Who is fixing it

What the regulator requires

A measure is a specific action the regulator requires the water company to take at a named site — to investigate a problem, keep monitoring it, or physically fix it — each with a completion date. These are the legally binding measures on record for this catchment: what each requires, and what to watch.

These measures are legally binding. Each one is a dated, site-specific requirement the company must deliver.

The Water Industry National Environment Programme is how the Environment Agency turns statutory duties into named obligations at named sites, with a completion date attached. Where a measure requires a physical upgrade, the Agency writes the result into the site's environmental permit — and from that point the requirement is criminally enforceable.

The measure itself is public. What is not published is the water company's action to comply with it — its delivery is reported to the regulator and scored, but the underlying work, and whether a measure has actually resolved the problem on the ground, is not on the public record. What to watch is slippage: a measure can be re-dated or re-scoped, and until the permit is varied the obligation has not changed.

What the types mean

Improvement

A physical upgrade — bigger storage, better treatment, more capacity. This is the only type that actually fixes the problem on the ground.

Investigation

A study of the cause. It produces a report, not a repair — an investigation must lead to an improvement before anything changes.

Monitoring

Installing or running instruments to measure the problem. Necessary evidence, but on its own it fixes nothing — it too has to be followed by an improvement.

So an overflow whose only measures are investigations or monitoring is being looked at, not yet fixed. On the gaps page, only a measure that is still active counts as action — a measure completed while the overflow is still failing does not.

30
Measures in this catchment
WINEP, current record
30
Still active
not yet past their date
0
Assumed complete
completion date has passed
11
Are physical improvements
the rest investigate or monitor
ReferenceDriverTypeWhat it requiresStatusAttached to
08SW104847 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
BLISLAND STW
Due 2026-27Lower River Camel
08SW104957 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
BODMIN (NANSTALLON) STW
Due 2026-27St Lawrence Stream
08SW104958 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
BODMIN (NANSTALLON) STW
Due 2026-27St Lawrence Stream
08SW104920 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
CAMELFORD STW
Due 2026-27Upper River Camel
08SW104919 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
CAMELFORD STW
Due 2026-27Upper River Camel
08SW104872 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
DELABOLE STW
Due 2026-27Allen
08SW104871 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
DELABOLE STW
Due 2026-27Allen
08SW104619 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
ST BREWARD STW
Due 2026-27Camel (De Lank to Stannon)
08SW104620 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
ST BREWARD STW
Due 2026-27Camel (De Lank to Stannon)
08SW104599 · aU_MON4Monitoring
Move AMP7 U_MON4 driver output to 2-minute flow monitoring (U_MON4a)
ST MABYN STW
Due 2026-27Allen
08SW104600 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
ST MABYN STW
Due 2026-27Allen
08SW104593 · aU_MON4Monitoring
PR24 U_MON4 from U_INV2 investigation (U_MON4c)
St Teath STW
Due 2026-27Allen
08SW104594 · aU_MON3Monitoring
MCERTS certification of an AMP7 U_MON3 driver output overflow operation monitor (U_MON3a)
St Teath STW
Due 2026-27Allen
08SW104999 · aeEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
CAMELFORD STW_SO_CAMELFORD
Due 2027-28CAMELFORD STW_SO_CAMELFORD
08SW104999 · gaEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
DELABOLE STW_SO_DELABOLE
Due 2027-28DELABOLE STW_SO_DELABOLE
08SW104999 · gdEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
DELABOLE STW_SSO_DELABOLE
Due 2027-28DELABOLE STW_SSO_DELABOLE
08SW100195 · aHD_INVInvestigation
Investigation to determine source apportionment and the impact of Helstone WwTW in the River Allen catchment.
HELSTONE STW
Due 2027-28Allen
08SW104999 · ebEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
ST BREWARD STW_SSO_ST BREWARD
Due 2027-28ST BREWARD STW_SSO_ST BREWARD
08SW104999 · egEnvAct_INV4Investigation
Investigation to meet EnvAct INV4 Driver
ST MABYN STW_SO_ST MABYN
Due 2027-28ST MABYN STW_SO_ST MABYN
08SW101500 · aHD_IMP_NNImprovement
New or tightened P consent
CAMELFORD_STW_CAMELFORD
Due 2027-28Upper River Camel
08SW101465 · aU_IMP4Improvement
Reduction of spills to meet EnvAct_IMP drivers
DELABOLE STW_SO_DELABOLE
Due 2027-28DELABOLE STW_SO_DELABOLE
08SW100094 · aU_IMP4Improvement
Reduction of spills to meet EnvAct_IMP drivers
DELABOLE STW_SSO_DELABOLE
Due 2027-28DELABOLE STW_SSO_DELABOLE
08SW101004 · aHD_IMP_NNImprovement
New or tightened P consent
NANSTALLON_STW_BODMIN
Due 2027-28Lower River Camel
08SW101503 · aHD_IMP_NNImprovement
New or tightened P consent
SCARLETTS WELL_STW_BODMIN
Due 2027-28Lower River Camel
08SW104296 · aU_IMP4Improvement
To comply with UWWTR
ST TEATH STW_SO_ST TEATH
Due 2027-28ST TEATH STW_SO_ST TEATH
08SW100005 · aHD_IMPImprovement
Review and change the licence - reducing available take from 100% above prescribed flow to 10% above prescribed flow. Increase prescribed flow from 0.066 m3/s to 0.091 m3/s. Daily licenced amount increased from 10 Ml/d to 12 Ml/d (which is the maximum capacity of De Lank WTW) but the annual licence remained unchanged. Inclusion of facilitating operational/engineering changes.
De Lank abstraction licence change
Due 2029-30De Lank River
08SW101558 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
MOYLE RD_CSO_PADSTOW
Due 2029-30MOYLE RD_CSO_PADSTOW
08SW101574 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
PADSTOW FORESHORE SPST_PSCSOEO_PADSTOW
Due 2029-30PADSTOW FORESHORE SPST_PSCSOEO_PADSTOW
08SW101575 · aEnvAct_IMP2Improvement
Reduction of spills to meet EnvAct_IMP drivers
PADSTOW HARBOUR SPS_PSCSOEO_PADSTOW
Due 2029-30PADSTOW HARBOUR SPS_PSCSOEO_PADSTOW
08SW102113 · eU_IMP1Improvement
Improve discharge from agglomeration that has crossed 250 and has envirronmental imapct
BLISLAND_STW_BLISLAND
Due 2030-31Lower River Camel

30 of 30 measures shown. A measure whose completion date has passed is shown as Complete; the water company's actual delivery against it is reported to the regulator but not published here.

There is no public change log

The live WINEP spreadsheet is internal, and there is no versioned public comparison or published reasons when a measure is re-dated or dropped. The only way to hold slippage to account is to archive every annual release and diff it yourself.

The 2027 pressure point

Most investigations must complete by 30 April 2027 to feed the 2030–35 programme. That date — not 2030 — is the one to hold: an investigation that slips past it cannot shape the next round of funded schemes.