What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08WW100254 · a | WFD_ND | No deterioration | Improvements to WRC to achieve tightened sanitary permit. Leyhill WRC - Permit Change | Complete 2025-26 | Tortworth Bk - source to conf R LIttle Avon |
| 08WW100630 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) Almondsbury WRC Flow Monitoring | Due 2026-27 | Chestle Pill |
| 08WW100403 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Almondsbury WRC Overflow Monitoring | Due 2026-27 | Chestle Pill |
| 08WW100631 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) Alveston WRC Flow Monitoring | Due 2026-27 | ALVESTON LOWER HAZEL INLET |
| 08WW100404 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Alveston WRC Overflow Monitoring | Due 2026-27 | ALVESTON LOWER HAZEL INLET |
| 08WW100659 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Charfield WRC Flow Monitoring | Due 2026-27 | Ozleworth Bk - source to conf Little Avon R |
| 08WW100433 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Charfield WRC Overflow Monitoring | Due 2026-27 | Ozleworth Bk - source to conf Little Avon R |
| 08WW100681 · a | U_MON4 | Monitoring | Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a) Cromhall WRC - Jubilee Lane SPS Flow Monitoring | Due 2026-27 | Tortworth Bk - source to conf R LIttle Avon |
| 08WW100455 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Cromhall WRC - Jubilee Lane SPS Overflow Monitoring | Due 2026-27 | Tortworth Bk - source to conf R LIttle Avon |
| 08WW100761 · a | U_MON4 | Monitoring | PR24 U_MON4 from U_INV2 investigation (U_MON4c) North Nibley WRC Flow Monitoring | Due 2026-27 | Doverte Brook |
| 08WW100533 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) North Nibley WRC Overflow Monitoring | Due 2026-27 | Doverte Brook |
| 08WW100779 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Redwick WRC Flow Monitoring | Due 2026-27 | Chestle Pill |
| 08WW100552 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Redwick WRC Overflow Monitoring | Due 2026-27 | Chestle Pill |
| 08WW100814 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Thornbury WRC Flow Monitoring | Due 2026-27 | Oldbury Naite Rhine |
| 08WW100588 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Thornbury WRC Overflow Monitoring | Due 2026-27 | Oldbury Naite Rhine |
| 08WW100816 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Tockington WRC Flow Monitoring | Due 2026-27 | Chestle Pill |
| 08WW100590 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Tockington WRC Overflow Monitoring | Due 2026-27 | Chestle Pill |
| 08WW100836 · a | U_MON4 | Monitoring | Move AMP7 U_INV2 driver output to 2-minute flow monitoring (U_MON4b) Wickwar WRC Flow Monitoring | Due 2026-27 | Little Avon R - source to conf Ozleworth Bk |
| 08WW100610 · a | U_MON3 | Monitoring | MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a) Wickwar WRC Overflow Monitoring | Due 2026-27 | Little Avon R - source to conf Ozleworth Bk |
| 08WW101000 · mh | EnvAct_INV4 | Investigation | Storm overflows - Investigations ALMONDSBURY WWTW | Due 2027-28 | Chestle Pill |
| 08WW101000 · mw | EnvAct_INV4 | Investigation | Storm overflows - Investigations HACK MILL COMBINED SEWER OVERFLOW | Due 2027-28 | Ozleworth Bk - source to conf Little Avon R |
| 08WW101000 · nb | EnvAct_INV4 | Investigation | Storm overflows - Investigations JUBILEE LANE PS | Due 2027-28 | Tortworth Bk - source to conf R LIttle Avon |
| 08WW103060 · a | WFD_IMPg | Improvement | Improvements to WRC to achieve new phosphorus permit. Almondsbury WRC – Phosphorus removal | Due 2029-30 | Chestle Pill |
| 08WW103061 · a | WFD_IMPg | Improvement | Improvements to WRC to achieve new phosphorus permit. Alveston WRC - Phosphorus removal | Due 2029-30 | ALVESTON LOWER HAZEL INLET |
| 08WW102117 · a | WFD_IMPg | Improvement | Improvements to WRC to achieve new phosphorus permit. Tockington WRC - Phosphorus Removal | Due 2029-30 | Chestle Pill |
| 08WW102224 · a | U_IMP1 | Improvement | Monitoring at Wickwar WRC - The site discharges to a non-sensitive area and is forecast to exceed 2,000pe by 2030, thus requiring monitoring under the UWWTR. Wickwar WRC - UWWTR Monitoring | Due 2030-31 | Little Avon R - source to conf Ozleworth Bk |
26 of 26 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.