What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| 08SO102553 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring BRIGHSTONE WTW | Due 2026-27 | BRIGHSTONE |
| 08SO102698 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor BRIGHSTONE WWTW | Due 2026-27 | Brighstone Streams |
| 08SO102554 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring CALBOURNE WTW | Due 2026-27 | CALBOURNE |
| 08SO102708 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor CALBOURNE WWTW | Due 2026-27 | Caul Bourne |
| 08SO102555 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils CHALE WTW | Due 2026-27 | CHALE |
| 08SO102712 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor CHALE WWTW | Due 2026-27 | Medina |
| 08SO102561 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring GODSHILL WTW | Due 2026-27 | GODSHILL |
| 08SO102759 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor GODSHILL WWTW | Due 2026-27 | Eastern Yar (Upper) |
| 08SO102814 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor MILL LANE SHALFLEET WPS | Due 2026-27 | Caul Bourne |
| 08SO102825 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor NEWBRIDGE ROAD NEWBRIDGE WPS | Due 2026-27 | Caul Bourne |
| 08SO102578 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring ROUD WTW | Due 2026-27 | ROUD |
| 08SO102861 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor ROUD WWTW | Due 2026-27 | Eastern Yar (Upper) |
| 08SO102584 · a | U_MON4 | Monitoring | U_MON4b - Move AMP7 U_INV2 driver output to 2-minute flow monitoring SHORWELL WTW | Due 2026-27 | SHORWELL |
| 08SO102872 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor SHORWELL WWTW | Due 2026-27 | Brighstone Streams |
| 08SO102586 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils ST HELENS WTW | Due 2026-27 | ST HELENS |
| 08SO102885 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor ST HELENS WWTW | Due 2026-27 | Eastern Yar (Lower) |
| 08SO102594 · a | U_MON4 | Monitoring | U_MON4c - PR24 U_MON4 from U_INV2 investigation including civils WROXALL WTW | Due 2026-27 | Wroxall Stream |
| 08SO102935 · a | U_MON3 | Monitoring | U_MON3a: MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor WROXALL WWTW | Due 2026-27 | Wroxall Stream |
| 08SO104802 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. BRIGHSTONE WTW | Due 2027-28 | BRIGHSTONE |
| 08SO100043 · h | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact BROOKSIDE DAIRY WROXALL CSO | Due 2027-28 | WROXALL STREAM |
| 08SO104950 · pz | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact CALBOURNE SSO | Due 2027-28 | Caul Bourne |
| 08SO104803 · a | WFD_INV | Investigation | Investigations for actions to improve water quality in terms of relevant WFD status objectives. CHILLERTON WTW | Due 2027-28 | Medina |
| 08SO104950 · nz | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the Shellfish Water and ensure no more than 10 spills per annum (on average) as an agglomeration MILL LANE SHALFLEET CEO | Due 2027-28 | Caul Bourne |
| 08SO100043 · bx | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact PARK ROAD RYDE CSO | Due 2027-28 | MONKTONMEAD BROOK |
| 08SO104950 · qr | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact PRICHETTS WAY ROOKLEY CEO | Due 2027-28 | Medina |
| 08SO104950 · pc | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact ROUD SSO | Due 2027-28 | Eastern Yar (Upper) |
| 08SO104950 · og | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the Shellfish Water and ensure no more than 10 spills per annum (on average) as an agglomeration SIMEON STREET RYDE CSO | Due 2027-28 | Monktonmead Brook |
| 08SO104950 · t | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact ST HELENS SSO | Due 2027-28 | Eastern Yar (Lower) |
| 08SO104950 · dr | EnvAct_INV4 | Investigation | Investigation to determine the target number of spills from the storm overflow to protect the environment and demonstrate no local adverse ecological impact WROXALL CEO | Due 2027-28 | WROXALL STREAM |
| 08SO100091 · a | EnvAct_IMP2 | Improvement | Screen Only (IMP5) BROOKSIDE DAIRY WROXALL CSO | Due 2029-30 | WROXALL STREAM |
| 08SO103938 · a | EnvAct_IMP2 | Improvement | Wetland + Lining CALBOURNE SSO | Due 2029-30 | Caul Bourne |
| 08SO104001 · a | HD_IMP_NN | Improvement | Amend permit limit of Total N to 10 mg/l WROXALL | Due 2029-30 | Wroxall Stream |
| 08SO100216 · a | EnvAct_IMP2 | Improvement | SuDS + Storage WROXALL CEO | Due 2029-30 | WROXALL STREAM |
| 08SO103235 · a | EnvAct_IMP2 | Improvement | SuDS and Storage are the preferred option, but costs based on storage only MILL LANE SHALFLEET CEO | Due 2034-35 | Caul Bourne |
| 08SO103260 · a | EnvAct_IMP2 | Improvement | SuDS + Storage SIMEON STREET RYDE CSO | Due 2034-35 | Monktonmead Brook |
| 08SO103962 · a | EnvAct_IMP2 | Improvement | Wetland + Lining ST HELENS SSO | Due 2034-35 | Eastern Yar (Lower) |
36 of 36 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.