Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

24
Measures in this catchment
WINEP, current record
24
Still active
not yet past their date
0
Assumed complete
completion date has passed
6
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08WW103158 · aWFD_NDINV_WRFlowInvestigation
Investigate effect of abstraction from Wessex Water's source at Friar Waddon on the River Wey
Frair Waddon WFD ND investigation
Due 2026-27Wey
08WW100092 · aWFD_NDINV_WRFlowInvestigation
Investigate effect of abstraction from Wessex Water's source at Litton Cheney on the WFD status of the River Bride
Litton Cheney WFD ND investigation
Due 2026-27Bride
08WW100776 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Puncknowle WRC Flow Monitoring
Due 2026-27Bride
08WW100549 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Puncknowle WRC Overflow Monitoring
Due 2026-27Bride
08WW100895 · aU_MON4Monitoring
MCERTS certified Flow passed forward flow monitor (U_MON4e)
WEST MILTON WRC flow monitoring
Due 2026-27Mangerton Brook
08WW100873 · aU_MON3Monitoring
MCERTS certified overflow operation monitor (U_MON3b)
WEST MILTON WRC overflow monitoring
Due 2026-27Mangerton Brook
08WW101000 · gcEnvAct_INV4Investigation
Storm overflows - Investigations
***A-WINEP*** BRIDPORT WEST STREET CSO SO Investigation (16822C)
Due 2027-28Brit (Upper)
08WW101000 · awEnvAct_INV4Investigation
Storm overflows - Investigations
CHICKERELL ROAD CSO SO Investigation (16848C)
Due 2027-28WEY
08WW101000 · hpEnvAct_INV4Investigation
Storm overflows - Investigations
CHICKSBRIDGE PS SO Investigation (14415B)
Due 2027-28Bride
08WW101000 · lsEnvAct_INV4Investigation
Storm overflows - Investigations
LONGCROFT ROAD CSO SO Investigation (16853C)
Due 2027-28WEY
08WW101000 · axEnvAct_INV4Investigation
Storm overflows - Investigations
NEWSTEAD ROAD PUMPING STATION SO Investigation (15552B)
Due 2027-28WEY
08WW101000 · cbEnvAct_INV4Investigation
Storm overflows - Investigations
PUNCKNOWLE WRC SO Investigation (13250S)
Due 2027-28Bride
08WW101000 · ayEnvAct_INV4Investigation
Storm overflows - Investigations
RODWELL AVENUE CSO SO Investigation (16857C)
Due 2027-28WEY
08WW101000 · enEnvAct_INV4Investigation
Storm overflows - Investigations
ROMAN ROAD COMBINED SEWER OVERFLOW SO Investigation (17030C)
Due 2027-28Wey
08WW101000 · nuEnvAct_INV4Investigation
Storm overflows - Investigations
SOUTH STREET CSO
Due 2027-28Brit (Upper)
08WW101000 · avEnvAct_INV4Investigation
Storm overflows - Investigations
SPRING LANE CSO SO Investigation (16861C)
Due 2027-28WEY
08WW101000 · lvEnvAct_INV4Investigation
Storm overflows - Investigations
SPRING ROAD COMBINED SEWER OVERFLOW SO Investigation (19557C)
Due 2027-28WEY
08WW101000 · luEnvAct_INV4Investigation
Storm overflows - Investigations
WESTON ROAD CSO SO Investigation (16864C)
Due 2027-28WEY
08WW101002 · ejEnvAct_IMP4Improvement
EnvAct_IMP4ej. Storm overflows - - Frequency improvements
CHICKERELL ROAD CSO SO improvement (16848C)
Due 2029-30WEY
08WW101002 · wbEnvAct_IMP4Improvement
Storm overflows - Wetland treatment solution.
LITTON CHENEY, CHICKSBRIDGE (Site ID 14415B)
Due 2029-30Bride
08WW101002 · ekEnvAct_IMP4Improvement
EnvAct_IMP4ek. Storm overflows - - Frequency improvements
NEWSTEAD ROAD PUMPING STATION SO improvement (15552B)
Due 2029-30WEY
08WW101002 · anEnvAct_IMP4Improvement
EnvAct_IMP4an. Storm overflows - Frequency improvements
PUNCKNOWLE WRC SO improvement (13250S)
Due 2029-30Bride
08WW101002 · elEnvAct_IMP4Improvement
EnvAct_IMP4el. Storm overflows - - Frequency improvements
RODWELL AVENUE CSO SO improvement (16857C)
Due 2029-30WEY
08WW101002 · czEnvAct_IMP4Improvement
EnvAct_IMP4cz. Storm overflows - Frequency improvements
ROMAN ROAD COMBINED SEWER OVERFLOW SO improvement (17030C)
Due 2029-30Wey

24 of 24 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.