Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

73
Measures in this catchment
WINEP, current record
56
Still active
not yet past their date
17
Assumed complete
completion date has passed
11
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08TW100556 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BENTLEY STW
Complete 2025-26Bentley STW
08TW100562 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BORDON STW
Complete 2025-26Bordon STW
08TW100575 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CHERTSEY STW
Complete 2025-26Chertsey STW
08TW100579 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CHOBHAM STW
Complete 2025-26Chobham STW
08TW100586 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CRANLEIGH STW
Complete 2025-26Cranleigh STW
08TW100604 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
FARNHAM STW
Complete 2025-26Farnham STW
08TW100609 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
GODALMING STW
Complete 2025-26Godalming STW
08TW100614 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
GUILDFORD STW
Complete 2025-26Guildford STW
08TW100621 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
HASLEMERE STW, ( SHOTTERMILL )
Complete 2025-26South Wey (Haslemere to Bordon)
08TW100625 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
HOCKFORD SEWAGE TREATMENT WORKS
Complete 2025-26Hoe Stream (Pirbright to River Wey confluence at Woking)
08TW100636 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
LIGHTWATER STW
Complete 2025-26Lightwater STW
08TW100714 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Newmans Lane PS (Alton STW)
Complete 2025-26Caker Stream
08TW100655 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
RIPLEY STW
Complete 2025-26Ripley STW
08TW100657 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SELBORNE STW
Complete 2025-26Selborne STW
08TW100658 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
SHAMLEY GREEN STW
Complete 2025-26Shamley Green STW
08TW100683 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WEYBRIDGE STW ( SEVEN ARCHESBRIDGE)
Complete 2025-26Wey (Shalford to River Thames confluence at Weybridge)
08TW100689 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
WOKING STW
Complete 2025-26Woking STW
08TW101573 · aU_MON4Monitoring
Install and run event-duration monitoring
BENTLEY STW
Due 2026-27Bentley STW
08TW100295 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
BORDON STW
Due 2026-27Bordon STW
08TW100311 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
CHERTSEY STW
Due 2026-27Chertsey STW
08TW101581 · aU_MON4Monitoring
Install and run event-duration monitoring
CHOBHAM STW
Due 2026-27Chobham STW
08TW100319 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
CRANLEIGH STW
Due 2026-27Cranleigh STW
08TW100433 · aU_MON4Monitoring
Install and run event-duration monitoring
FARNHAM STW
Due 2026-27Farnham STW
08TW100434 · aU_MON4Monitoring
Install and run event-duration monitoring
GODALMING STW
Due 2026-27Godalming STW
08TW100420 · aU_MON4Monitoring
Install and run event-duration monitoring
GUILDFORD STW
Due 2026-27Guildford STW
08TW101593 · aU_MON4Monitoring
Install and run event-duration monitoring
HASLEMERE STW, ( SHOTTERMILL )
Due 2026-27South Wey (Bordon to River Slea confluence)
08TW100346 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
HOCKFORD SEWAGE TREATMENT WORKS
Due 2026-27Hoe Stream (Pirbright to River Wey confluence at Woking)
08TW100358 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
LIGHTWATER STW
Due 2026-27Lightwater STW
08TW100370 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Newmans Lane PS (Alton STW)
Due 2026-27Caker Stream
08TW101606 · aU_MON4Monitoring
Install and run event-duration monitoring
SELBORNE STW
Due 2026-27Selborne STW
08TW100379 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
SHAMLEY GREEN STW
Due 2026-27Shamley Green STW
08TW100453 · aU_MON4Monitoring
Install and run event-duration monitoring
WEYBRIDGE STW ( SEVEN ARCHESBRIDGE)
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100409 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
WOKING STW
Due 2026-27Woking STW
08TW101447 · aWFD_NDLS_Chem1No deterioration
Alton STW cypermethrin permit limit
Alton STW- Reduce Cypermethrin loading
Due 2026-27Caker Stream
08TW100474 · aWFD_NDLS_Chem1No deterioration
Chertsey STW cypermethrin load standstill permit limit
Chertsey STW
Due 2026-27Chertsey STW
08TW100483 · aWFD_NDLS_Chem1No deterioration
Hockford STW cypermethrin load standstill limit
Hockford STW
Due 2026-27Hockford STW
08TW100145 · aWFD_NDLS_Chem2No deterioration
new PFOS limit
PFOS Weybridge STW
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100146 · aWFD_NDLS_Chem2No deterioration
new PFOS limit
PFOS Wisley STW
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100095 · aWFD_NDLS_Chem2No deterioration
Shamely Green STW, cypermethrin, 0.001031ug
Reduce cypermethrin loading
Due 2026-27Cranleigh Waters
08TW100100 · aWFD_NDLS_Chem2No deterioration
Wisley STW, cypermethrin, 0.000764ug
Reduce cypermethrin loading
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100098 · aWFD_NDLS_Chem2No deterioration
Weybridge STW, cypermethrin, 0.003679ug
Reduce cypermethrin loading
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100075 · aWFD_NDLS_Chem2No deterioration
Cranleigh STW, cypermethrin, 0.002866ug
Reduce cypermethrin loading
Due 2026-27Cranleigh Waters
08TW100072 · aWFD_NDLS_Chem2No deterioration
Chobham STW, cypermethrin, 0.000515ug
Reduce cypermethrin loading
Due 2026-27Addlestone Bourne (West End to Hale/Mill Bourne confluence at Mimbridge)
08TW100140 · aWFD_NDLS_Chem2No deterioration
Hockford STW, zinc (dissolved), 6.68
Reduce metal loading
Due 2026-27Hoe Stream (Pirbright to River Wey confluence at Woking)
08TW100103 · aWFD_NDLS_Chem2No deterioration
Lightwater STW, iron (total), 1667.7
Reduce metal loading
Due 2026-27Hale/Mill Bourne (Bagshot to Addlestone Bourne confluence near Chobham)
08TW100104 · aWFD_NDLS_Chem2No deterioration
Alton STW, Nonylphenol, 0.642484 ug
Reduce Nonylphenol loading
Due 2026-27Caker Stream
08TW100136 · aWFD_NDLS_Chem2No deterioration
Weybridge STW, Nonylphenol, 0.82 ug
Reduce Nonylphenol loading
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100131 · aWFD_NDLS_Chem2No deterioration
Ripley STW, Nonylphenol, 0.61 ug
Reduce Nonylphenol loading
Due 2026-27Wey (Shalford to River Thames confluence at Weybridge)
08TW100116 · aWFD_NDLS_Chem2No deterioration
Chertsey STW, Nonylphenol, 0.55 ug
Reduce Nonylphenol loading
Due 2026-27Chertsey Bourne (Chertsey to River Thames confluence)
08TW100112 · aWFD_NDLS_Chem2No deterioration
Bordon STW, Nonylphenol, 0.73 ug
Reduce Nonylphenol loading
Due 2026-27South Wey (Bordon to River Slea confluence)
08TW101545 · eWFD_INV_CHEMInvestigation
PFOS investigation - Weybridge STW
4a Investigation to develop and trial a framework that meets statutory requirements
Due 2027-28Wey (Shalford to River Thames confluence at Weybridge)
08TW101545 · fWFD_INV_CHEMInvestigation
PFOS investigation - Wisley STW
4a Investigation to develop and trial a framework that meets statutory requirements
Due 2027-28Wey (Shalford to River Thames confluence at Weybridge)
08TW101108 · tcEnvAct_INV4Investigation
Storm Overflows investigation
BORDON WASTEWATER TREATMENT WORKS- Storm Overflows investigation
Due 2027-28South Wey (Bordon to River Slea confluence)
08TW101108 · teEnvAct_INV4Investigation
Storm Overflows investigation
CHOBHAM (OLD) WWTW- Storm Overflows investigation
Due 2027-28Addlestone Bourne (West End to Hale/Mill Bourne confluence at Mimbridge)
08TW101108 · aeEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at BENTLEY STW
Due 2027-28North Wey (Alton to Tilford)
08TW101108 · qgEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at Farnham STW
Due 2027-28North Wey (Alton to Tilford)
08TW101108 · fuEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at HOLYBOURNE SPS
Due 2027-28North Wey (Alton to Tilford)
08TW101108 · guEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at HUCKERS LANE (SELBOURNE) SPS
Due 2027-28Oakhanger Stream
08TW101108 · abEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at NEWMANS LANE SPS
Due 2027-28North Wey at Alton
08TW101108 · gvEnvAct_INV4Investigation
Investigate the cause of the spills
Storm Overflows investigation at SELBORNE STW
Due 2027-28Oakhanger Stream
08TW100002 · aWFD_ND_WRFlowNo deterioration
Engineering solutions to enable reduction
Netley WTW sustainability reduction
Due 2029-30Tillingbourne
08TW100174 · aWFD_IMPgImprovement
Farnham STW, Dissolved oxygen (S+), 6 ug
Reduce BOD loading
Due 2029-30North Wey (Alton to Tilford)
08TW100465 · aWFD_ND_CHEM3No deterioration
Alton STW cypermethrin permit limit
Reduce cypermethrin loading
Due 2029-30Caker Stream
08TW100886 · aEnvAct_IMP1Improvement
0.25 mg/l Phosphorus permit at Chertsey STW
Reduce Phosphorus Loadings at Chertsey STW
Due 2029-30Chertsey Bourne (Chertsey to River Thames confluence)
09TW100049 · aEnvAct_IMP1Improvement
0.25 mg/l Phosphorus permit at Weybridge STW
Reduce Phosphorus Loadings at Weybridge STW
Due 2029-30Wey (Shalford to River Thames confluence at Weybridge)
08TW100981 · aENVAct_IMP2Improvement
Option C1: Investigation and Solution in AMP 8: FFT Equivalent, 1.48Ha SUDS IA Removal, No screen required
Storm Overflows action at BENTLEY STW
Due 2029-30North Wey (Alton to Tilford)
08TW100986 · aEnvAct_IMP3Improvement
Option C1: Solution in AMP 08: Storage Solution20m3 screen
Storm Overflows action at CHURT SPS
Due 2029-30South Wey (River Slea confluence to Tilford)
11TW100035 · aEnvAct_IMP2Improvement
Storm Overflows improvements at FARNHAM STW
Storm Overflows action at FARNHAM STW
Due 2029-30North Wey (Alton to Tilford)
08TW101073 · aENVAct_IMP2Improvement
Default scheme: Investigation and Solution in AMP 8: 1,285m3 storage, 20m3 screen
Storm Overflows action at HOLYBOURNE SPS
Due 2029-30North Wey (Alton to Tilford)
08TW101030 · aENVAct_IMP2Improvement
Default scheme: Investigation and Solution in AMP 8: 1,285m3 storage, 20m3 screen
Storm Overflows action at HUCKERS LANE (SELBOURNE) SPS
Due 2029-30Oakhanger Stream
08TW100976 · aENVAct_IMP2Improvement
Option C1: Investigation and Solution in AMP 8: Storage Solution20m3 screen
Storm Overflows action at Newmans Lane SPS
Due 2029-30North Wey at Alton
08TW101089 · aENVAct_IMP2Improvement
Option C1: Investigation and Solution in AMP 8: 726m of sewer relining, 0.30Ha SUDS IA Removal, No screen required
Storm Overflows action at Selborne STW
Due 2029-30Oakhanger Stream
08TW104007 · aWFD_IMP_PHYSHABImprovement
Implement a river restorations schmeme to promote natural morphological processes
Tillingbourne habitat improvement measures
Due 2029-30Tillingbourne

73 of 73 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.