What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100229a · c7d36565 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ HERMON STW STORM OVERFLOW HERMON | Complete 2025-26 | Hermon WwTW Storm Overflow |
| DCWW100238a · 7bb25409 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LAUGHARNE WASTE WATER TREATMENT WKS | Complete 2025-26 | Laugharne WwTW Storm Overflow |
| DCWW100329a · f7d37303 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PENDINE STW | Complete 2025-26 | Pendine WwTW Storm Overflow |
| DCWW100371a · 4aa0be96 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ST CLEARS SPS | Complete 2025-26 | St. Clears Storm Overflow |
| DCWW100409a · 8c1d9d77 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ WHITLAND WWTW WHITLAND CARMS | Complete 2025-26 | Whitland WwTW Storm Overflow |
| DCWW102191a · 5c87e3e5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Craigwen New CSO | Due 2026-27 | Craigwen New Storm Overflow |
| DCWW102194a · 788d60ba | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Laugharne - The Grist | Due 2026-27 | The Grist Storm Overflow |
| DCWW102208a · 756dadd4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LAUGHARNE STW DISCHARGE | Due 2026-27 | Laugharne WwTW Storm Overflow |
| DCWW100648a · bd908b8f | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANFYRNACH | Due 2027-28 | Llanfyrnach WwTW Storm Overflow |
| DCWW100690a · d90de362 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ TAVERNSPITE | Due 2027-28 | Tavernspite WwTW Storm Overflow |
| DCWW100655a · 8183f391 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ TAVERNSPITE | Due 2027-28 | Tavernspite WwTW Storm Overflow |
| DCWW102892a · 24334aab | W_U_IMP1 | Improvement | Implementation of actions to improve discharges from agglomerations that, through population growth, have crossed the population thresholds in the UWWTR (Urban Waste Water Treatment Regulations) and therefore must achieve more stringent UWWTR requirements. This includes newly qualifying discharges (from agglomerations >10,000 population equivalent (pe)) within existing Sensitive Areas. This includes discharges of >2,000pe to freshwaters and estuaries, and discharges > 10,000pe to coastal waters, as well as discharges >10,000pe and 100,000pe to Sensitive Areas WQ Laugharne WWTW | Due 2028-29 | LAUGHARNE |
| DCWW100694a · fc680046 | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ BANCYFELIN (ST CLEARS) | Due 2029-30 | Bancyfelin WwTW Storm Overflow |
| DCWW100888a · 3f3e06bf | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CARMARTHEN RD SPS, NR FELIN, CLIFTON, ST.CLEARS | Due 2029-30 | Water body only |
| DCWW100989a · ea686fd7 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ EMERGENCY DISCHARGE FROM P.S. GLASNANT CRYMYCH | Due 2029-30 | Water body only |
| DCWW100892a · d2a12d5b | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Graigwen SPS,Tenby Road, St Clears | Due 2029-30 | Craigwen New Storm Overflow |
| DCWW100887a · 7ab61c61 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANBOIDY ROAD SPS, ST CLEARS | Due 2029-30 | Water body only |
| DCWW100959a · d3465375 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANBOIDY STW | Due 2029-30 | Llanboidy WwTW Storm Overflow |
| DCWW102380a · ed4393b4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANBOIDY STW | Due 2029-30 | Llanboidy WwTW Storm Overflow |
| DCWW100891a · 0ee0fdc4 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANDDOWROR VILLAGE P.S | Due 2029-30 | Llanddowror Village Storm Overflow |
| DCWW101582a · ffaa1ae0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llanfrynach SPS | Due 2029-30 | Llanfyrnach Storm Overflow |
| DCWW100976a · 7061cc0b | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANFYRNACH SPS | Due 2029-30 | Llanfyrnach Storm Overflow |
| DCWW101582a · 069f346d | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llangynog STW | Due 2029-30 | Llangynog WwTW Storm Overflow |
| DCWW102388a · a9720cb9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NARBERTH EAST STW | Due 2029-30 | Narberth East Storm Overflow |
| DCWW100996a · 97d50eca | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ NARBERTH SPRINGFIELD PARK ESTATE PUMPING STATION | Due 2029-30 | Narberth East Storm Overflow |
| DCWW101582a · 3d054b80 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PENDINE SEWAGE TREATMENT WORKS | Due 2029-30 | Pendine WwTW Storm Overflow |
| DCWW101582a · f1797266 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Settled Storm Overflow at Llanfyrnach Wastewater Treatment Works | Due 2029-30 | Llanfyrnach WwTW Storm Overflow |
| DCWW102558a · cd0be3ad | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ St. Clears SPS CSO | Due 2029-30 | St. Clears Storm Overflow |
| DCWW101014a · 21648fc4 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ THE PUMPING STATION AT THE FORMER SITE OF NARBERTH EAST STW, NARBERTH, DYFED | Due 2029-30 | Narberth East Storm Overflow |
| DCWW100984a · 9c5dc845 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ WHITLAND TERMINAL PUMPING STATION | Due 2029-30 | Whitland Storm Overflow |
| DCWW101582a · c7555cd7 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Wogan Mews CSO | Due 2029-30 | Wogan Street Laugharne Storm Overflow |
31 of 31 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.