← All spills

Combe St Nicholas Off Pudleigh Lane Storm Tank

WXW00314
Overflow on the network feeding Combe St Nicholas STW · Storm overflow
Showing history for 2026 · records go back to 2024
Not spilling

The monitor is reporting and shows no discharge.

Last spill ended
28 Feb, 11:44
Counted spills, 2026
18
15 discharge events
Hours spilled, 2026
193
Is the feed working?
Working
Last checked 38 min ago · we poll SWW hourly
48h agonow
47/48 hourly readings received
Dry spills, 2026
0
None in 2026 · 0 since 2020
How a dry spill is decided →
Spilled before its STW, 2026
0
0 in 2026 · 0 since 2020
What this means →

Its permit

What the environmental permit sets for this overflow — and where the public record is silent, which is itself the finding.

Pass-forward flow
Not published
Spill frequency limit
None set
Monitoring tier
Not published
Assessment trigger
Not crossed (threshold 10/year)

What you can do about this one

OPEN NOW

Ask for the data

Under the Environmental Information Regulations, Combe St Nicholas Off Pudleigh Lane Storm Tank's telemetry, the works' flow-to-full-treatment setting, and any spill investigations are emissions information — they cannot be withheld on commercial-confidentiality grounds. A written request is the fastest lever.

BY 30 APR 2027

Get it into the next programme

Investigations that will shape the 2030–35 environment programme must complete by this date. Putting this overflow on the record now — to South West Water and the Environment Agency — is what gets it considered.

BY 1 NOV 2027

Put it in the drainage plan

South West Water's draft Drainage & Wastewater Management Plan goes to a twelve-week consultation. A named overflow with evidence behind it is far harder to leave out.

Put this on the national record

This is the fastest way to act on what you have seen. Our petition asks the Government to publish a fix-by date and yearly progress for every storm overflow. At 100,000 signatures it must be considered for debate in Parliament.

332of 10,000 for a Government response
Sign the petition ↗

The record since 2020

0 dry spills and 0 pre-STW spills since 2020. Pick a year to see its events below.

Count by

2026: 18 spills · 15 discharge events

Counted spills — the EA's 12/24-hour block method, the basis of the 10-a-year cap. Published annual return where available, computed the same way for the current year. Two ways to count →

Dry spills, every year

0 dry spills since 2020 · showing up to 12

No dry spills on record for this overflow since 2020.

Spilled before its works

0 events since 2020 · started while Combe St Nicholas STW stayed shut

This overflow has never been recorded spilling ahead of its treatment works.

Spills by month — 2026 to date

Dry Wet weather
10Jan
5Feb