What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100110a · 4d273138 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ABERDARON WASTEWATER TREATMENT WKS | Complete 2025-26 | Aberdaron Storm Overflow |
| DCWW100065a · d2c7f4f4 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ ABERERCH WWTW | Complete 2025-26 | Abererch WwTW Storm Overflow |
| DCWW100115a · a66735d5 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ AFONWEN | Complete 2025-26 | Afonwen WwTW Storm Overflow |
| DCWW100066a · 489d3364 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BEDDGELERT WASTE WATER TREATMENT | Complete 2025-26 | Beddgelert WwTW Storm Overflow |
| DCWW100129a · a4d84418 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BLAENAU FFESTINIOG WWTW | Complete 2025-26 | Blaenau Ffestiniog WwTW Point 1 Storm Overflow |
| DCWW100162a · 2b173649 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CHWILOG STW | Complete 2025-26 | Chwilog WwTW Storm Overflow |
| DCWW100177a · 5e496a6d | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ CRICCIETH STW FINAL | Complete 2025-26 | West Parade Criccieth Overflow |
| DCWW100211a · f1f3d054 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ Fourcrosses STW | Complete 2025-26 | Four Crosses WwTW Storm Overflow |
| DCWW100214a · 978877bd | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ GARNDOLBENMAEN STW | Complete 2025-26 | Garndolbenmaen WwTW Storm Overflow |
| DCWW100216a · df49bf26 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ GELLILYDAN STW | Complete 2025-26 | Gellilydan WwTW Settled Storm Overflow |
| DCWW100226a · 22969098 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ HARLECH MAIN SPS | Complete 2025-26 | Harlech Storm Overflow |
| DCWW100259a · cba0ee5d | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANERCH-Y-MOR | Complete 2025-26 | Stryd Y Felin Storm Overflow |
| DCWW100081a · 7013cc61 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANFFESTINIOG STW | Complete 2025-26 | Llan Ffestiniog WwTW Inlet Storm Overflow |
| DCWW100295a · a91f0fff | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANYSTUMDWY A WWTW | Complete 2025-26 | Llanystumdwy WwTW Storm Overflow |
| DCWW100101a · a9663ecf | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLITHFAEN STW | Complete 2025-26 | Llithfaen WwTW Storm Overflow |
| DCWW100314a · 1f90e601 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ MYNYTHO STW - STORM OVERFLOW | Complete 2025-26 | Mynytho WwTW Storm Overflow |
| DCWW100090a · 7433756b | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ NEFYN WWTW | Complete 2025-26 | Nefyn WwTW Inlet PS (Discharge Point A) Storm Overflow |
| DCWW100091a · 14cc11ca | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PENRHOS CAMP STW - SCREENED ST | Complete 2025-26 | Penrhos Camp WwTW Storm Overflow |
| DCWW100333a · 10395080 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PENRHYNDEUDRAETH WWTW FE | Complete 2025-26 | Penrhyndeudraeth WwTW Settled Storm Overflow |
| DCWW100349a · 72d6affa | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PORTHMADOG WWTW | Complete 2025-26 | Porthmadog WwTW Tank Overflow |
| DCWW100352a · 1474235a | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ PWLLHELI STW GIMBLET ROCK SITE | Complete 2025-26 | Gimblet Rock Storm Overflow |
| DCWW100099a · 923df04f | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ TRAWSFYNYDD STW | Complete 2025-26 | Maes Gwyndy Trawsfynydd Storm Overflow |
| DCWW100201a · 17015967 | W_U_MON4 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows WQ EFAILNEWYDD | Due 2026-27 | Efailnewydd WwTW Storm Overflow |
| DCWW102224a · 394ae6ff | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Maentwrog SWK SSO | Due 2026-27 | Maentwrog WwTW Storm Overflow |
| DCWW102219a · ef68e90a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PORTHMADOG BORTH-Y-GEST PS | Due 2026-27 | Amanda Terrace Storm Overflow |
| DCWW101647a · b45fc64e | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper WQ Efailnewydd STW (7CDC1096) | Due 2027-28 | Water body only |
| DCWW101651a · 122093f7 | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper WQ SARN MEILLTEYRN STW (7CDC0937) | Due 2027-28 | Water body only |
| DCWW101652a · 4108d498 | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper WQ SARN STW (7CDC0938) | Due 2027-28 | Water body only |
| DCWW100627a · 64d34d34 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ BEDDGELERT | Due 2027-28 | Beddgelert WwTW Storm Overflow |
| DCWW100629a · 790d3756 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ BLAENAU FFESTINIOG | Due 2027-28 | Blaenau Ffestiniog WwTW Point 1 Storm Overflow |
| DCWW100688a · 69bcf7be | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANYSTUMDWY (W PORTHMADOG) A | Due 2027-28 | Llanystumdwy WwTW Storm Overflow |
| DCWW100651a · ad6efe52 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANYSTUMDWY (W PORTHMADOG) A | Due 2027-28 | Llanystumdwy WwTW Storm Overflow |
| DCWW102241a · 40499670 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ ABERDARON WORKS STW CSO | Due 2029-30 | Aberdaron WwTW Storm Overflow |
| DCWW100626a · f27c9909 | W_U_IMP5 | Improvement | Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW WQ ABERERCH | Due 2029-30 | Abererch WwTW Storm Overflow |
| DCWW101200a · 2560a0ca | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ ABERSOCH HARBOUR PUMPING STATION | Due 2029-30 | Abersoch Harbour Storm Overflow |
| DCWW101346a · 7246db1e | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ AFONWEN WASTEWATER TREATMENT WORKS PUMPING STATION | Due 2029-30 | Afonwen WwTW Storm Overflow |
| DCWW101582a · 7ea92600 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ AFONWEN WWTW PS | Due 2029-30 | Afonwen WwTW Storm Overflow |
| DCWW101582a · 4dba1b82 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ AMMANDA TERRACE BORTH Y GEST PORTHM | Due 2029-30 | Amanda Terrace Storm Overflow |
| DCWW101582a · f8bf79e5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BAKERS LANE/CHANDLERS PLACE PORTH | Due 2029-30 | Chandlers Place Porthmadog Storm Overflow |
| DCWW101830b · 31ce3a22 | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ BEDDGELERT WWTW | Due 2029-30 | Water body only |
| DCWW101830a · 137c02ba | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ BEDDGELERT WWTW | Due 2029-30 | Water body only |
| DCWW102821a · 33af64d7 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BLAENAU FFESTINIOG A | Due 2029-30 | Blaenau Ffestiniog WwTW Point 2 Storm Overflow |
| DCWW101582a · a614a240 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Blaenau Ffestiniog CSO No 3 | Due 2029-30 | The Square Blaenau Ffestiniog Storm Overflow |
| DCWW101232a · 2ec35ce1 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BLAENAU FFESTINIOG NO2 | Due 2029-30 | Llwyn Y Gell Road Ffestiniog Storm Overflow |
| DCWW101582a · 50295403 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BRIDGE GARAGE PWLLHELI | Due 2029-30 | Abererch Road Crossing Storm Overflow |
| DCWW101582a · 68c1d191 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BRITANNIA PS | Due 2029-30 | Porthmadog Britannia Place Storm Overflow |
| DCWW101582a · d6050a91 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BRYNCOCH SEWAGE PUMPING STATION | Due 2029-30 | Nefyn WwTW Inlet PS (Discharge Point A) Storm Overflow |
| DCWW101582a · 10ef59e5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CHAPEL STREET/MADOG STREET PORTHM | Due 2029-30 | Chapel Street Porthmadog Storm Overflow |
| DCWW101253a · 290860a9 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CLYNNOG FAWR PUMPING STATION | Due 2029-30 | Clynnog Fawr Storm Overflow |
| DCWW102807a · 804a6a3a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Criccieth - Hen Felin Newydd CSO | Due 2029-30 | Beach Bank Criccieth Storm Overflow |
| DCWW101582a · 4280a247 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CRICCIETH EAST PS | Due 2029-30 | Esplanade Criccieth Storm Overflow |
| DCWW101274a · 177674c7 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CRICCIETH EAST PUMPING STATION | Due 2029-30 | Esplanade Criccieth Storm Overflow |
| DCWW101582a · 6eeb1277 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Criccieth STW CSO to Settled Storm Sewage Tanks | Due 2029-30 | West Parade Criccieth Overflow |
| DCWW101582a · 0887985d | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CRICCIETH WEST PS | Due 2029-30 | West Parade Criccieth Overflow |
| DCWW101275a · 37c08df5 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CRICCIETH WEST PUMPING STATION | Due 2029-30 | West Parade Criccieth Overflow |
| DCWW101831a · a5f8a10c | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ CROESOR SEWAGE TREATMENT WORKS | Due 2029-30 | Water body only |
| DCWW101481a · 47f7fb8e | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ CSO & EO at Aberdaron PS | Due 2029-30 | Aberdaron Storm Overflow |
| DCWW101582a · df34e7a2 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO and EO at Llanystumdwy Pumping Station | Due 2029-30 | Llanystumdwy WwTW Storm Overflow |
| DCWW101582a · 3e1545d2 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Beddgelert East Bank Afon Glaslyn | Due 2029-30 | East Bank Afon Glaslyn Beddgelert Storm Overflow |
| DCWW101582a · 44f02e0c | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Land Off A496 Manod Blaenau Ffesti | Due 2029-30 | Congl Y Wal Blaenau Ffestiniog Storm Overflow Storm Overflow |
| DCWW101582a · 1c9cd7f0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Talsarnau SPS | Due 2029-30 | Talsarnau WwTW Storm Overflow |
| DCWW101582a · 9f537dc0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Trawsfynydd WwTW | Due 2029-30 | Trawsfynydd WwTW Storm Overflow |
| DCWW101582a · 947c95d5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO Rear Of Prysor Filling Station Traw | Due 2029-30 | A470 A4212 Junction Storm Overflow |
| DCWW102490a · aa941657 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Edern SPS CSO | Due 2029-30 | Lôn Goch Edern Storm Overflow |
| DCWW101330a · aa642f54 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ EDERN SPS CSO, EDERN, LLEYN PENINSULA | Due 2029-30 | Lôn Goch Edern Storm Overflow |
| DCWW102236a · decad341 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ EFILNEWYDD STW CSO | Due 2029-30 | Efailnewydd WwTW Storm Overflow |
| DCWW101987a · c26bcb99 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ Ffestiniog STW | Due 2029-30 | Llan Ffestiniog WwTW Inlet Storm Overflow |
| DCWW101582a · bee16653 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ FRIOG SEWAGE PUMPING STATION | Due 2029-30 | Nefyn WwTW Inlet PS (Discharge Point A) Storm Overflow |
| DCWW101582a · 623efb2a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ GIMBLET ROCK TIDAL TANK CSO | Due 2029-30 | Gimblet Rock Storm Overflow |
| DCWW101186a · 34da3ac5 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ GIMBLET ROCK TIDAL TANK PWLLHELI | Due 2029-30 | Gimblet Rock Storm Overflow |
| DCWW101582a · b9521787 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ GLAN Y DON PS PWLLHELI | Due 2029-30 | Glan-Y-Don Pwllheli Storm Overflow |
| DCWW101201a · c22df1eb | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ GLAN-Y-DON SEWAGE PUMPING STATION | Due 2029-30 | Glan-Y-Don Pwllheli Storm Overflow |
| DCWW102814a · 0b322ba5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ HARLECH FFORDD PENLLACH O/S LAUNDRY | Due 2029-30 | Ffordd Penllach Storm Overflow |
| DCWW101582a · ba91c0a4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Harlech Rum Hole CSO | Due 2029-30 | Harlech Storm Overflow |
| DCWW101336a · 9ff1f4e2 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ HARLECH TERMINAL PUMPING STATION - OUTFALL A | Due 2029-30 | Harlech Storm Overflow |
| DCWW101290a · 99a4b33f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ HARLECH TERMINAL PUMPING STATION - OUTFALL B | Due 2029-30 | Bron Castell Storm Overflow |
| DCWW101172a · e5d369cb | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANBEDROG SEWAGE PUMPING STATION | Due 2029-30 | Llanbedrog Long Nant-Iago Storm Overflow |
| DCWW101582a · a8f0a373 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llanbedrog SPS | Due 2029-30 | Llanbedrog Long Nant-Iago Storm Overflow |
| DCWW101582a · 92eab887 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ LLANERCH CSO | Due 2029-30 | Stryd Y Felin Storm Overflow |
| DCWW101832b · 4ad82dc3 | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ LLANFROTHEN STW | Due 2029-30 | Water body only |
| DCWW101832a · fb040dcd | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ LLANFROTHEN STW | Due 2029-30 | Water body only |
| DCWW101582a · 23825aec | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llanystumdwy (W Porthmadog) A (Settled Storm) | Due 2029-30 | Llanystumdwy WwTW Storm Overflow |
| DCWW101324a · 6ec02528 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ Llanystumdwy Pumping Station | Due 2029-30 | Llanystumdwy WwTW Storm Overflow |
| DCWW101582a · 655f04c1 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ MAENTWROG CSO | Due 2029-30 | Maentwrog Storm Overflow |
| DCWW102003a · 9ecda952 | W_U_O_IMP1 | Improvement | Action to implement improvements to overflows classified as Unsatisfactory WQ MAES GWYNDY CSO | Due 2029-30 | Maes Gwyndy Trawsfynydd Storm Overflow |
| DCWW102822a · a403b60a | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Morfa Bychan STW EO | Due 2029-30 | Morfa Bychan WwTW Storm Overflow |
| DCWW102614a · a78eaf1b | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Morfa Bychan WwTW Storm Overflow | Due 2029-30 | Morfa Bychan WwTW Storm Overflow |
| DCWW101582a · 23ec1bab | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ MORFA GARREG PS PWLLHELI | Due 2029-30 | Morfa'r Garreg Storm Overflow |
| DCWW101202a · adeb3da5 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MORFA GARREG SPS, PWLLHELI | Due 2029-30 | Morfa'r Garreg Storm Overflow |
| DCWW102491a · 551068bf | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Morfa Nefyn (New) STW CSO | Due 2029-30 | Nefyn WwTW Settled Storm Overflow |
| DCWW101582a · 3d1254ac | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes River MORFA NEFYN PUMPING STATION CSO (B) | Due 2029-30 | Water body only |
| DCWW101331a · 8d26f520 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MORFA NEFYN SPS CSO (A), NEFYN, LLEYN PENINSULA | Due 2029-30 | Lôn Goch Edern Storm Overflow |
| DCWW101332a · 7be31d44 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ MORFA NEFYN SPS CSO (B), NEFYN, LLEYN PENINSULA | Due 2029-30 | Nefyn WwTW Inlet PS (Discharge Point A) Storm Overflow |
| DCWW101582a · 656f42ec | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEFYN PUMPING STATION | Due 2029-30 | Nefyn Storm Overflow |
| DCWW101173a · 67c86e1f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ NEFYN SPS CSO, NEFYN | Due 2029-30 | Nefyn Storm Overflow |
| DCWW101582a · 069767da | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ NEFYN WWTW | Due 2029-30 | Nefyn WwTW Inlet PS (Discharge Point A) Storm Overflow |
| DCWW102468a · a199f6b0 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Parry's Terrace CSO Blaenau Ffestiniog | Due 2029-30 | Llwyn Y Gell Road Ffestiniog Storm Overflow |
| DCWW101582a · fda908a4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Penrhyndeudraeth Wastewater Treatment Works Storm Overflow | Due 2029-30 | Penrhyndeudraeth WwTW Settled Storm Overflow |
| DCWW102598a · cb2112c9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PORTHMADOG LOMBARD STREET/BANK PLACE | Due 2029-30 | Lombard Street Bank Place Porthmadog Storm Overflow |
| DCWW101307a · c2d55a36 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PORTHMADOG SEWAGE TREATMENT WORKS STORM STORAGE TANKS | Due 2029-30 | Porthmadog WwTW Tank Overflow |
| DCWW101306a · f0fc5876 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ PORTHMADOG SEWAGE TREATMENT WORKS, ON SITE SEWAGE PUMPING STATION | Due 2029-30 | Porthmadog WwTW Tank Overflow |
| DCWW102816a · 9bd81092 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ PORTHMADOG SWK EOF | Due 2029-30 | Porthmadog WwTW Tank Overflow |
| DCWW102791a · 77cce5d8 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Porthmadog WwTW Final Effluent PS EOF | Due 2029-30 | Porthmadog WwTW Tank Overflow |
| DCWW102487a · 9565f140 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Porthmadog WwTW Storm Tank | Due 2029-30 | Porthmadog WwTW Tank Overflow |
| DCWW101833a · cd299323 | W_HR_P_ND_IMP1 | Improvement | Implementation of actions to prevent deterioration to achieve the 5mg/l “back stop” limit in a Special Area of Conservation (SAC) river catchment, where the waterbody meets the Phosphate standard but where there is evidence of a risk of failure. WQ Prenteg WwTW | Due 2029-30 | Water body only |
| DCWW101833b · e2794a2f | W_HR_AMM_T_IMP1 | Improvement | Ammonia reduction to meet numeric permit limit
Implementation of actions to meet Total Ammonia standards at required water company assets to address observed and/or predicted failure of Total Ammonia standards in Special Area of Conservation (SAC) river catchments. WQ Prenteg WwTW | Due 2029-30 | Water body only |
| DCWW100602a · 23f4a1c9 | W_U_IMP7(a-e) | Improvement | Upgrade septic tank primary treated effluent to secondary treated effluent capable of delivering 40/60 BOD/SS Biological Oxygen Demand: Suspended Soilids WQ Rhyd-y-sarn, Gwynedd Septic Tank | Due 2029-30 | Water body only |
| DCWW101582a · 6df339a5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Settled Storm Overflow at Trefor Wastewater Treatment Works | Due 2029-30 | Trefor WwTW Relief Discharge Point Storm Overflow |
| DCWW101145a · 7c86e4d4 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ SNOWDON STREET SEWAGE PUMPING STATION | Due 2029-30 | Snowdon Street Storm Overflow |
| DCWW102483a · 009ac7f1 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ TRAWSFYNYDD NEAR BRON GWYNDY | Due 2029-30 | Fronwynion Street Trawsfynydd Storm Overflow |
| DCWW101582a · 1bfaaa64 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Trefor CSO | Due 2029-30 | Trefor Storm Overflow |
| DCWW101582a · 8ef15f86 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ TREMADOG SSO | Due 2029-30 | Tremadog Iscraig Storm Overflow |
| DCWW101582a · e6de3dd9 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Y Maes CSO | Due 2029-30 | Y Maes Pwllheli Storm Overflow |
113 of 113 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.