Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The National Environment Programme is how Natural Resources Wales turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, NRW writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

79
Measures in this catchment
NEP, current record
67
Still active
not yet past their date
12
Assumed complete
completion date has passed
9
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
DCWW100124a · 9d330aecW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BETWS Y COED WWTW
Complete 2025-26Betws-Y-Coed WwTW Storm Overflow
DCWW100125a · aea6c4ffW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
BETWS YN RHOS STW
Complete 2025-26Betws Yn Rhos WwTW Storm Overflow
DCWW100150a · f53a26bfW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CAPEL CURIG SD.SCHEME
Complete 2025-26Capel Curig WwTW Storm Overflow
DCWW100187a · e961defeW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
CWM PENMACHNO STW
Complete 2025-26Cwm Penmachno Storm Overflow
DCWW100098a · ce5b11d0W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
DOLGARROG/TALYBONT STW
Complete 2025-26Talybont WwTW Storm Overflow
DCWW100075a · 1554dfeeW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
DOLWYDDELAN WWTW
Complete 2025-26Dolwyddelan WwTW Storm Overflow
DCWW100077a · 37d98003W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
EGLWYSBACH STW
Complete 2025-26Eglwysbach WwTW Storm Overflow
DCWW100213a · 44a6a986W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
GANOL WWTW (STW) GLAN CONWY CORNER
Complete 2025-26Ganol Disinfected Overflow
DCWW100082a · 7ee170ecW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLAN PENMACHNO STW
Complete 2025-26Llan Penmachno WwTW Storm Overflow
DCWW100288a · 39f9c593W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
LLANRWST STW LLLANWRST CONWY
Complete 2025-26Llanrwst WwTW Settled Storm Overflow
DCWW100102a · 46156c01W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
ROWEN STW
Complete 2025-26Rowen WwTW Storm Overflow
DCWW100402a · cfbff1e7W_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TYN Y GROES STORM OVERFLOW
Complete 2025-26Tyn-y-Groes WwTW Storm Overflow
DCWW102222a · 74ddf5eaW_U_O_INV1Investigation
Investigation to classify a storm overflow in ''high priority locations'' in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DEGANWY TYWYN
Due 2026-27Glan Y Mor Road Deganwy Tywyn Storm Overflow
DCWW101664a · 7715f3dcW_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration.
WQ
EGLWYSBACH
Due 2026-27Eglwysbach WwTW Storm Overflow
DCWW100389a · f133da6dW_U_MON3Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation monitoring at WwTW or last in line Sewage Pumping Station overflows
WQ
TRECASTLE SWK
Due 2026-27Tan-y-Fedw Trefriw Storm Overflow
DCWW100392a · 2067b9eeW_U_MON4Monitoring
MCERTS certified Flow Passed Forward (FPF) overflow operation at WwTW or last in line Sewage Pumping Station overflows
WQ
TREFOR NORTH-WEST
Due 2026-27Tan-y-Fedw Trefriw Storm Overflow
DCWW101655a · 290d2509W_WFD_PD_IMPImprovement
Improvements at Waste Water Treatment Works WWTW across permit parameters as per driver code under Water Framework Directive Regulations WFD to prevent deterioration. Those with CDC references are carried over from PR19/AMP7 under driver code W_WFD_PD_IMP and associated PR19 driver paper
WQ
BETWS YN RHOS (7CDC1089)
Due 2027-28Water body only
DCWW100628a · 24f1f924W_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
BETWS-Y-COED
Due 2027-28Betws-Y-Coed WwTW Storm Overflow
DCWW100650a · 1dd4c47bW_U_IMP5Improvement
Increasing Flow Passed Forward (FPF) flow at WwTW’s that were identified in PR19 as having low permitted FPF / DWF (Dry Weather Flow) ratios and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANRWST
Due 2027-28Llanrwst WwTW Settled Storm Overflow
DCWW100687a · 45a18e00W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
LLANRWST
Due 2027-28Llanrwst WwTW Settled Storm Overflow
DCWW101351a · b6a17899W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Betws yn Rhos SPS, Betws yn Rhos, Abergele, LL22 8AW
Due 2029-30Betws Yn Rhos WwTW Storm Overflow
DCWW102466a · cf3ec94cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BETWS-Y-COED MURIAU PS
Due 2029-30Betws-Y-Coed Muriau Storm Overflow
DCWW102463a · 47bf7fd6W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
BETWS-Y-COED WATERLOO HOTEL PS
Due 2029-30Waterloo Bridge Storm Overflow
DCWW101226a · 4745a52dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
BETWYS Y COED MURIAU P.S.
Due 2029-30Betws-Y-Coed Muriau Storm Overflow
DCWW101989a · 5cc18ac8W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Capel Curig WwTW
Due 2029-30Capel Curig WwTW Storm Overflow
DCWW101300a · df0aa860W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CHURCH ROAD SEWAGE PUMPING STATION
Due 2029-30Church Road Rhos-on-Sea Storm Overflow
DCWW101310a · d2dba9e4W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
CONWY ROAD SEWAGE PUMPING STATION
Due 2029-30Llandudno Conway Road Storm Overflow
DCWW101322a · 2e2b03f3W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Conwy Road SPS 77271 to rear of Mercedes dealer, Llandudno Junction LL31 9NZ
Due 2029-30Pendraw R Llan Glan Conwy Storm Overflow
DCWW101582a · 865f0e5fW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
CSO and EO at Glan Y Mor SPS
Due 2029-30Biwla Storm Overflow
DCWW101999a · d9bb3606W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Cwm Penmachno
Due 2029-30Cwm Penmachno Storm Overflow
DCWW100665a · e3ff40a6W_U_IMP6Improvement
Increasing storm tank capacity to provide adequate settlement and detention at WwTWs that were identified in PR19 and were subsequently deferred until PR24 with the written agreement of NRW
WQ
CWM PENMACHNO
Due 2029-30Cwm Penmachno Storm Overflow
DCWW101582a · 4ffb8e16W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DEGANWY BEACH SPS
Due 2029-30Near Marine Gardens Deganwy Storm Overflow
DCWW101227a · b1cc5448W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
DEGANWY BEACH SPS
Due 2029-30Near Marine Gardens Deganwy Storm Overflow
DCWW102603a · d1de7a80W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
DEGANWY DEGANWY ROAD
Due 2029-30Near Marine Gardens Deganwy Storm Overflow
DCWW101312a · 250e1d57W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
DEGANWY SEWAGE PUMPING STATION, MARINE CRESCENT, DEGANWY
Due 2029-30Marine Crescent Deganwy Storm Overflow
DCWW101248a · 8de9fa21W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
DOLGARROG TAN Y FFORDD PS
Due 2029-30Tan Y Ffordd Dolgarrog Storm Overflow
DCWW101318a · 6bf7eb9dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
DOLWYDDELAN WASTE WATER TREATMENT WORKS, DOLWYDDELAN, CONWY
Due 2029-30Dolwyddelan Storm Overflow
DCWW101308a · 3466408bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GANOL SEWAGE TREATMENT WORKS
Due 2029-30Ganol Disinfected Overflow
DCWW101180a · a5eaef52W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GLAN CONWY SEWAGE PUMPING STATION, GLAN CONWY
Due 2029-30Pendraw R Llan Glan Conwy Storm Overflow
DCWW101171a · 2e43dadfW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GLAN-Y-MOR SEWAGE PUMPING STATION
Due 2029-30Biwla Storm Overflow
DCWW102467a · 1645afbaW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
GLANWYDDEN CSO NEW
Due 2029-30Glanwydden Storm Overflow
DCWW101228a · 2eaf1581W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GLANWYDDEN SPS
Due 2029-30Glanwydden Storm Overflow
DCWW101159a · ea43c9aeW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
GYFFIN SEWAGE PUMPING STATION, MORFA BACH, LLANRWST ROAD, CONWY
Due 2029-30Conwy Gyffin Storm Overflow
DCWW101163a · 686884a9W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
INDUSTRIAL ESTATE GLAN MORFA, LLANDUDNO JUNCTION
Due 2029-30Tremarl Llandudno Junction Overfow
DCWW101996a · 4ce7afa8W_U_O_IMP1Improvement
Action to implement improvements to overflows classified as Unsatisfactory
WQ
Llan Penmachno WwTW
Due 2029-30Llan Penmachno WwTW Storm Overflow
DCWW101181a · 542d3aecW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDDULAS SEWAGE PUMPING STATION
Due 2029-30Llandulas Storm Overflow
DCWW101309a · b1615503W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDUDNO JUNCTION PUMPING STATION
Due 2029-30Llandudno Junction Glan-Y-Mor Road Storm Overflow
DCWW101224a · db9e08ebW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDUDNO LLANRHOS SPS
Due 2029-30Hill View Road Llanrhos Storm Overflow
DCWW101582a · 3a523f72W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANDUDNO LLANRHOS SPS
Due 2029-30Hill View Road Llanrhos Storm Overflow
DCWW101255a · 1c19803bW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
LLANDUDNO ROAD (PENRHYN BAY) PUMPING STATION
Due 2029-30Llandudno Road Penrhyn Bay Overflow
DCWW101582a · ab243502W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLANDULAS MILL ST CSO , ,
Due 2029-30Llandulas Storm Overflow
DCWW101321a · 7b1727a2W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
Llanrwst Sewage Pumping Station
Due 2029-30Llanrwst WwTW Settled Storm Overflow
DCWW101582a · 34498467W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Llanwrst CSO
Due 2029-30Llanrwst Storm Overflow
DCWW102712a · 01ccc5a1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLAWR PENTRE (Near Beach Road)
Due 2029-30Llawr Pentre Abergele Road Storm Overflow
DCWW101582a · de54f188W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
LLYSFAEN
Due 2029-30Abergele Road Storm Overflow
DCWW101207a · fe703425W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MILL ROAD SPS, BETWS Y COED
Due 2029-30Mill Road Betws-Y-Coed Storm Overflow
DCWW101183a · e5166663W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
MORFA SEWAGE PUMPING STATION, MORFA DRIVE, MORFA, CONWY
Due 2029-30Morfa Drive Conwy Storm Overflow
DCWW102489a · 54909f04W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
NR CSO 2250, DOLWYDDELAN
Due 2029-30Dolwyddelan Storm Overflow
DCWW101582a · 842b10a8W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Old Colwyn Beach Rd
Due 2029-30Min Y Don Woodland Storm Overflow
DCWW101182a · 84c1d13fW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PENRHYN BAY PUMPING STATION
Due 2029-30Penrhyn-Isaf Road Penrhyn Bay Storm Overflow
DCWW101582a · 0f5591a1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Pentrefoelas - CSO
Due 2029-30Pentrefoelas WwTW Storm Overflow
DCWW101160a · 44eec4a6W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
PUMPING STATION B, BY GOLF CLUB HOUSE, BETWS-Y-COED
Due 2029-30Betws-Y-Coed Storm Overflow
DCWW101256a · afa70af8W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
QUAY SEWAGE PUMPING STATION, CONWY QUAY, CONWY
Due 2029-30Lower Gate Street Conwy Storm Overflow
DCWW102526a · 17cdd317W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
r/o 92 Penrhyn-Isaf Rd CSO Penrhyn Bay
Due 2029-30Penrhyn-Isaf Road Penrhyn Bay Storm Overflow
DCWW101231a · 078e6012W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
RHYD Y FOEL
Due 2029-30Tan Y Foel Rhyd Y Foel Storm Overflow
DCWW101582a · 4632f443W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Rhyd Y Foel PS
Due 2029-30Tan Y Foel Rhyd Y Foel Storm Overflow
DCWW102240a · 218f73b9W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ROEWEN STW
Due 2029-30Rowen WwTW Storm Overflow
DCWW101480a · a7788b00W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
SPS at Trefriw STW , End of unnamed lane, Junction of B5106 and Gower Road, Trefriw
Due 2029-30Trefriw WwTW Storm Overflow
DCWW101304a · ae123c7cW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
SPS OFF LLANELIAN ROAD, COLWYN BAY
Due 2029-30Old Colwyn Llanelian Road Overflow
DCWW101582a · 81fef1b4W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
ST. AGNES ROAD CSO
Due 2029-30Mill Hill Storm Overflow
DCWW102461a · a6438bb1W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
TAL-Y-BONT (S OF CONWY) STW
Due 2029-30Talybont WwTW Storm Overflow
DCWW102599a · 91a1b360W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
TAN Y FFORDD SPS DOLGARROG SSO
Due 2029-30Tan Y Ffordd Dolgarrog Storm Overflow
DCWW101582a · 12b0905cW_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
Tan-y-Fedw CSO, Trefriw (MH No. 104)
Due 2029-30Tan-y-Fedw Trefriw Storm Overflow
DCWW102609a · 65445b68W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
TREFRIW COED GWYDYR NR PS NR NO 2
Due 2029-30Tan-y-Fedw Trefriw Storm Overflow
DCWW102462a · e5378dc2W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
TREFRIW MAIN
Due 2029-30Trefriw Main Storm Overflow
DCWW102597a · f11165a3W_U_O_INV1Investigation
Investigation to classify a storm overflow in accordance with NRW’s storm overflow classification guidance where assessment of the asset has not previously been captured by other programmes
WQ
TYN-Y-GROES STW STORM
Due 2029-30Tyn-y-Groes WwTW Storm Overflow
DCWW101311a · 144da723W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
TYWYN SEWAGE PUMPING STATION
Due 2029-30Glan Y Mor Road Deganwy Tywyn Storm Overflow
DCWW101161a · 0302aab2W_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
WATERLOO SPS, OPP WATERLOO HOTEL, A5, BETWS Y COED
Due 2029-30Waterloo Bridge Storm Overflow
DCWW101303a · 35c9851dW_U_MON6Monitoring
MCERTS certified monitoring (EDM event duration monitor) of emergency overflow operation on network pumping stations
WQ
WOODLANDS ESTATE P.S MARL LANE, DEGANWY
Due 2029-30Woodlands Llandudno Junction Overflow

79 of 79 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

NRW publishes the NEP as an open map layer, but there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.