Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

26
Measures in this catchment
WINEP, current record
25
Still active
not yet past their date
1
Assumed complete
completion date has passed
4
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08WW100254 · aWFD_NDNo deterioration
Improvements to WRC to achieve tightened sanitary permit.
Leyhill WRC - Permit Change
Complete 2025-26Tortworth Bk - source to conf R LIttle Avon
08WW100630 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Almondsbury WRC Flow Monitoring
Due 2026-27Chestle Pill
08WW100403 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Almondsbury WRC Overflow Monitoring
Due 2026-27Chestle Pill
08WW100631 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
Alveston WRC Flow Monitoring
Due 2026-27ALVESTON LOWER HAZEL INLET
08WW100404 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Alveston WRC Overflow Monitoring
Due 2026-27ALVESTON LOWER HAZEL INLET
08WW100659 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Charfield WRC Flow Monitoring
Due 2026-27Ozleworth Bk - source to conf Little Avon R
08WW100433 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Charfield WRC Overflow Monitoring
Due 2026-27Ozleworth Bk - source to conf Little Avon R
08WW100681 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
Cromhall WRC - Jubilee Lane SPS Flow Monitoring
Due 2026-27Tortworth Bk - source to conf R LIttle Avon
08WW100455 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Cromhall WRC - Jubilee Lane SPS Overflow Monitoring
Due 2026-27Tortworth Bk - source to conf R LIttle Avon
08WW100761 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
North Nibley WRC Flow Monitoring
Due 2026-27Doverte Brook
08WW100533 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
North Nibley WRC Overflow Monitoring
Due 2026-27Doverte Brook
08WW100779 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Redwick WRC Flow Monitoring
Due 2026-27Chestle Pill
08WW100552 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Redwick WRC Overflow Monitoring
Due 2026-27Chestle Pill
08WW100814 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Thornbury WRC Flow Monitoring
Due 2026-27Oldbury Naite Rhine
08WW100588 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Thornbury WRC Overflow Monitoring
Due 2026-27Oldbury Naite Rhine
08WW100816 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Tockington WRC Flow Monitoring
Due 2026-27Chestle Pill
08WW100590 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Tockington WRC Overflow Monitoring
Due 2026-27Chestle Pill
08WW100836 · aU_MON4Monitoring
Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b)
Wickwar WRC Flow Monitoring
Due 2026-27Little Avon R - source to conf Ozleworth Bk
08WW100610 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
Wickwar WRC Overflow Monitoring
Due 2026-27Little Avon R - source to conf Ozleworth Bk
08WW101000 · mhEnvAct_INV4Investigation
Storm overflows - Investigations
ALMONDSBURY WWTW
Due 2027-28Chestle Pill
08WW101000 · mwEnvAct_INV4Investigation
Storm overflows - Investigations
HACK MILL COMBINED SEWER OVERFLOW
Due 2027-28Ozleworth Bk - source to conf Little Avon R
08WW101000 · nbEnvAct_INV4Investigation
Storm overflows - Investigations
JUBILEE LANE PS
Due 2027-28Tortworth Bk - source to conf R LIttle Avon
08WW103060 · aWFD_IMPgImprovement
Improvements to WRC to achieve new phosphorus permit.
Almondsbury WRC – Phosphorus removal
Due 2029-30Chestle Pill
08WW103061 · aWFD_IMPgImprovement
Improvements to WRC to achieve new phosphorus permit.
Alveston WRC - Phosphorus removal
Due 2029-30ALVESTON LOWER HAZEL INLET
08WW102117 · aWFD_IMPgImprovement
Improvements to WRC to achieve new phosphorus permit.
Tockington WRC - Phosphorus Removal
Due 2029-30Chestle Pill
08WW102224 · aU_IMP1Improvement
Monitoring at Wickwar WRC - The site discharges to a non-sensitive area and is forecast to exceed 2,000pe by 2030, thus requiring monitoring under the UWWTR.
Wickwar WRC - UWWTR Monitoring
Due 2030-31Little Avon R - source to conf Ozleworth Bk

26 of 26 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.