Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

33
Measures in this catchment
WINEP, current record
33
Still active
not yet past their date
0
Assumed complete
completion date has passed
8
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SO104731 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Bognor Main
Due 2026-27Aldingbourne Rife
08SO102694 · aU_MON3Monitoring
U_MON3b: MCERTS certified overflow operation monitor
Bognor Main WPS
Due 2026-27Aldingbourne Rife
08SO102493 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Lavant WTW
Due 2026-27Lavant (Sussex)
08SO102791 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
LAVANT WWTW
Due 2026-27Lavant (Sussex)
08SO102433 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Lidsey WTW
Due 2026-27Lidsey Rife
08SO102794 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
LIDSEY WWTW
Due 2026-27Lidsey Rife
08SO102499 · aU_MON4Monitoring
U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils
Sidlesham WTW
Due 2026-27Broad Rife
08SO102873 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
SIDLESHAM WWTW
Due 2026-27Broad Rife
08SO102527 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Summer Lane Pagham WTW
Due 2026-27Pagham Rife
08SO102897 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
SUMMER LANE PAGHAM WWTW
Due 2026-27Pagham Rife
08SO104733 · aU_MON4Monitoring
U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring
Tangmere WTW
Due 2026-27Aldingbourne Rife
08SO102900 · aU_MON3Monitoring
U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor
TANGMERE WWTW
Due 2026-27Aldingbourne Rife
08SO101180 · aBW_NDNo deterioration
SuDS and storage. Costings are based on the least cost option, which is a 30m3 storage tank. However, SuDS will be explored first to maximise green options before sizing any storage needed to achieve the spill requirements of 2 or less spills per bathing water season. Note: Overflow discharges to inalnd watercourse, but as the reason is for bathing waters, a EnvAct_IMP3 secondary driver has been assigned.
Bognor Main CEO
Due 2026-27Aldingbourne Rife
08SO101101 · cWFD_NDLS_Chem1No deterioration
Prevent any deterioration
Tangmere WTW
Due 2026-27Aldingbourne Rife
08SO104950 · opEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
LAVANT NO. SSO
Due 2027-28Lavant (Sussex)
08SO104950 · bbEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
LIDSEY SSO
Due 2027-28LIDSEY RIFE
08SO104950 · rhEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
MARSHALL CLOSE BARNHAM CSO
Due 2027-28Lidsey Rife
08SO103818 · aWFD_INVInvestigation
Investigations for actions to improve water quality in terms of relevant WFD status objectives.
SIDLESHAM WTW
Due 2027-28Broad Rife
08SO104950 · lEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the Shellfish Water and ensure no more than 10 spills per annum (on average) as an agglomeration
SINGLETON RELIEF CEO
Due 2027-28Lavant (Sussex)
08SO104950 · pqEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
SUMMER LANE PAGHAM SSO
Due 2027-28Pagham Rife
08SO100043 · cvEnvAct_INV4Investigation
Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact
TANGMERE SSO
Due 2027-28ALDINGBOURNE RIFE
08SO104029 · aWFD_INVInvestigation
Investigate the cause of the spills
Tangmere WTW WFD_INV
Due 2027-28Aldingbourne Rife
08SO103964 · aSW_NDNo deterioration
Wetland + Lining
SINGLETON RELIEF CEO
Due 2027-28Lavant (Sussex)
08SO103980 · aHD_IMP_NNImprovement
Amend permit limit of Total N to 10 mg/l
LAVANT WWTW
Due 2029-30Lavant (Sussex)
08SO104042 · aWFD_NDNo deterioration
Amend WFD ND BOD permit
LIDSEY
Due 2029-30Lidsey Rife
08SO100198 · aEnvAct_IMP2Improvement
Currently meets Defra rainfall target but may need <0 spill solution to prevent ecological harm
TANGMERE SSO
Due 2029-30ALDINGBOURNE RIFE
08SO101101 · bWFD_IMP_CHEMImprovement
Deliver a physical improvement
Tangmere WTW
Due 2029-30Aldingbourne Rife
08SO101101 · aWFD_ND_CHEM4No deterioration
Prevent any deterioration
Tangmere WTW
Due 2029-30Aldingbourne Rife
08SO100999 · aU_IMP1Improvement
Actions to improve discharges from agglomerations that, through population growth, have crossed the population thresholds in the UWWTR and therefore must achieve more stringent UWWTR requirements. This includes newly qualifying discharges (from agglomerations >10,000population equivalent (PE)) within existing Sensitive Areas. This includes discharges of >2,000 PE to fresh waters and estuaries and discharges >10,000 PE to coastal waters, as well as discharges >10,000 PE and 100,000 PE to Sensitive Areas.
Summer Lane Pagham WWTW
Due 2030-31Pagham Rife
08SO103956 · aEnvAct_IMP2Improvement
Wetland + Lining
LAVANT NO SSO
Due 2034-35Lavant (Sussex)
08SO103958 · aEnvAct_IMP4Improvement
Wetland + Lining
LIDSEY SSO
Due 2034-35Lidsey Rife
08SO103929 · aEnvAct_IMP2Improvement
Preferred option is SuDS and Storage, but costs based on storage only
MARSHALL CLOSE BARNHAM CSO
Due 2034-35Lidsey Rife
08SO103914 · aEnvAct_IMP2Improvement
SuDS + Storage
SUMMER LANE PAGHAM SSO
Due 2034-35Pagham Rife

33 of 33 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.