River Hub
Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

24
Measures in this catchment
NEP, current record
20
Still active
not yet past their date
4
Assumed complete
completion date has passed
4
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100121a · 66ba5a02W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BARMOUTH WWTW
Complete 2025-26Barmouth WwTW Short Sea Storm Overflow
DCWW100244a · 553683b5W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANBEDR WWTW
Complete 2025-26Llanbedr WwTW Storm Overflow
DCWW100299a · 683a4882W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLWYNGWRIL WWTW
Complete 2025-26Llwyngwril Storm Overflow
DCWW100403a · 7e2dd2b5W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TYWYN STW MORFA GWYLLT TYWYN
Complete 2025-26Tywyn WwTW Settled Storm Overflow
DCWW102217a · 95634da4W_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Barmouth WwTW Storm Discharge
Due 2026-27Barmouth WwTW Short Sea Storm Overflow
DCWW101616a · e3bad282W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
Dyffryn Ardudwy STW
Due 2027-28Water body only
DCWW101582a · c02109bfW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Abergynolwyn SPS
Due 2029-30Llanegryn Street Storm Overflow
DCWW101338a · c7bcf68fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BARMOUTH WASTEWATER TREATMENT WORKS (LONG SEA OUTFALL)
Due 2029-30Barmouth WwTW Short Sea Storm Overflow
DCWW101168a · 0127d0c5W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BARMOUTH WASTEWATER TREATMENT WORKS (MLWS OUTFALL)
Due 2029-30Barmouth WwTW Short Sea Storm Overflow
DCWW101347a · c6943f91W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BARMOUTH WASTEWATER TREATMENT WORKS (VIA THE HEOL IDRIS VALVE)
Due 2029-30Barmouth WwTW Short Sea Storm Overflow
DCWW102613a · 9167f6b2W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BARMOUTH WwTW O/F via Long Sea Outfall
Due 2029-30Barmouth WwTW Short Sea Storm Overflow
DCWW101265a · 0e2caef8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BRYNCRUG SEWAGE PUMPING STATION
Due 2029-30Bryncrug Overflow
DCWW101582a · 306090a4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO at Llandanwg SPS
Due 2029-30Llandanwg Station Storm Overflow
DCWW100666a · bd634c7bW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
DYFFRYN ARDUDWY
Due 2029-30Dyffryn Ardudwy WwTW Storm Overflow
DCWW100479a · 0bebca0cW_EEL_IMP1Improvement
Implementation of actions to improve abstractions and outfalls to prevent the entrainment of eels and to address barriers to passage of eels
WR
Fathew
Due 2029-30Water body only
DCWW101582a · 6e0dbec7W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Idris Villas Sewage Pumping Station
Due 2029-30Idris Villas to NRA Storm Overflow
DCWW100672a · 882a7e2dW_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANBEDR (GWYNEDD)
Due 2029-30Llanbedr WwTW Storm Overflow
DCWW101582a · 815406f5W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llanbedr CSO
Due 2029-30A496 Llanbedr Storm Overflow
DCWW101334a · 9ffc2012W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANBEDR TERMINAL PUMPING STATION (EMERGENCY)
Due 2029-30Llanbedr WwTW Storm Overflow
DCWW102612a · 4bad58ffW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llandanwg Station SPS O/F
Due 2029-30Llandanwg Station Storm Overflow
DCWW101335a · f999c553W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDANWG TERMINAL PUMPING STATION
Due 2029-30Llandanwg Station Storm Overflow
DCWW101582a · cbf06fe4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llwyngwril SPS
Due 2029-30Llwyngwril Storm Overflow
DCWW101352a · 045521dfW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLWYNGWRIL WWTW
Due 2029-30Llwyngwril Storm Overflow
DCWW101284a · 657b3afbW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TYWYN SEWAGE TREATMENT WORKS
Due 2029-30Tywyn WwTW Storm Overflow

24 of 24 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.