What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SW104928 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) BUCKLAND MONACHORUM | Due 2026-27 | lower river tavy |
| 08SW104927 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) BUCKLAND MONACHORUM | Due 2026-27 | lower river tavy |
| 08SW104780 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HORRABRIDGE STW | Due 2026-27 | Walkham |
| 08SW104779 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) HORRABRIDGE STW | Due 2026-27 | Walkham |
| 08SW104764 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Lamerton STW | Due 2026-27 | Lumburn |
| 08SW104765 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Lamerton STW | Due 2026-27 | Lumburn |
| 08SW104730 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) MARY TAVY STW | Due 2026-27 | Upper River Tavy |
| 08SW104731 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) MARY TAVY STW | Due 2026-27 | Upper River Tavy |
| 08SW104579 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) TAVISTOCK STW | Due 2026-27 | Lumburn |
| 08SW104580 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) TAVISTOCK STW | Due 2026-27 | Lumburn |
| 08SW102972 · a | HD_INV | Investigation | Investigation and options appraisal to restore EFI, and investigation into habitat and/or flow improvements associated with Dartmoor SAC and Plymouth Sounds SAC. Tavy at Lopwell Dam and Abbey Weir - Lower Tavy | Due 2026-27 | Lower River Tavy |
| 08SW102973 · a | HD_INV | Investigation | Investigate and confirm within waterbody impact caused by HEP abstraction. (Barrier to fish passage?) Tavy Cleave and Hill bridge - Upper River Tavy | Due 2026-27 | Upper River Tavy |
| 08SW104554 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) WALKHAMPTON STW | Due 2026-27 | Walkham |
| 08SW104553 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) WALKHAMPTON STW | Due 2026-27 | Walkham |
| 08SW104999 · aa | EnvAct_INV4 | Investigation | Investigation to meet EnvAct INV4 Driver BUCKLAND MONACHORUM STW_SSO_BUCKLAND MON | Due 2027-28 | BUCKLAND MONACHORUM STW_SSO_BUCKLAND MON |
| 08SW104999 · ge | EnvAct_INV4 | Investigation | Investigation to meet EnvAct INV4 Driver MARY TAVY STW_SSO_MARY TAVY | Due 2027-28 | MARY TAVY STW_SSO_MARY TAVY |
| 08SW104294 · a | U_IMP4 | Improvement | To comply with UWWTR PLAYING FIELD_CSO_TAVISTOCK | Due 2027-28 | PLAYING FIELD_CSO_TAVISTOCK |
| 08SW104295 · a | U_IMP4 | Improvement | To comply with UWWTR WESTBRIDGE COTTS_CSO_TAVISTOCK | Due 2027-28 | WESTBRIDGE COTTS_CSO_TAVISTOCK |
| 08SW102962 · a | EE_IMP | Improvement | (Abstraction) Combined INV/IMP required. SWW ownership to be confirmed. Site being looked at as part of the PR24 INTAKE project. Investigation and implementation. Eel Abstraction - R Tavy at Abbey Weir | Due 2029-30 | Lower River Tavy |
| 08SW102948 · a | EE_IMP | Improvement | (Abstraction) Combined INV/IMP required. Site being looked at as part of the PR24 INTAKE project. Eel Abstraction - R Tavy at Hill Bridge | Due 2029-30 | Upper River Tavy |
| 08SW102967 · d | EE_IMP | Improvement | Deliver a physical improvement Eel Obstruction - R Tavy at Abbey Weir | Due 2029-30 | Lower River Tavy |
| 08SW102967 · e | EE_IMP | Improvement | Deliver a physical improvement Eel Obstruction - R Tavy at Hill Bridge | Due 2029-30 | Lower River Tavy |
22 of 22 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.