What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100136a · 667a6ad2 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ Bow Street SPS | Complete 2025-26 | Bow Street Storm Overflow |
| DCWW100264a · d416d8ec | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANFAIR STW | Complete 2025-26 | Llanfarian WwTW Inlet Storm Overflow |
| DCWW100265a · f8e85eea | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANFARIAN WWTW LLANFARIAN CERED'N | Complete 2025-26 | Llanfarian WwTW Inlet Storm Overflow |
| DCWW100087a · c10dbf77 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANILAR SPS | Complete 2025-26 | Llanilar on Clos Henri Storm Overflow |
| DCWW100336a · cffe2dda | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PENTRE-LLYN SPS | Complete 2025-26 | Pentrellyn Storm Overflow |
| DCWW100377a · ff851eab | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ TALLEY WWTW LLANDEILO CARMS | Complete 2025-26 | Aberystwyth Tan-Y-Cae Storm Overflow |
| DCWW100380a · 692d44ba | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ Tan-Y-Cae SPS | Complete 2025-26 | Aberystwyth Tan-Y-Cae Storm Overflow |
| DCWW102125a · 4429dad9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CLARACH BAY HOLIDAY VILLAGE PS | Due 2026-27 | Clarach Bay Overflow |
| DCWW100634a · 486759a1 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANFARIAN (ABERYSTWYTH) | Due 2027-28 | Llanfarian WwTW Inlet Storm Overflow |
| DCWW102573a · e0039636 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Aberystwyth - Trefechan Bridge | Due 2029-30 | Trefechan Bridge Storm Overflow |
| DCWW101582a · 6cccad97 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BOW STREET SPS BOW STREET | Due 2029-30 | Bow Street Storm Overflow |
| DCWW101083a · fdeb3c58 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Cae Ceredic SPS, Parc Avenue, Aberystwyth, SY23 3GG | Due 2029-30 | Fifth Avenue Storm Overflow |
| DCWW101582a · 47486216 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Clarach STW CSO | Due 2029-30 | Clarach WwTW Storm Overflow |
| DCWW101582a · a0121baa | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Min-y-Ddol Southgate, Aberystwyth, Penparcau, Ceredigion | Due 2029-30 | Min-Y-Ddol Storm Overflow |
| DCWW100975a · 04510ee0 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANBADARN SPS | Due 2029-30 | Llanbadarn Fawr Storm Overflow |
| DCWW102377a · b42d5c2f | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANFARIAN (ABERYSTWYTH) STW | Due 2029-30 | Llanfarian WwTW Inlet Storm Overflow |
| DCWW100952a · 643c3c83 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANFARIAN WASTEWATER TREATMENT WORKS SPS | Due 2029-30 | Llanfarian WwTW Inlet Storm Overflow |
| DCWW101582a · eba3e5b6 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llanilar CSO at SPS | Due 2029-30 | Llanilar on Clos Henri Storm Overflow |
| DCWW100934a · 0fb3d609 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANILAR SPS NO 2 | Due 2029-30 | Llanilar on Clos Henri Storm Overflow |
| DCWW101582a · 290e517b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PENTRELLYN PS | Due 2029-30 | Pentrellyn Storm Overflow |
| DCWW100933a · 6397e21b | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PENTRELLYN SPS NO 1 | Due 2029-30 | Pentrellyn Storm Overflow |
| DCWW101046a · 0d4b867f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PUMPING STATION, CLARACH BAY HOLIDAY VILLAGE, CLARACH BAY, ABERYSTWYTH, DYFED | Due 2029-30 | Clarach Bay Overflow |
| DCWW100970a · ffb12d37 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ TAN Y CAE SPS ABERYSTWYTH | Due 2029-30 | Aberystwyth Tan-Y-Cae Storm Overflow |
23 of 23 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.