Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

15
Measures in this catchment
WINEP, current record
15
Still active
not yet past their date
0
Assumed complete
completion date has passed
4
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104689 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Par STW
Due 2026-27Par River (Lower)
08SW104688 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Par STW
Due 2026-27Par River (Lower)
08SW104624 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
St Austell Menagwins
Due 2026-27St Austell River
08SW104623 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
St Austell Menagwins
Due 2026-27St Austell River
08SW104621 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
St Austell North STW
Due 2026-27Par River (Upper)
08SW104622 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
St Austell North STW
Due 2026-27Par River (Upper)
08SW104999 · bzEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
LONDON APPRENTICE SPST_PSCSOEO_ST AUSTEL
Due 2027-28LONDON APPRENTICE SPST_PSCSOEO_ST AUSTEL
08SW104285 · aEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
MENAGWINS STW_SSO_ST AUSTELL
Due 2027-28MENAGWINS STW_SSO_ST AUSTELL
08SW104999 · cmEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
MOLINNIS_CSO_BUGLE
Due 2027-28MOLINNIS_CSO_BUGLE
08SW104999 · crEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
NANSLADRON SPST_PSCSOEO_ST AUSTELL
Due 2027-28NANSLADRON SPST_PSCSOEO_ST AUSTELL
08SW104999 · dfEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
POLGOOTH_CSO_ST AUSTELL
Due 2027-28POLGOOTH_CSO_ST AUSTELL
08SW100520 · cSW_IMPImprovement
10 Spills 50m3
LUXULYAN STW_SSO_ST AUSTELL
Due 2029-30LUXULYAN STW_SSO_ST AUSTELL
08SW101054 · aWFD_IMPgImprovement
New or tightened P consent
LUXULYAN_STW_ST_AUSTELL
Due 2029-30Par River (Lower)
08SW100520 · dSW_IMPImprovement
10 Spills 50m3
MENAGWINS STW_SSO_ST AUSTELL
Due 2029-30MENAGWINS STW_SSO_ST AUSTELL
08SW101085 · aWFD_IMPmImprovement
New or tightened P consent
MENAGWINS_STW_ST AUSTELL
Due 2029-30St Austell River

15 of 15 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.