What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SW104887 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) Churchinford STW | Due 2026-27 | Upper River Otter |
| 08SW104888 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Churchinford STW | Due 2026-27 | Upper River Otter |
| 08SW104835 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) FENITON STW | Due 2026-27 | Lower River Otter |
| 08SW104834 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Fluxton STW | Due 2026-27 | Lower River Otter |
| 08SW104833 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Fluxton STW | Due 2026-27 | Lower River Otter |
| 08SW104781 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) HONITON STW | Due 2026-27 | Middle River Otter |
| 08SW104782 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) HONITON STW | Due 2026-27 | Middle River Otter |
| 08SW104682 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) PAYHEMBURY STW | Due 2026-27 | Tale |
| 08SW104683 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) PAYHEMBURY STW | Due 2026-27 | Tale |
| 08SW104584 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) TALATON STW | Due 2026-27 | Tale |
| 08SW104583 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) TALATON STW | Due 2026-27 | Tale |
| 08SW101302 · a | EnvAct_IMP4 | Improvement | Reduction of spills to meet EnvAct_IMP drivers FORTESCUE_CSO_SIDMOUTH | Due 2027-28 | FORTESCUE_CSO_SIDMOUTH |
| 08SW101305 · a | EnvAct_IMP4 | Improvement | Reduction of spills to meet EnvAct_IMP drivers MANSTONE LN_CSO_SIDMOUTH | Due 2027-28 | MANSTONE LN_CSO_SIDMOUTH |
| 08SW100004 · a | WFDGW_IMP | Improvement | Proactively reduce Otter Valley abstraction by 4 ML/d as an initial step to address future deficits under future Environmental Destination scenarios. Note this is dependent on SWW investment decision making around a supply side option to accomodate Otter valley abstraction change | Due 2029-30 | Lower River Otter |
| 08SW102100 · m | U_IMP1 | Improvement | Increased monitoring FLUXTON_STW_OTTERY ST MARY | Due 2030-31 | Lower River Otter |
| 08SW102148 · b | U_IMP2 | Improvement | P removal installed in PR14 WFD.will require Monitoring only HONITON_STW_HONITON | Due 2030-31 | Lower River Otter |
| 08SW102113 · ae | U_IMP1 | Improvement | Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct UPOTTERY_STW_UPOTTERY | Due 2030-31 | Upper River Otter |
17 of 17 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.