What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SO102407 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils Boldre WTW | Due 2026-27 | BOLDRE |
| 08SO102695 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BOLDRE WWTW | Due 2026-27 | Lymington River |
| 08SO102408 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Brockenhurst WTW | Due 2026-27 | Lymington River |
| 08SO102700 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BROCKENHURST WWTW | Due 2026-27 | Lymington River |
| 08SO102414 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring East Boldre WTW | Due 2026-27 | EAST BOLDRE |
| 08SO102731 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor EAST BOLDRE WWTW | Due 2026-27 | Hatchet Stream |
| 08SO102487 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Flexford Lane Sway WTW | Due 2026-27 | Avon Water |
| 08SO102748 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor FLEXFORD LANE SWAY WWTW | Due 2026-27 | Avon Water |
| 08SO102434 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring Lyndhurst WTW | Due 2026-27 | LYNDHURST SSO - 115810 |
| 08SO102804 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor LYNDHURST WWTW | Due 2026-27 | Beaulieu |
| 08SO104950 · gs | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact BECTON LANE BARTON ON SEA CEO | Due 2027-28 | Becton Bunny |
| 08SO100043 · g | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact BROCKENHURST CSO | Due 2027-28 | LYMINGTON RIVER |
| 08SO104950 · pa | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact BROCKENHURST SSO | Due 2027-28 | Lymington River |
| 08SO104950 · x | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact FLEXFORD LANE SWAY SSO | Due 2027-28 | Avon Water |
| 08SO104950 · af | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact LYNDHURST SSO | Due 2027-28 | Beaulieu |
| 08SO102615 · a | WFD_INV_N-Tal | Investigation | Investigation to assess treatment options for nitrogen. Full-scale trial, Optimise MLE Milford Road Pennington WTW | Due 2027-28 | Avon Water |
| 08SO104003 · a | HD_IMP_NN | Improvement | Amend permit limit of Total N to 37.80 mg/l Brockenhurst WwTW | Due 2029-30 | Lymington River |
| 08SO102633 · a | SSSI_IMP | Improvement | N reduction East End WwTW | Due 2029-30 | Sowley Stream |
| 08SO103975 · a | HD_IMP_NN | Improvement | Amend permit limit of Total N to 10 mg/l FLEXFORD LANE SWAY | Due 2029-30 | Avon Water |
| 08SO103983 · a | HD_IMP_NN | Improvement | Amend permit limit of Total N to 10 mg/l LYNDHURST | Due 2029-30 | Beaulieu |
| 08SO100089 · a | EnvAct_IMP4 | Improvement | Wetland + Lining BROCKENHURST CSO | Due 2034-35 | LYMINGTON RIVER |
| 08SO103963 · a | EnvAct_IMP2 | Improvement | Wetland + Lining BROCKENHURST SSO | Due 2034-35 | Lymington River |
22 of 22 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.