Wellington Place Car Park Storm Overflow
Pumping station overflow · DCWW208 · feeds LLANINA (NEW WORKS)
Dry spill
Evidence strength
Medium confidence- ✓ Sustained discharge (≥1 h)
- ✓ Dry across a 4-day antecedent window
The discharge
- Spill day
- Sunday, 13 September 2026
- Started
- 13 Sept 2026, 01:00
- Ended
- 13 Sept 2026, 02:00
- Duration
- 1 hour
- Receiving water
- —
- Community
- New Quay
Rainfall evidence
Daily rainfall at the matched gauge (Rhos Ymryson Raingauge) for the spill day and the days before. A spill is dry when every day in the window is ≤ 0.25 mm.
1-day window: Dry spill3-day window: Dry spill4-day window: Dry spill
| Date | Rainfall | |
|---|---|---|
| 13/09/2026 (spill day) | 0 mm | dry |
| 12/09/2026 | 0 mm | dry |
| 11/09/2026 | 0 mm | dry |
| 10/09/2026 | 0 mm | dry |
| 09/09/2026 | 0 mm | dry |
River flow that day: 0.522 m³/s.
Gauge proximity
Outlet (red) vs matched rain gauge (blue), 12.5 km apart. Closer means the rainfall reading is more representative of the overflow.
Loading map…
Severity & context
- Bathing water
- Not a bathing-water overflow
- Shellfish water
- Not a shellfish-water overflow
- Ahead of the works
- Yes — the treatment works' own overflow stayed shut that day, so capacity was available. Avoidable.
Method & provenance. Dry/wet classification is decided by rainfall at the nearest NRW gauge — ≤ 0.25 mm on the spill day and each preceding day of the window (how we classify). Spill data: Dŵr Cymru Welsh Water live storm overflow feed, read hourly by River Hub (outlet DCWW208). Rainfall: NRW telemetry gauge H062515204. A dry spill is precautionary evidence of a likely fault, not proof of an offence — we test the rainfall, not the works' flow. Generated by Aeron ac arfordir Ceredigion / Aeron and Ceredigion coast Data.