What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08TW100556 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BENTLEY STW | Complete 2025-26 | Bentley STW |
| 08TW100562 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BORDON STW | Complete 2025-26 | Bordon STW |
| 08TW100575 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CHERTSEY STW | Complete 2025-26 | Chertsey STW |
| 08TW100579 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CHOBHAM STW | Complete 2025-26 | Chobham STW |
| 08TW100586 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) CRANLEIGH STW | Complete 2025-26 | Cranleigh STW |
| 08TW100604 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) FARNHAM STW | Complete 2025-26 | Farnham STW |
| 08TW100609 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) GODALMING STW | Complete 2025-26 | Godalming STW |
| 08TW100614 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) GUILDFORD STW | Complete 2025-26 | Guildford STW |
| 08TW100621 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HASLEMERE STW, ( SHOTTERMILL ) | Complete 2025-26 | South Wey (Haslemere to Bordon) |
| 08TW100625 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HOCKFORD SEWAGE TREATMENT WORKS | Complete 2025-26 | Hoe Stream (Pirbright to River Wey confluence at Woking) |
| 08TW100636 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) LIGHTWATER STW | Complete 2025-26 | Lightwater STW |
| 08TW100714 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Newmans Lane PS (Alton STW) | Complete 2025-26 | Caker Stream |
| 08TW100655 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) RIPLEY STW | Complete 2025-26 | Ripley STW |
| 08TW100657 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) SELBORNE STW | Complete 2025-26 | Selborne STW |
| 08TW100658 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) SHAMLEY GREEN STW | Complete 2025-26 | Shamley Green STW |
| 08TW100683 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) WEYBRIDGE STW ( SEVEN ARCHESBRIDGE) | Complete 2025-26 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100689 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) WOKING STW | Complete 2025-26 | Woking STW |
| 08TW101573 · a | U_MON4 | Monitoring | Install and run event-duration monitoring BENTLEY STW | Due 2026-27 | Bentley STW |
| 08TW100295 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) BORDON STW | Due 2026-27 | Bordon STW |
| 08TW100311 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) CHERTSEY STW | Due 2026-27 | Chertsey STW |
| 08TW101581 · a | U_MON4 | Monitoring | Install and run event-duration monitoring CHOBHAM STW | Due 2026-27 | Chobham STW |
| 08TW100319 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) CRANLEIGH STW | Due 2026-27 | Cranleigh STW |
| 08TW100433 · a | U_MON4 | Monitoring | Install and run event-duration monitoring FARNHAM STW | Due 2026-27 | Farnham STW |
| 08TW100434 · a | U_MON4 | Monitoring | Install and run event-duration monitoring GODALMING STW | Due 2026-27 | Godalming STW |
| 08TW100420 · a | U_MON4 | Monitoring | Install and run event-duration monitoring GUILDFORD STW | Due 2026-27 | Guildford STW |
| 08TW101593 · a | U_MON4 | Monitoring | Install and run event-duration monitoring HASLEMERE STW, ( SHOTTERMILL ) | Due 2026-27 | South Wey (Bordon to River Slea confluence) |
| 08TW100346 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) HOCKFORD SEWAGE TREATMENT WORKS | Due 2026-27 | Hoe Stream (Pirbright to River Wey confluence at Woking) |
| 08TW100358 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) LIGHTWATER STW | Due 2026-27 | Lightwater STW |
| 08TW100370 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Newmans Lane PS (Alton STW) | Due 2026-27 | Caker Stream |
| 08TW101606 · a | U_MON4 | Monitoring | Install and run event-duration monitoring SELBORNE STW | Due 2026-27 | Selborne STW |
| 08TW100379 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) SHAMLEY GREEN STW | Due 2026-27 | Shamley Green STW |
| 08TW100453 · a | U_MON4 | Monitoring | Install and run event-duration monitoring WEYBRIDGE STW ( SEVEN ARCHESBRIDGE) | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100409 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) WOKING STW | Due 2026-27 | Woking STW |
| 08TW101447 · a | WFD_NDLS_Chem1 | No deterioration | Alton STW cypermethrin permit limit Alton STW- Reduce Cypermethrin loading | Due 2026-27 | Caker Stream |
| 08TW100474 · a | WFD_NDLS_Chem1 | No deterioration | Chertsey STW cypermethrin load standstill permit limit Chertsey STW | Due 2026-27 | Chertsey STW |
| 08TW100483 · a | WFD_NDLS_Chem1 | No deterioration | Hockford STW cypermethrin load standstill limit Hockford STW | Due 2026-27 | Hockford STW |
| 08TW100145 · a | WFD_NDLS_Chem2 | No deterioration | new PFOS limit PFOS Weybridge STW | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100146 · a | WFD_NDLS_Chem2 | No deterioration | new PFOS limit PFOS Wisley STW | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100095 · a | WFD_NDLS_Chem2 | No deterioration | Shamely Green STW, cypermethrin, 0.001031ug Reduce cypermethrin loading | Due 2026-27 | Cranleigh Waters |
| 08TW100100 · a | WFD_NDLS_Chem2 | No deterioration | Wisley STW, cypermethrin, 0.000764ug Reduce cypermethrin loading | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100098 · a | WFD_NDLS_Chem2 | No deterioration | Weybridge STW, cypermethrin, 0.003679ug Reduce cypermethrin loading | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100075 · a | WFD_NDLS_Chem2 | No deterioration | Cranleigh STW, cypermethrin, 0.002866ug Reduce cypermethrin loading | Due 2026-27 | Cranleigh Waters |
| 08TW100072 · a | WFD_NDLS_Chem2 | No deterioration | Chobham STW, cypermethrin, 0.000515ug Reduce cypermethrin loading | Due 2026-27 | Addlestone Bourne (West End to Hale/Mill Bourne confluence at Mimbridge) |
| 08TW100140 · a | WFD_NDLS_Chem2 | No deterioration | Hockford STW, zinc (dissolved), 6.68 Reduce metal loading | Due 2026-27 | Hoe Stream (Pirbright to River Wey confluence at Woking) |
| 08TW100103 · a | WFD_NDLS_Chem2 | No deterioration | Lightwater STW, iron (total), 1667.7 Reduce metal loading | Due 2026-27 | Hale/Mill Bourne (Bagshot to Addlestone Bourne confluence near Chobham) |
| 08TW100104 · a | WFD_NDLS_Chem2 | No deterioration | Alton STW, Nonylphenol, 0.642484 ug Reduce Nonylphenol loading | Due 2026-27 | Caker Stream |
| 08TW100136 · a | WFD_NDLS_Chem2 | No deterioration | Weybridge STW, Nonylphenol, 0.82 ug Reduce Nonylphenol loading | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100131 · a | WFD_NDLS_Chem2 | No deterioration | Ripley STW, Nonylphenol, 0.61 ug Reduce Nonylphenol loading | Due 2026-27 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100116 · a | WFD_NDLS_Chem2 | No deterioration | Chertsey STW, Nonylphenol, 0.55 ug Reduce Nonylphenol loading | Due 2026-27 | Chertsey Bourne (Chertsey to River Thames confluence) |
| 08TW100112 · a | WFD_NDLS_Chem2 | No deterioration | Bordon STW, Nonylphenol, 0.73 ug Reduce Nonylphenol loading | Due 2026-27 | South Wey (Bordon to River Slea confluence) |
| 08TW101545 · e | WFD_INV_CHEM | Investigation | PFOS investigation - Weybridge STW 4a Investigation to develop and trial a framework that meets statutory requirements | Due 2027-28 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW101545 · f | WFD_INV_CHEM | Investigation | PFOS investigation - Wisley STW 4a Investigation to develop and trial a framework that meets statutory requirements | Due 2027-28 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW101108 · tc | EnvAct_INV4 | Investigation | Storm Overflows investigation BORDON WASTEWATER TREATMENT WORKS- Storm Overflows investigation | Due 2027-28 | South Wey (Bordon to River Slea confluence) |
| 08TW101108 · te | EnvAct_INV4 | Investigation | Storm Overflows investigation CHOBHAM (OLD) WWTW- Storm Overflows investigation | Due 2027-28 | Addlestone Bourne (West End to Hale/Mill Bourne confluence at Mimbridge) |
| 08TW101108 · ae | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at BENTLEY STW | Due 2027-28 | North Wey (Alton to Tilford) |
| 08TW101108 · qg | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at Farnham STW | Due 2027-28 | North Wey (Alton to Tilford) |
| 08TW101108 · fu | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at HOLYBOURNE SPS | Due 2027-28 | North Wey (Alton to Tilford) |
| 08TW101108 · gu | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at HUCKERS LANE (SELBOURNE) SPS | Due 2027-28 | Oakhanger Stream |
| 08TW101108 · ab | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at NEWMANS LANE SPS | Due 2027-28 | North Wey at Alton |
| 08TW101108 · gv | EnvAct_INV4 | Investigation | Investigate the cause of the spills Storm Overflows investigation at SELBORNE STW | Due 2027-28 | Oakhanger Stream |
| 08TW100002 · a | WFD_ND_WRFlow | No deterioration | Engineering solutions to enable reduction Netley WTW sustainability reduction | Due 2029-30 | Tillingbourne |
| 08TW100174 · a | WFD_IMPg | Improvement | Farnham STW, Dissolved oxygen (S+), 6 ug Reduce BOD loading | Due 2029-30 | North Wey (Alton to Tilford) |
| 08TW100465 · a | WFD_ND_CHEM3 | No deterioration | Alton STW cypermethrin permit limit Reduce cypermethrin loading | Due 2029-30 | Caker Stream |
| 08TW100886 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Chertsey STW Reduce Phosphorus Loadings at Chertsey STW | Due 2029-30 | Chertsey Bourne (Chertsey to River Thames confluence) |
| 09TW100049 · a | EnvAct_IMP1 | Improvement | 0.25 mg/l Phosphorus permit at Weybridge STW Reduce Phosphorus Loadings at Weybridge STW | Due 2029-30 | Wey (Shalford to River Thames confluence at Weybridge) |
| 08TW100981 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: FFT Equivalent, 1.48Ha SUDS IA Removal, No screen required Storm Overflows action at BENTLEY STW | Due 2029-30 | North Wey (Alton to Tilford) |
| 08TW100986 · a | EnvAct_IMP3 | Improvement | Option C1: Solution in AMP 08: Storage Solution20m3 screen Storm Overflows action at CHURT SPS | Due 2029-30 | South Wey (River Slea confluence to Tilford) |
| 11TW100035 · a | EnvAct_IMP2 | Improvement | Storm Overflows improvements at FARNHAM STW Storm Overflows action at FARNHAM STW | Due 2029-30 | North Wey (Alton to Tilford) |
| 08TW101073 · a | ENVAct_IMP2 | Improvement | Default scheme: Investigation and Solution in AMP 8: 1,285m3 storage, 20m3 screen Storm Overflows action at HOLYBOURNE SPS | Due 2029-30 | North Wey (Alton to Tilford) |
| 08TW101030 · a | ENVAct_IMP2 | Improvement | Default scheme: Investigation and Solution in AMP 8: 1,285m3 storage, 20m3 screen Storm Overflows action at HUCKERS LANE (SELBOURNE) SPS | Due 2029-30 | Oakhanger Stream |
| 08TW100976 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: Storage Solution20m3 screen Storm Overflows action at Newmans Lane SPS | Due 2029-30 | North Wey at Alton |
| 08TW101089 · a | ENVAct_IMP2 | Improvement | Option C1: Investigation and Solution in AMP 8: 726m of sewer relining, 0.30Ha SUDS IA Removal, No screen required Storm Overflows action at Selborne STW | Due 2029-30 | Oakhanger Stream |
| 08TW104007 · a | WFD_IMP_PHYSHAB | Improvement | Implement a river restorations schmeme to promote natural morphological processes Tillingbourne habitat improvement measures | Due 2029-30 | Tillingbourne |
73 of 73 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.