Why it keeps happening

Treatment works capacity

Every overflow goes to a sewage treatment works that serves a fixed area. There is no public data available to understand if the works has sufficient capacity to treat the sewage for the local population. We estimate this capacity based on the required capacity in the EA permit compared to the local population estimated to be on the sewage system. As we receive data on the actual processing capacity from South West Water we will add that too. South West Water has now given an initial response to our information requests, with figures for the flow to full treatment and the population served at several of the works, which we have built into the estimates here. We are still seeking the rest.

Capacity across the River Dart

Of the 7 works we could assess, none are estimated to be over their permitted flow. 5 more can’t be assessed yet: River Hub has no permit for them.

0
Over their permitted flow
of the 7 works we could assess
3
Have headroom but spill anyway
of the 7 assessed: points to another problem
5
Cannot be assessed yet
no permit loaded
0
People on an over-loaded works
among the works we could assess
Works
Load against permit
Overflow at works
Spare capacity
Broadhempston STW
374 people · 75 m³/day permitted
70%
Within capacity
1,039 h
0 upstream
~160
more people it could serve
Dittisham Main STW
299 people · 66 m³/day permitted
63%
Within capacity
205 h
2 upstream · 605 pre-STW
~170
more people it could serve
Strete STW
384 people · 122 m³/day permitted
44%
Within capacity
0 h
0 upstream
~490
more people it could serve
Totnes STW
10,832 people · 3,967 m³/day permitted
38%
Within capacity
593 h
12 upstream · 1,048 pre-STW
~17,500
more people it could serve
Ashprington STW
356 people · 181 m³/day permitted
28%
Within capacity
25 h
0 upstream
~940
more people it could serve
Harberton STW
259 people · 150 m³/day permitted
24%
Within capacity
1,829 h
0 upstream
~810
more people it could serve
Princetown STW
1,110 people · 1,023 m³/day permitted
15%
Within capacity
0 h
1 upstream · 35 pre-STW
~6,200
more people it could serve
Rattery STW
144 people · permit not found
Not known
Not assessed
1,712 h
0 upstream
Not known
Scorriton STW
48 people · permit not found
Not known
Not assessed
1,833 h
0 upstream
Not known
Widecombe STW
72 people · permit not found
Not known
Not assessed
19 h
1 upstream · 17 pre-STW
Not known
Buckfastleigh STW
7,015 people · permit not found
Not known
Not assessed
2,187 h
5 upstream · 260 pre-STW
Not known
Holne STW
129 people · permit not found
Not known
Not assessed
1,400 h
0 upstream
Not known

The black line marks 100% of permitted dry-weather flow; a dashed empty bar means no permit was found to measure against. Load is an estimate — population served × per-head water use, plus infiltration — not a permit-compliance finding. A works over 100% here is a signal to investigate, not a proven breach. Overflow hours are the works' own storm overflow in the last full year.

5 works with no permit loaded

River Hub doesn’t yet hold the permits for Rattery STW, Scorriton STW, Widecombe STW, Buckfastleigh STW, Holne STW, so it can’t check whether they are big enough for the people they serve. That’s a gap, not a clean bill of health, and it’s the quickest thing on this page to fix: discharge permits are public, and the Environment Agency must supply them on request. No request for them has been published on River Hub yet.

  1. Look a works up on the EA’s public register of discharge permits.
  2. Ask the Environment Agency for them through WhatDoTheyKnow: the request is written for you, and it and the reply are published there.
  3. Got a permit already? Send it to us and the works will be assessed.

Why this matters for reading spills

Works over capacity

If a works cannot treat the flow it receives, it spills to protect itself. The remedy is capital investment or a lower permitted load — years and millions, but it is the water company's to fix.

Headroom, but still spills

A works with spare capacity whose network still spills points to another problem — often something on that branch, like a blockage, a failed pump, or groundwater getting into the sewer. Frequently cheap to fix, and fixable now.

No permit found

Where we cannot find the permitted flow, the works cannot be assessed at all. That is a gap in the public record, and closing it is the first step to holding capacity to account.

How growth becomes spills

A developer has a section 106 right to connect to the public sewer, and the water company has a section 94 duty to accept the flow — but capacity is only funded on a five-yearly capital cycle. New connections can therefore arrive years before the works is enlarged to take them, and the overflow absorbs the gap. Schedule 3 to the Flood and Water Management Act 2010, which would make sustainable drainage mandatory and give a SuDS Approving Body a say, has been in force in Wales since 2018 but remains uncommenced in England — so here there is no such body.

What the permit actually sets

The permitted dry-weather flow is set by Formula A — roughly DWF + 1,360 × population + 2 × trade effluent (litres/day). The permit also sets a flow to full treatment, typically about three times DWF, below which everything must be treated rather than spilled. Our load figure compares estimated demand against that permitted DWF. 5 works here have no permitted flow loaded in River Hub yet, so their load can’t be calculated: they show as not assessed, never 0%.