Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

35
Measures in this catchment
WINEP, current record
22
Still active
not yet past their date
13
Assumed complete
completion date has passed
5
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08TW100552 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BAMPTON STW
Complete 2025-26Bampton STW
08TW100567 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BURFORD STW
Complete 2025-26Burford STW
08TW100569 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CARTERTON STW
Complete 2025-26Carterton STW
08TW100583 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CLANFIELD STW
Complete 2025-26Clanfield STW
08TW100602 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
FARINGDON SEWAGE TREATMENT WORKS (Last in Line Overflow off site)
Complete 2025-26Thames (Leach to Evenlode)
08TW100635 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
LECHLADE STW
Complete 2025-26Lechlade STW
08TW100715 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
NORTHLEACH STW
Complete 2025-26Northleach STW
08TW100664 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SOUTH LEIGH STW
Complete 2025-26South Leigh STW
08TW100666 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
STANDLAKE STW
Complete 2025-26Standlake STW
08TW100668 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
STANTON HARCOURT STW
Complete 2025-26Stanton Harcourt STW
08TW100730 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WITNEY SEWAGE TREATMENT WORKS
Complete 2025-26Windrush and tributaries (Little Rissington to Thames)
08TW101402 · gWFDGW_NDNo deterioration
Necessary scope to move from groundwater authorisation to EPR
GW authorisation to EPR: Temple Guiting STW
Complete 2025-26Windrush (Source to Slade Barn Stream)
08TW100877 · aEnvAct_IMP1Improvement
0.4 mg/l Phosphorus permit at Bourton-on-the-Water STW
Reduce Phosphorus Loadings at Bourton-on-the-Water STW
Complete 2025-26Dikler (Wyck Rissington to Windrush) and Lower Eye
08TW100415 · aU_MON4Monitoring
Install and run event-duration monitoring
BAMPTON STW
Due 2026-27Bampton STW
08TW100302 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
BURFORD STW
Due 2026-27Burford STW
08TW100305 · aU_MON4Monitoring
Install and run event-duration monitoring
CARTERTON STW
Due 2026-27Carterton STW
08TW100317 · aU_MON4Monitoring
Install and run event-duration monitoring
CLANFIELD STW
Due 2026-27Clanfield STW
08TW100333 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
FARINGDON SEWAGE TREATMENT WORKS (Last in Line Overflow off site)
Due 2026-27Thames (Leach to Evenlode)
08TW100357 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
LECHLADE STW
Due 2026-27Lechlade STW
08TW100371 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
NORTHLEACH STW
Due 2026-27Northleach STW
08TW101405 · dEDWRMP_INVInvestigation
Large catchment investigation
Seven Springs - Environmental Destination
Due 2026-27Windrush (Slade Barn Stream to Dikler)
08TW101610 · aU_MON4Monitoring
Install and run event-duration monitoring
SOUTH LEIGH STW
Due 2026-27South Leigh STW
08TW100449 · aU_MON4Monitoring
Install and run event-duration monitoring
STANDLAKE STW
Due 2026-27Standlake STW
08TW100387 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
STANTON HARCOURT STW
Due 2026-27Stanton Harcourt STW
08TW100408 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
WITNEY SEWAGE TREATMENT WORKS
Due 2026-27Windrush and tributaries (Little Rissington to Thames)
08TW100101 · aWFD_NDLS_Chem2No deterioration
Witney STW, cypermethrin, 0.000163 ug
Reduce cypermethrin loading
Due 2026-27Windrush and tributaries (Little Rissington to Thames)
08TW100491 · aWFD_NDLS_Chem1No deterioration
Stanton Harcourt STW cypermethrin load standstill limit
Stanton Harcourt STW
Due 2026-27Stanton Harcourt STW
08TW101108 · thEnvAct_INV4Investigation
Storm Overflows investigation
FARINGDON WWTW- Storm Overflows investigation
Due 2027-28Thames (Leach to Evenlode)
08TW101108 · tlEnvAct_INV4Investigation
Storm Overflows investigation
SOUTH LEIGH WWTW- Storm Overflows investigation
Due 2027-28Chil and Limb Brooks (source to B4044)
08TW101108 · cjEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at STANDLAKE STW
Due 2027-28Windrush and tributaries (Little Rissington to Thames)
08TW101108 · qrEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at Witney STW
Due 2027-28Windrush and tributaries (Little Rissington to Thames)
08TW100954 · aEnvAct_IMP1Improvement
0.25 mg/l Phosphorus permit at Buckland STW
Reduce Phosphorus Loadings at Buckland STW
Due 2029-30Wadley Stream (Source to Thames at Duxford)
11TW100004 · aENVAct_IMP2Improvement
Option C1: Investigation and Solution in AMP 8: FFT Equivalent, 428m3 storage, 1.53Ha SUDS IA Removal, No screen required
Storm Overflows action at Bampton STW
Due 2029-30Shill Brook and Tributaries
08TW101032 · aEnvAct_IMP2Improvement
Option C1: Solution in AMP 08: 804m of sewer relining, 0.33Ha SUDS IA Removal, No screen required
Storm Overflows action at SOUTH LEIGH STW
Due 2029-30Chil and Limb Brooks (source to B4044)
08TW101033 · aENVAct_IMP2Improvement
Option C2: 1,851m2 wetland equivalent treatment, 1.15 Ha SUDS IA Removal, 44m3 storage and 20m3 screen
Storm Overflows action at STANDLAKE STW
Due 2029-30Windrush and tributaries (Little Rissington to Thames)

35 of 35 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.