a · 978e9afcW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ABERARTH Sewage Pumping Station
Due 2029-30Aberarth Storm Overflow
DCWW101119a · 17b951deW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERARTH SEWAGE PUMPING STATION
Due 2029-30Aberarth Storm Overflow
DCWW102740a · 5fb0ad2fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ABERPORTH HEADLAND E/O
Due 2029-30Aberporth Headland Overflow
DCWW101032a · cadaab22W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERPORTH HEADLAND PS ABERPORTH
Due 2029-30Aberporth Headland Overflow
DCWW100998a · d5725f98W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Aberporth No 1 Pumping Station
Due 2029-30Aberporth No. 1 Storm Overflow
DCWW101031a · f79906deW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ABERPORTH STW ABERPORTH ,
Due 2029-30Aberporth WwTW Storm Overflow
DCWW102549a · 3325dd7eW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BRYNOG ARMS PH YSTRAD AERON SPS CSO
Due 2029-30Ystrad Aeron Storm Overflow
DCWW101456a · 4673a24dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Brynog Arms PS, Ystrad Aeron, Ceredigion
Due 2029-30Ystrad Aeron Storm Overflow
DCWW101124a · 4a678ae9W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CEI BACH SPS, NEWQUAY
Due 2029-30Ceibach Storm Overflow
DCWW101582a · 7ae3d27aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cross Inn / Nebo STW Settled Storm
Due 2029-30Nebo WwTW Storm Overflow
DCWW100692a · 837ce387W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
CROSS INN & NEBO
Due 2029-30Nebo WwTW Storm Overflow
DCWW101473a · 21296b9cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CSO & EO at Aberporth PS No 2 Austins
Due 2029-30Aberporth No. 2 Storm Overflow
DCWW101582a · d28f3ae4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO and EO at Cei Bach SPS
Due 2029-30Ceibach Storm Overflow
DCWW101582a · 09070b06W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Toad Hall Bridge Street, Aberaeron, Ceredigion,
Due 2029-30Heol Y Farchnad Road Storm Overflow
DCWW101582a · e8b2f6bdW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Ffos-y-ffin CSO
Due 2029-30Ffos-y-ffin Storm Overflow
DCWW101582a · 5ed0fb24W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANARTH BRIDGE CSO LLANARTH CERE'N
Due 2029-30Llanarth Bridge Storm Overflow
DCWW102723a · fb9af08bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANGRANOG CSO
Due 2029-30Llangranog Beach Storm Overflow
DCWW102415a · 9dd1c504W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANINA STW EOF
Due 2029-30Llanina Point Storm Overflow
DCWW101116a · 80d73f51W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANINA WwTW OLD HEADWATER PS
Due 2029-30Llanina Point Storm Overflow
DCWW101115a · f562678fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANINA WwTW PS
Due 2029-30Llanina Point Storm Overflow
DCWW101582a · ab5fd0e5W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANINA WWTW PS LLANINA NEW QUAY
Due 2029-30Llanina Point Storm Overflow
DCWW102374a · 9cdab909W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANRHYSTUD STW
Due 2029-30Llanrhystud WwTW Storm Overflow
DCWW100935a · 66841509W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANRHYSTUD WwTW INLET SPS
Due 2029-30Llanrhystud WwTW Storm Overflow
DCWW101122a · 6c436c9cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANSAINTFFRAID SEWAGE PUMPING STATION
Due 2029-30Water body only
DCWW101582a · 10954ad0W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llwyncelyn STW Settled Storm
Due 2029-30Llwyncelyn WwTW Storm Overflow
DCWW101089a · 22b43649W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Mill View SPS, Llangranog, Ceredigion
Due 2029-30Mill View Llangranog Storm Overflow
DCWW101582a · d92d7e3dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Mydroilyn WwTW Storm Overflow
Due 2029-30Mydroilyn WwTW Storm Overflow
DCWW101582a · 44ecb18aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PUMPING STATION ADJ TO NANT HAWEN
Due 2029-30Mill View Llangranog Storm Overflow
DCWW100962a · dd1c9432W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ROCK STREET PS, NEW QUAY
Due 2029-30Wellington Place Car Park Storm Overflow
DCWW100977a · c5605bd7W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Ship Inn Car Park PS, Llangranog
Due 2029-30Llangranog Beach Storm Overflow
DCWW101582a · 9f8bdbedW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Tresaith CSO
Due 2029-30Lower Tresaith Storm Overflow
DCWW100964a · 7167dacdW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
WATER ST, ABERAERON
Due 2029-30Peniel Lane Storm Overflow
DCWW101582a · 2819c656W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
WATER ST.SWO.ABERAERON ABERAE
Due 2029-30Peniel Lane Storm Overflow
DCWW101582a · de4120b8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Wellington St CSO Abera Ab
Due 2029-30Harbour Lane Junction Storm Overflow
DCWW100963a · 04e3c5d8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
WELLINGTON ST, ABERAERON
Due 2029-30Harbour Lane Junction Storm Overflow

48 of 48 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.