What the regulator requires
A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.
These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.
The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.
The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.
What the types mean
A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.
A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.
Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.
So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.
| Reference | Driver | Type | What it requires | Status | Attached to |
|---|---|---|---|---|---|
| DCWW100121a · 66ba5a02 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ BARMOUTH WWTW | Complete 2025-26 | Barmouth WwTW Short Sea Storm Overflow |
| DCWW100244a · 553683b5 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLANBEDR WWTW | Complete 2025-26 | Llanbedr WwTW Storm Overflow |
| DCWW100299a · 683a4882 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ LLWYNGWRIL WWTW | Complete 2025-26 | Llwyngwril Storm Overflow |
| DCWW100403a · 7e2dd2b5 | W_U_MON3 | Monitoring | MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows WQ TYWYN STW MORFA GWYLLT TYWYN | Complete 2025-26 | Tywyn WwTW Settled Storm Overflow |
| DCWW102217a · 95634da4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Barmouth WwTW Storm Discharge | Due 2026-27 | Barmouth WwTW Short Sea Storm Overflow |
| DCWW101616a · e3bad282 | W_WFD_PD_IMP | Improvement | Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. WQ Dyffryn Ardudwy STW | Due 2027-28 | Water body only |
| DCWW101582a · c02109bf | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Abergynolwyn SPS | Due 2029-30 | Llanegryn Street Storm Overflow |
| DCWW101338a · c7bcf68f | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BARMOUTH WASTEWATER TREATMENT WORKS (LONG SEA OUTFALL) | Due 2029-30 | Barmouth WwTW Short Sea Storm Overflow |
| DCWW101168a · 0127d0c5 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BARMOUTH WASTEWATER TREATMENT WORKS (MLWS OUTFALL) | Due 2029-30 | Barmouth WwTW Short Sea Storm Overflow |
| DCWW101347a · c6943f91 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BARMOUTH WASTEWATER TREATMENT WORKS (VIA THE HEOL IDRIS VALVE) | Due 2029-30 | Barmouth WwTW Short Sea Storm Overflow |
| DCWW102613a · 9167f6b2 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ BARMOUTH WwTW O/F via Long Sea Outfall | Due 2029-30 | Barmouth WwTW Short Sea Storm Overflow |
| DCWW101265a · 0e2caef8 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ BRYNCRUG SEWAGE PUMPING STATION | Due 2029-30 | Bryncrug Overflow |
| DCWW101582a · 306090a4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ CSO at Llandanwg SPS | Due 2029-30 | Llandanwg Station Storm Overflow |
| DCWW100666a · bd634c7b | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ DYFFRYN ARDUDWY | Due 2029-30 | Dyffryn Ardudwy WwTW Storm Overflow |
| DCWW100479a · 0bebca0c | W_EEL_IMP1 | Improvement | Implementation of actions to improve abstractions and outfalls to prevent the entrainment of eels and to address barriers to passage of eels WR Fathew | Due 2029-30 | Water body only |
| DCWW101582a · 6e0dbec7 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Idris Villas Sewage Pumping Station | Due 2029-30 | Idris Villas to NRA Storm Overflow |
| DCWW100672a · 882a7e2d | W_U_IMP6 | Improvement | Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW WQ LLANBEDR (GWYNEDD) | Due 2029-30 | Llanbedr WwTW Storm Overflow |
| DCWW101582a · 815406f5 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llanbedr CSO | Due 2029-30 | A496 Llanbedr Storm Overflow |
| DCWW101334a · 9ffc2012 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANBEDR TERMINAL PUMPING STATION (EMERGENCY) | Due 2029-30 | Llanbedr WwTW Storm Overflow |
| DCWW102612a · 4bad58ff | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llandanwg Station SPS O/F | Due 2029-30 | Llandanwg Station Storm Overflow |
| DCWW101335a · f999c553 | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLANDANWG TERMINAL PUMPING STATION | Due 2029-30 | Llandanwg Station Storm Overflow |
| DCWW101582a · cbf06fe4 | W_U_O_INV1 | Investigation | Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes WQ Llwyngwril SPS | Due 2029-30 | Llwyngwril Storm Overflow |
| DCWW101352a · 045521df | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ LLWYNGWRIL WWTW | Due 2029-30 | Llwyngwril Storm Overflow |
| DCWW101284a · 657b3afb | W_U_MON6 | Monitoring | MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations WQ TYWYN SEWAGE TREATMENT WORKS | Due 2029-30 | Tywyn WwTW Storm Overflow |
24 of 24 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.
There is no public change log
NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.
The 2027 pressure point
Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.