Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

136
Measures in this catchment
NEP, current record
118
Still active
not yet past their date
18
Assumed complete
completion date has passed
41
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100114a · 832086a7W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ADPAR WWTW ADPAR CEREDIGION
Complete 2025-26Adpar Storm Overflow
DCWW100127a · f57602bfW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BEULAH WWTW INLET SO BEULAH CERED'N
Complete 2025-26Beulah WwTW Storm Overflow
DCWW100133a · 9bf7f9bcW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BONCATH STW
Complete 2025-26Boncath WwTW Storm Overflow
DCWW100155a · cab2b16bW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CARDIGAN WWTW(STW) CARDIGAN
Complete 2025-26Cardigan WwTW Storm Overflow
DCWW100160a · d39cf3d9W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CENARTH (GLANYRAFON)
Complete 2025-26Cenarth WwTW Storm Overflow
DCWW100164a · 30ffe871W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CILGERRAN STW
Complete 2025-26Cilgerran WwTW Storm Overflow
DCWW100074a · a8248dedW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CWRTNEWYDD STW CWRTNEWTDD
Complete 2025-26Cwrtnewydd WwTW Storm Overflow
DCWW100076a · e0e664d8W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
DREFACH/VELINDRE WWTW
Complete 2025-26Llysnewydd Storm Overflow
DCWW100079a · 0dd665a3W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
HENLLAN STW
Complete 2025-26Henllan Storm Overflow
DCWW100235a · fadac404W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LAMPETER STW LAMPETER
Complete 2025-26Lampeter Storm Overflow
DCWW100248a · e7181cccW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANDEWI BREFI WWTW LLANDEWI BREFI
Complete 2025-26Llanddewi Brefi WwTW Storm Overflow
DCWW100294a · 0c33ee8aW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANYBYDDER WWTW CEREDIGION
Complete 2025-26Llanybydder Storm Overflow
DCWW100296a · 6651e5c2W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLECHRYD STW
Complete 2025-26Llechryd No 1 Storm Overflow
DCWW100328a · dbd89808W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PENCADER STW
Complete 2025-26Pencader WwTW Storm Overflow
DCWW100335a · aecb144fW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PENTRECWRT STW
Complete 2025-26Pentrecwrt WwTW Storm Overflow
DCWW100092a · 53da6f15W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PONTRHYDFENDIGAID STW
Complete 2025-26Pontrhydfendigaid Storm Overflow
DCWW100094a · c62bc27dW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
RHYDLEWIS
Complete 2025-26Rhydlewis South WwTW Storm Overflow
DCWW100393a · 1512e6eeW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TREFRIW STW
Complete 2025-26Tregaron WwTw Storm Overflow
DCWW100109a · 3ed49f89W_U_MON4Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows
WQ
ABERCYCH STW
Due 2026-27Abercych Storm Overflow
DCWW100108a · c3c4cf66W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ABERCYCH STW
Due 2026-27Abercych Storm Overflow
DCWW101594a · 27819417W_WFD_PG_IMP2Improvement
Implementation of actions to achieve Good status at a waterbody and / or site level due to Biological Oxygen Demand (BOD) in WaSC discharges relating to Dissolved Oxygen (DO) status of the waterbody
WQ
Beulah
Due 2026-27BEULAH (NR Aberporth)
DCWW101657a · f935f041W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
BONCATH
Due 2026-27BONCATH
DCWW102196a · a9572952W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARDIGAN NO 3 SPS STORM
Due 2026-27Cardigan Bridge Storm Overflow
DCWW102197a · 6db4d881W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARDIGAN NO 4 SPS EOF
Due 2026-27Quay Street Car Park Storm Overflow
DCWW102210a · 57f2b479W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CARDIGAN WwTW STORM CSO
Due 2026-27Cardigan WwTW Storm Overflow
DCWW102123a · d439d4ccW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CENARTH NO 1 SPS
Due 2026-27Cenarth South of Afon Storm Overflow
DCWW102143a · 901f019fW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CILGERRAN&PENYBRYN PS NO 1 EOF
Due 2026-27Cilgerran No.1 Storm Overflow
DCWW100175a · b636adacW_U_MON4Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows
WQ
CRIBYN STW
Due 2026-27Cribyn WwTW Storm Overflow
DCWW100176a · 14896ed6W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CRIBYN STW
Due 2026-27Cribyn WwTW Storm Overflow
DCWW101538a · e80f2ed2W_FISH_IMP1Improvement
Implementation of actions to prevent or mitigate causes of entrainment or impediment to fish passage. Including removal of assets or deliver / install / construct fish passage solutions at sites where water company assets have been identified to impede fish passage, to include sites where their assets are the barrier in it’s entirety, or where their asset forms part of the barrier preventing or restricting fish passage. This includes both up and downstream fish passage.
Fish
Fish Barrier Mitigation at asset 40414511
Due 2026-27Water body only
DCWW101679a · 25d5c877W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
PONTRHYDYCEIRT
Due 2026-27PONTRHYDYCEIRT
DCWW102198a · 80ce3bb3W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ST DOGMAELS MAIN PS
Due 2026-27St Dogmaels Main Storm Overflow
DCWW102199a · e6d2aaa8W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ST DOGMAELS, REAR OF PH, MAESHYFRYD
Due 2026-27St. Dogmaels Maeshyfryd Street Storm Overflow
DCWW101649a · 035ad00dW_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper
WQ
PENPRYS (7CDC1104)
Due 2027-28PONTRHYDYCEIRT
DCWW100700a · 89635c6dW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
TREGARON
Due 2027-28Tregaron WwTw Storm Overflow
DCWW100656a · 0e99d903W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
TREGARON
Due 2027-28Tregaron WwTw Storm Overflow
DCWW101582a · 5d73b80bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
A Sewage Pumping Station at Llanwnen, Llanybydder
Due 2029-30Llanwnnen South Storm Overflow
DCWW101582a · 61facd07W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Aberbanc Sewage Pumping Station
Due 2029-30Aberbanc Storm Overflow
DCWW101085a · 0273ae24W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Aberbanc SPS, nr Newcastle Emlyn, SA44 5NP
Due 2029-30Aberbanc Storm Overflow
DCWW101781a · 6025ff17W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
ABERCYCH STW
Due 2029-30Water body only
DCWW101782a · 5c6bc431W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
ADPAR STW
Due 2029-30Water body only
DCWW101782b · 1b95a855W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
ADPAR WWTW ADPAR CEREDIGION
Due 2029-30Water body only
DCWW100889a · 67ddfbd6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ALLTYBLACCA, LLANYBYDDER, DYFED
Due 2029-30Alltyblaca Overflow
DCWW100695a · 7efe9f46W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
BEULAH (NR ABERPORTH)
Due 2029-30Beulah WwTW Storm Overflow
DCWW101784a · 8962ff2fW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
BONCATH STW
Due 2029-30BONCATH
DCWW101582a · 14d0e472W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BRIDGE STREET CSO LAMPETER
Due 2029-30New Street Lampeter Storm Overflow
DCWW101114a · b33398b5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Bryn Steffan, Residential Development, Adj Aberaeron Road, Lampeter, SA48 8AW
Due 2029-30Water body only
DCWW101582a · f2c619edW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cardigan - Penparc CSO
Due 2029-30Penparc Storm Overflow
DCWW102570a · 88653120W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cardigan - St.Mary Street
Due 2029-30St.Mary Street Storm Overflow
DCWW100904a · 8c8d4377W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CARDIGAN 1
Due 2029-30Pont-Y-Cleifion Storm Overflow
DCWW100905a · bbb40673W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CARDIGAN 2
Due 2029-30St.Mary Street Storm Overflow
DCWW100906a · f77a35b8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Cardigan Bridge PS
Due 2029-30Cardigan Bridge Storm Overflow
DCWW101582a · 194b5ca3W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cardigan Hospital CSO
Due 2029-30Pont-Y-Cleifion Storm Overflow
DCWW100907a · 5e20b946W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CARDIGAN PS NO.4 (CSO & EO)
Due 2029-30Quay Street Car Park Storm Overflow
DCWW100908a · 27c12671W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CARDIGAN SPS NO 5 (CSO & EO)
Due 2029-30Cardigan Cattle Market Storm Overflow
DCWW101786a · 6e157ac3W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CELLAN STW
Due 2029-30Water body only
DCWW101787a · b07007c2W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CENARTH 2 STW
Due 2029-30CENARTH NO 2 (GLANYRAFON)
DCWW101471a · 245dfedcW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CENARTH 2 STW (GLANYRAFON)
Due 2029-30Cenarth WwTW Storm Overflow
DCWW101010a · 9b2ed895W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CENARTH NO.1 SEWAGE PUMPING STATION
Due 2029-30Cenarth South of Afon Storm Overflow
DCWW100974a · 2a0e4a1aW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CENARTH SEWAGE PUMPING STATION
Due 2029-30Cenarth South of Afon Storm Overflow
DCWW101582a · 05913d9fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cenarth Wastewater Treatment Works Inlet Storm Overflow
Due 2029-30Cenarth WwTW Storm Overflow
DCWW101787b · ba883dfdW_HR_AMM_T_IMP1Improvement
Ammonia reduction to meet numeric permit limit Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
CENARTH WWTTW CENARTH CEREDIGION
Due 2029-30CENARTH NO 2 (GLANYRAFON)
DCWW100662a · ba4fa9b7W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
CILGERRAN
Due 2029-30Cilgerran WwTW Storm Overflow
DCWW101582a · f6683b02W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Cilgerran Flyght PS
Due 2029-30Cnwcau Storm Overflow
DCWW101455a · ba46f01aW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Cilgerran Sewage Pumping Station
Due 2029-30Cilgerran No.1 Storm Overflow
DCWW101788a · 27ff6dbcW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CILGERRAN SEWAGE TREATMENT WORKS
Due 2029-30CILGERRAN
DCWW101788b · d57067b2W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
CILGERRAN STW
Due 2029-30CILGERRAN
DCWW102768a · 1568147dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CWM PLYSGOG CSO
Due 2029-30Off Church Street Cwm Plysgog Storm Overflow
DCWW101062a · 40d0855cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Cwmann SPS, Lampeter
Due 2029-30Cwmann Overflow
DCWW100923a · 3c5c0224W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CWRTNEWYDD SPS NO1
Due 2029-30Cwrtnewydd WwTW Storm Overflow
DCWW101790a · fbf69c8dW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
CWRTNEWYDD STW CWRTNEWTDD
Due 2029-30CWRTNEWYDD
DCWW100924a · b7a56de1W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
DolwenSPS, Drefach, Llanybydder
Due 2029-30Dolwen Storm Overflow
DCWW101791a · 41190f60W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
Drefach/Velindre
Due 2029-30HENLLAN (NR Newcastle Emlyn)
DCWW101913a · 0b6ec3e6W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Ffostrasol WwTW
Due 2029-30Ffostrasol WwTW Overflow
DCWW101582a · ffc8d2f8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Gloster Row SPS
Due 2029-30Cardigan Cattle Market Storm Overflow
DCWW100595a · ab18e10eW_U_IMP7(a-e)Improvement
Upgrade septic tank primary treated effluent to secondary treated effluent capable of delivering 40/60 BOD/SS Biological Oxygen Demand: Suspended Soilids
WQ
GREENFIELD TERRACE Septic Tank
Due 2029-30Water body only
DCWW100936a · 5a1c5c56W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Grove Park Estate, Cnwc-y-Dintir, Cardigan, SA43 1AX
Due 2029-30Water body only
DCWW101120a · 140ec900W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GWBERT SEWAGE PUMPING STATION
Due 2029-30Gwbert Overflow
DCWW102521a · d8164f09W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
HENLLAN (NR NEWCASTLE EMLYN) STW STORM
Due 2029-30Henllan Storm Overflow
DCWW101794a · 6b140e57W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
HENLLAN STW
Due 2029-30HENLLAN (NR Newcastle Emlyn)
DCWW101025a · f6f81a27W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
HOREB SEWAGE PUMPING STATION, LLANDYSUL, DYFED
Due 2029-30Water body only
DCWW101965a · a503a5c6W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Lampeter - No. 3, University
Due 2029-30Lampeter Campus Storm Overflow
DCWW102856b · 6e7c29a5W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
LAMPETER STW   LAMPETER
Due 2029-30Water body only
DCWW101582a · 88e2e048W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llanddewi Brefi CSO
Due 2029-30Llanddewi Brefi Storm Overflow
DCWW101796a · 3ab59b4bW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANDYSSUL STW
Due 2029-30Water body only
DCWW101796b · fc7a8590W_HR_AMM_T_IMP1Improvement
Ammonia reduction to meet numeric permit limit Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
Llandysul Wastewater Treatment Works
Due 2029-30Water body only
DCWW101797a · 20c30ab6W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANFIHANGEL ARARTH STW
Due 2029-30LLANFIHANGEL-AR-ARTH
DCWW100927a · 06f35495W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANFIHANGEL-AR-ARTH STW
Due 2029-30Llanfihangel-ar-arth WwTW Overflow
DCWW101797b · 750f381fW_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
LLANFIHANGEL-AR-ARTH STW
Due 2029-30LLANFIHANGEL-AR-ARTH
DCWW101798a · 36ca38c5W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLANGYBI SEWAGE TREATMENT WORKS
Due 2029-30Water body only
DCWW101015a · 3c5e4dabW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Llanwnen SPS, Llanybydder
Due 2029-30Llanwnnen South Storm Overflow
DCWW100677a · 68d513b8W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANYBYDDER
Due 2029-30Llanybydder Storm Overflow
DCWW102248a · 8c819c7cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llanybydder - Oriel Jones
Due 2029-30Heol Llanbedr Llanybydder Storm Overflow
DCWW101036a · 3a36c36bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLECHRYD NO 1 SPS NEAR CARDIGAN DYFED
Due 2029-30Llechryd No 1 Storm Overflow
DCWW101582a · 1325a81fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llechryd SPS
Due 2029-30Llechryd No 1 Storm Overflow
DCWW101799b · 3630fe7aW_HR_AMM_T_IMP1Improvement
Ammonia reduction to meet numeric permit limit Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
LLECHRYD STW
Due 2029-30Water body only
DCWW101799a · 76a762bcW_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
LLECHRYD STW
Due 2029-30Water body only
DCWW101582a · c0b4a165W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llysnewydd SPS
Due 2029-30Llysnewydd Storm Overflow
DCWW100901a · 601d2ba6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Llysnewydd SPS, Velindre, Llandysul, Dyfed
Due 2029-30Llysnewydd Storm Overflow
DCWW100926a · 0019a203W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Manhole 7 CSO & EO from Llanybydder Terminal SPS,
Due 2029-30Llanybydder Cattle Market Storm Overflow
DCWW101582a · 9fd941e9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Newchapel STW CSO
Due 2029-30Newchapel WwTW Storm Overflow
DCWW100913a · 159e3f30W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Oriel Jones SPS, Llanybydder, Ceredigion
Due 2029-30Water body only
DCWW101582a · 9913f8cdW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pencader Bridge CSO
Due 2029-30Pencader Bridge Storm Overflow
DCWW101582a · 1a8c278aW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pencader SPS
Due 2029-30Pencader Storm Overflow
DCWW100882a · 5b08f47fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Pencader SPS, Pencader, Carms SA39 9ES
Due 2029-30Pencader Storm Overflow
DCWW101801b · efdf3dadW_HR_AMM_T_IMP1Improvement
Ammonia reduction to meet numeric permit limit Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
PENCADER STW
Due 2029-30PENCADER
DCWW100883a · 123503feW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PENCADER STW PS
Due 2029-30Pencader WwTW Storm Overflow
DCWW101582a · 667cacfdW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Penrhiwllan SPS
Due 2029-30Penrhiwllan Storm Overflow
DCWW101109a · a145453dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Penrhiwllan SPS, Llandysul, Ceredigion SA44 5NG
Due 2029-30Penrhiwllan Storm Overflow
DCWW101802a · 0c760871W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
PENTRECWRT STW
Due 2029-30PENTRECWRT
DCWW101802b · 03f05c83W_HR_AMM_T_IMP1Improvement
Operational costs relating to Ammonia permit condition Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments.
WQ
PENTRECWRT STW
Due 2029-30PENTRECWRT
DCWW101088a · cb26d231W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Pentrellwyn Pumping Station, Off Gorig Road, Pentrellwyn
Due 2029-30Water body only
DCWW101960a · 667fea3dW_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Pontrhydfendgaid SPS
Due 2029-30Pontrhydfendigaid Storm Overflow
DCWW101883a · 1d52c691W_HR_P_ND_IMP1Improvement
Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure.
WQ
Pontrhydyceirt STW Pontrhydyceirt
Due 2029-30PONTRHYDYCEIRT
DCWW101972a · 6aa4d148W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Rhos/Llangeler (Capel Seilo) SPS CSO
Due 2029-30Capel Silo Storm Overflow
DCWW100902a · aa3abf9bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHYDFACH PS
Due 2029-30Rhydfach Storm Overflow
DCWW101958a · ed2ff952W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Rhydlewis
Due 2029-30Rhydlewis South WwTW Storm Overflow
DCWW101582a · 7ca6e2c6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
RHYDLEWIS PS NO 1
Due 2029-30Rhydlewis North PS Storm Overflow
DCWW100950a · f15956e7W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHYDLEWIS PS NO 1
Due 2029-30Rhydlewis North PS Storm Overflow
DCWW100951a · be7361fbW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHYDLEWIS PS NO 2
Due 2029-30Rhydlewis South WwTW Storm Overflow
DCWW102707a · 37198d6dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Saron - A484 O.S.Maesgeler
Due 2029-30Saron Storm Overflow
DCWW101582a · 5308606fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Settled Storm Overflow at Ferwig Wastewater Treatment Works
Due 2029-30Verwig WwTW Storm Overflow
DCWW101582a · dbbfd2e6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Settled Storm Overflow at Llandewi Brefi Wastewater Treatment Works
Due 2029-30Llanddewi Brefi WwTW Storm Overflow
DCWW101582a · c0a4f587W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Silian PS Lampeter Ceredigion
Due 2029-30Silian Storm Overflow
DCWW101110a · c5ecd5d8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Silian PS Lampeter, Ceredigion
Due 2029-30Silian Storm Overflow
DCWW101582a · e38cf18cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
St Dogmaels CSO
Due 2029-30Glanteifon Storm Overflow
DCWW101106a · e57e8ffbW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ST DOGMAELS NORTH END SPS (CSO & EO)
Due 2029-30St. Dogmaels No.2 Storm Overflow
DCWW100910a · d3059861W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
ST DOGMAELS, JEWSONS CSO (ST DOGMAELS MAIN PS CSO & EO)
Due 2029-30St Dogmaels Main Storm Overflow
DCWW101582a · cef618feW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Storm Overflow at Rhydlewis Wastewater Treatment Works
Due 2029-30Rhydlewis South WwTW Storm Overflow
DCWW101121a · aebe4d10W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TALGARREG WASTEWATER TREATMENT WORKS LIFT PUMPING STATION
Due 2029-30Talgarreg WwTW Storm Overflow
DCWW101582a · 6edc8b3bW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Tregaron SPS (CSO and EO
Due 2029-30Tregaron Storm Overflow
DCWW100900a · 9201df4dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Tregaron SPS, High Street, Tregaron
Due 2029-30Tregaron Storm Overflow
DCWW101582a · f4da97f1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Ty Hen Rhos PS
Due 2029-30Capel Silo Storm Overflow
DCWW101111a · 258f63a7W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Ty Hen Rhos/Capel Silo SPS, Lon Helyg, Rhos, Llandysul, Dyfed SA44 5HD
Due 2029-30Capel Silo Storm Overflow
DCWW101956a · 185ccfe3W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Verwig WwTW
Due 2029-30Verwig WwTW Storm Overflow
DCWW101582a · 31b21973W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
WILKES HEAD CSO LLANDYSUL CERED'N
Due 2029-30Northeast of Lewis Street Storm Overflow

136 of 136 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.