← Burry Port Ashburnham Road Storm Overflow
Spill evidence · River Hub
Burry Port Ashburnham Road Storm Overflow
Combined sewer overflow · DCWW1033 · feeds PEMBREY WASTEWATER TREATMENT WORKS STW
Wet weather
The discharge
- Spill day
- Tuesday, 27 January 2026
- Started
- 27 Jan 2026, 07:30
- Ended
- 27 Jan 2026, 08:00
- Duration
- 30 minutes
- Receiving water
- —
- Community
- Pembrey and Burry Port Town
Rainfall evidence
Daily rainfall at the matched gauge (Felinfoel Raingauge) for the spill day and the days before. A spill is dry when every day in the window is ≤ 0.25 mm.
1-day window: Wet weather3-day window: Wet weather4-day window: Wet weather
| Date | Rainfall | |
|---|---|---|
| 27/01/2026 (spill day) | 15.4 mm | rain |
| 26/01/2026 | 12.2 mm | rain |
| 25/01/2026 | 2.4 mm | rain |
| 24/01/2026 | 12.8 mm | rain |
| 23/01/2026 | 3.2 mm | rain |
River flow that day: 70.629 m³/s.
Gauge proximity
Outlet (red) vs matched rain gauge (blue), 8.4 km apart. Closer means the rainfall reading is more representative of the overflow.
Loading map…
Severity & context
- Bathing water
- Not a bathing-water overflow
- Shellfish water
- Not a shellfish-water overflow
- Ahead of the works
- Yes — the treatment works' own overflow stayed shut that day, so capacity was available. Avoidable.
Method & provenance. Dry/wet classification is decided by rainfall at the nearest NRW gauge — ≤ 0.25 mm on the spill day and each preceding day of the window (how we classify). Spill data: Dŵr Cymru Welsh Water live storm overflow feed, read hourly by River Hub (outlet DCWW1033). Rainfall: NRW telemetry gauge H059499326. A dry spill is precautionary evidence of a likely fault, not proof of an offence — we test the rainfall, not the works' flow. Generated by Gwendraeth Fach a Fawr / Gwendraeth Fach and Fawr Data.