Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

31
Measures in this catchment
NEP, current record
26
Still active
not yet past their date
5
Assumed complete
completion date has passed
5
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100229a · c7d36565W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
HERMON STW STORM OVERFLOW HERMON
Complete 2025-26Hermon WwTW Storm Overflow
DCWW100238a · 7bb25409W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LAUGHARNE WASTE WATER TREATMENT WKS
Complete 2025-26Laugharne WwTW Storm Overflow
DCWW100329a · f7d37303W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
PENDINE STW
Complete 2025-26Pendine WwTW Storm Overflow
DCWW100371a · 4aa0be96W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ST CLEARS SPS
Complete 2025-26St. Clears Storm Overflow
DCWW100409a · 8c1d9d77W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
WHITLAND WWTW WHITLAND CARMS
Complete 2025-26Whitland WwTW Storm Overflow
DCWW102191a · 5c87e3e5W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Craigwen New CSO
Due 2026-27Craigwen New Storm Overflow
DCWW102194a · 788d60baW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Laugharne - The Grist
Due 2026-27The Grist Storm Overflow
DCWW102208a · 756dadd4W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LAUGHARNE STW DISCHARGE
Due 2026-27Laugharne WwTW Storm Overflow
DCWW100648a · bd908b8fW_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANFYRNACH
Due 2027-28Llanfyrnach WwTW Storm Overflow
DCWW100690a · d90de362W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
TAVERNSPITE
Due 2027-28Tavernspite WwTW Storm Overflow
DCWW100655a · 8183f391W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
TAVERNSPITE
Due 2027-28Tavernspite WwTW Storm Overflow
DCWW102892a · 24334aabW_U_IMP1Improvement
Implementation of actions to improve discharges from agglomerations that, through population growth, have crossed the population thresholds in the UWWTR (Urban Waste Water Treatment Regulations) and therefore must achieve more stringent UWWTR requirements. This includes newly qualifying discharges (from agglomerations >10,000 population equivalent (pe)) within existing Sensitive Areas. This includes discharges of >2,000pe to freshwaters and estuaries, and discharges > 10,000pe to coastal waters, as well as discharges >10,000pe and 100,000pe to Sensitive Areas
WQ
Laugharne WWTW
Due 2028-29LAUGHARNE
DCWW100694a · fc680046W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
BANCYFELIN (ST CLEARS)
Due 2029-30Bancyfelin WwTW Storm Overflow
DCWW100888a · 3f3e06bfW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CARMARTHEN RD SPS, NR FELIN, CLIFTON, ST.CLEARS
Due 2029-30Water body only
DCWW100989a · ea686fd7W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
EMERGENCY DISCHARGE FROM P.S. GLASNANT CRYMYCH
Due 2029-30Water body only
DCWW100892a · d2a12d5bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Graigwen SPS,Tenby Road, St Clears
Due 2029-30Craigwen New Storm Overflow
DCWW100887a · 7ab61c61W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANBOIDY ROAD SPS, ST CLEARS
Due 2029-30Water body only
DCWW100959a · d3465375W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANBOIDY STW
Due 2029-30Llanboidy WwTW Storm Overflow
DCWW102380a · ed4393b4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANBOIDY STW
Due 2029-30Llanboidy WwTW Storm Overflow
DCWW100891a · 0ee0fdc4W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDDOWROR VILLAGE P.S
Due 2029-30Llanddowror Village Storm Overflow
DCWW101582a · ffaa1ae0W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llanfrynach SPS
Due 2029-30Llanfyrnach Storm Overflow
DCWW100976a · 7061cc0bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANFYRNACH SPS
Due 2029-30Llanfyrnach Storm Overflow
DCWW101582a · 069f346dW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llangynog STW
Due 2029-30Llangynog WwTW Storm Overflow
DCWW102388a · a9720cb9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
NARBERTH EAST STW
Due 2029-30Narberth East Storm Overflow
DCWW100996a · 97d50ecaW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
NARBERTH SPRINGFIELD PARK ESTATE PUMPING STATION
Due 2029-30Narberth East Storm Overflow
DCWW101582a · 3d054b80W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
PENDINE SEWAGE TREATMENT WORKS
Due 2029-30Pendine WwTW Storm Overflow
DCWW101582a · f1797266W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Settled Storm Overflow at Llanfyrnach Wastewater Treatment Works
Due 2029-30Llanfyrnach WwTW Storm Overflow
DCWW102558a · cd0be3adW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
St. Clears SPS CSO
Due 2029-30St. Clears Storm Overflow
DCWW101014a · 21648fc4W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
THE PUMPING STATION AT THE FORMER SITE OF NARBERTH EAST STW, NARBERTH, DYFED
Due 2029-30Narberth East Storm Overflow
DCWW100984a · 9c5dc845W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
WHITLAND TERMINAL PUMPING STATION
Due 2029-30Whitland Storm Overflow
DCWW101582a · c7555cd7W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Wogan Mews CSO
Due 2029-30Wogan Street Laugharne Storm Overflow

31 of 31 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.