← Railway Station, Axminster

Spill evidence · River Hub

Railway Station, Axminster

Combined sewer overflow · SBB01014 · feeds AXMINSTER STW
Wet weather

The discharge

Spill day
Tuesday, 9 December 2025
Started
9 Dec 2025, 00:42
Ended
10 Dec 2025, 11:28
Duration
1 day 10 hours
Receiving water
Lower Axe
Parish
Axminster

Rainfall evidence

Daily rainfall at the matched gauge (Raymonds Hill) for the spill day and the days before. A spill is dry when every day in the window is ≤ 0.25 mm.

1-day window: Wet weather3-day window: Wet weather4-day window: Wet weather
DateRainfall
09/12/2025 (spill day)4 mmrain
08/12/202537.1 mmrain
07/12/20256.2 mmrain
06/12/202512.4 mmrain
05/12/202522.9 mmrain

River flow that day: 69.563 m³/s. Verify at the EA rainfall station.

Gauge proximity

Outlet (red) vs matched rain gauge (blue), 3.2 km apart. Closer means the rainfall reading is more representative of the overflow.

Loading map…

Severity & context

Bathing water
Not Applicable
Shellfish water
Not Applicable
Ahead of the works
Yes — the treatment works' own overflow stayed shut that day, so capacity was available. Avoidable.
EA annual return (2025)
68 counted spills · 587 h total
Monitor uptime (2025)
100% operational
Method & provenance. Dry/wet classification is decided by rainfall at the nearest EA gauge — ≤ 0.25 mm on the spill day and each preceding day of the window (how we classify). Spill data: Environment Agency EDM (outlet SBB01014). Rainfall: EA Hydrology gauge 9cbfd7c3-d11f-4a5e-ac4c-99575bf18c86. A dry spill is precautionary evidence of a likely fault, not proof of an offence — we test the rainfall, not the works' flow. Generated by Axe & Lim Data.